Bannerman Energy's Etango Uranium Project in Namibia is currently in early works construction, with activities tracking in line with budget and schedule, progress at June 2026 includes:

Early works construction activities tracking to overall budget and schedule:

  • Contractor workforce on site exceeds 560 personnel and 1.1 million LTI-free hours achieved on the project to date.

  • Bulk earthworks contract advancing in line with schedule with approx. 92% complete; focus remains the freshwater pond, wet plant terraces and heap leach pad.

  • Production of heap leach drainage aggregate continues to deliver on-spec material, with approx. 29% of total requirement completed.

  • Concrete construction activities continue across key dry plant infrastructure areas, with major processing facilities now beginning to take shape; total of 10,800m3 concrete has been cast, representing approx. 60% of the Phase 1 and 2A packages.

Detailed design and procurement activities on schedule:

  • Civil and mechanical design for dry plant approx. 94% complete and aligned with schedule requirement for issue of construction drawings.

  • Wet plant design also remains aligned with schedule requirement for issue of construction drawings later this year.

Long-term infrastructure and utilities supply activities progressing strongly:

  • Permanent water supply agreement executed with NamWater.

  • Phase 1 of permanent water supply pipeline installation now approx. 87% complete.


0

likes

0

questions

0

company answers

Ask a question


Your question will be visible to everyone.

Investor Q&As

Start the conversation

Ask Bannerman Energy a question about this update.