Etango Uranium Project - December 2025
Bannerman Energy's Etango Uranium Project in Namibia is currently in construction. Early works construction activities are tracking in line with budget and schedule, progress at December 2025 includes:
Early works construction activities tracking to overall budget and schedule:
Site contractor workforce progressively increased to over 370 personnel.
Bulk earthworks contract progressing well and approx. 51% complete, major focus remains construction of heap leach pads.
Blasting, crushing and screening of heap leach drainage aggregate advancing to schedule and on-spec.
Phase 1 and Phase 2A concrete contracts placed and commenced, with foundations for both primary crusher and stockpile tunnel already poured.
High-Pressure Grinding Rolls (HPGR) tertiary crusher successfully manufactured, transported and delivered to site.
0
likes
•
0
questions
•
0
company answers
Ask a question
Your question will be visible to everyone.
Investor Q&As
Start the conversation
Ask Bannerman Energy a question about this update.