Etango Uranium Project - December 2025

Bannerman Energy's Etango Uranium Project in Namibia is currently in construction. Early works construction activities are tracking in line with budget and schedule, progress at December 2025 includes:

Early works construction activities tracking to overall budget and schedule:

  • Site contractor workforce progressively increased to over 370 personnel.

  • Bulk earthworks contract progressing well and approx. 51% complete, major focus remains construction of heap leach pads.

  • Blasting, crushing and screening of heap leach drainage aggregate advancing to schedule and on-spec.

  • Phase 1 and Phase 2A concrete contracts placed and commenced, with foundations for both primary crusher and stockpile tunnel already poured.

  • High-Pressure Grinding Rolls (HPGR) tertiary crusher successfully manufactured, transported and delivered to site.


0

likes

0

questions

0

company answers

Ask a question


Your question will be visible to everyone.

Investor Q&As

Start the conversation

Ask Bannerman Energy a question about this update.