Etango Uranium Project - June 2026
Bannerman Energy's Etango Uranium Project in Namibia is currently in early works construction, with activities tracking in line with budget and schedule, progress at June 2026 includes:
Early works construction activities tracking to overall budget and schedule:
Contractor workforce on site exceeds 560 personnel and 1.1 million LTI-free hours achieved on the project to date.
Bulk earthworks contract advancing in line with schedule with approx. 92% complete; focus remains the freshwater pond, wet plant terraces and heap leach pad.
Production of heap leach drainage aggregate continues to deliver on-spec material, with approx. 29% of total requirement completed.
Concrete construction activities continue across key dry plant infrastructure areas, with major processing facilities now beginning to take shape; total of 10,800m3 concrete has been cast, representing approx. 60% of the Phase 1 and 2A packages.
Detailed design and procurement activities on schedule:
Civil and mechanical design for dry plant approx. 94% complete and aligned with schedule requirement for issue of construction drawings.
Wet plant design also remains aligned with schedule requirement for issue of construction drawings later this year.
Long-term infrastructure and utilities supply activities progressing strongly:
Permanent water supply agreement executed with NamWater.
Phase 1 of permanent water supply pipeline installation now approx. 87% complete.
0
likes
•
0
questions
•
0
company answers
Ask a question
Your question will be visible to everyone.
Investor Q&As
Start the conversation
Ask Bannerman Energy a question about this update.