Etango Expansion Scoping Study Announcement
Released
Released
Announcement PDF
Cautionary Statement: ETANGO-XP / ETANGO-XT PROJECTS SCOPING STUDY
The Etango-XP / Etango-XT Scoping Study referred to in this ASX release has been undertaken for the purpose of initial
evaluation of either: (1) potential expansion to the Etango Project’s throughput to 16 Mtpa (Etango-XP); or (2) potential
extension of the life of mine from the current 15 years to 27 years (at 8 Mtpa throughput) (Etango-XT). It is a preliminary
technical and economic study of these two options to determine the potential viability of an increase in either capacity or
an extension to the life of mine of the Etango Project, which has previously been the subject of a Definitive Feasibility
Study (DFS) in 2022 (including Ore Reserve declaration) at an 8 Mtpa development scale (Etango-8).
The Etango-XP / Etango-XT Scoping Study outcomes, production target and forecast financial information referred to in
this release are based on low accuracy level technical and economic assessments that are insufficient to support the
estimation of Ore Reserves. While each of the modifying factors was considered and applied, there is no certainty of
eventual conversion to Ore Reserves or that the production target itself will be realised. Further exploration and
evaluation work and appropriate studies are required before Bannerman will be in a position to estimate any Ore Reserves
or to provide any assurance of an economic development case. Given the uncertainties involved, investors should not
make any investment decisions based solely on the results of the Scoping Study.
Of the Mineral Resources scheduled for extraction in the Scoping Study production plan, approximately 11.7% are
classified as Measured, 88.3% as Indicated and 0.0% as Inferred. There is a low level of geological confidence
associated with Inferred Mineral Resources, and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production target itself will be realised. Inferred Resources were
excluded from the Scoping Study production schedule. Bannerman confirms that the financial viability of the Etango-XP
and Etango-XT Projects is not dependent on the inclusion of Inferred Resources in the production schedule.
The Mineral Resources underpinning the production target in the Scoping Study have been prepared by a competent
person in accordance with the requirements of the JORC Code (2012). The Competent Person's Statement is found in
Appendix A of this ASX release. For full details of the Mineral Resources estimate, please refer to Bannerman ASX
release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of any
new information or data that materially affects the information included in that release. All material assumptions and
technical parameters underpinning the estimates in that ASX release continue to apply and have not materially changed.
This release contains a series of forward-looking statements. Generally, the words "expect," "potential", "intend,"
"estimate," "will" and similar expressions identify forward-looking statements. By their very nature forward-looking
statements are subject to known and unknown risks and uncertainties that may cause our actual results, performance or
achievements, to differ materially from those expressed or implied in any of our forward-looking statements, which are
not guarantees of future performance. Statements in this release regarding Bannerman's business or proposed business,
which are not historical facts, are forward-looking statements that involve risks and uncertainties, such as Mineral
Resource estimates, market prices of metals, capital and operating costs, changes in project parameters as plans
continue to be evaluated, continued availability of capital and financing and general economic, market or business
conditions, and statements that describe Bannerman's future plans, objectives or goals, including words to the effect that
Bannerman or management expects a stated condition or result to occur. Forward-looking statements are necessarily
based on estimates and assumptions that, while considered reasonable by Bannerman, are inherently subject to significant
technical, business, economic, competitive, political and social uncertainties and contingencies. Since forward-looking
statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties.
Actual results in each case could differ materially from those currently anticipated in such statements. Investors are
cautioned not to place undue reliance on forward-looking statements, which speak only as of the date they are made.
Bannerman has concluded that it has a reasonable basis for providing these forward-looking statements and the forecast
financial information included in this ASX release. This includes a reasonable basis to expect that it will be able to fund
the development of the Etango-XP or Etango-XT Project upon successful delivery of key development milestones and
when required. The detailed reasons for these conclusions are outlined throughout this ASX release and in Appendix B.
While Bannerman considers all of the material assumptions to be based on reasonable grounds, there is no certainty that
they will prove to be correct or that the range of outcomes indicated by the Scoping Study will be achieved.
To achieve the range of outcomes indicated in the Scoping Study, pre-production funding in excess of A$320M is
required. There is no certainty that Bannerman will be able to source that amount of funding when required. It is also
possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of
Bannerman's shares. It is also possible that Bannerman could pursue other value realisation strategies such as a sale,
partial sale or joint venture of the Etango Project. These could materially reduce Bannerman's proportionate ownership of
the Etango Project.
No Ore Reserve has been declared in this Scoping Study. This ASX release has been prepared in compliance with the
current JORC Code (2012) and the ASX Listing Rules. All material assumptions, including sufficient progression of all
JORC modifying factors on which the production target and forecast financial information are based, have been included
in this ASX release.
Page 1 of 6
ASX ANNOUNCEMENT
18 March 2024
ETANGO-XP AND ETANGO-XT SCOPING STUDY
Bannerman Energy Ltd (ASX:BMN, OTCQX:BNNLF, NSX:BMN) (Bannerman or the Company) is
pleased to advise of the completion of a Scoping Study evaluating future higher throughput and
operating life cases for its flagship Etango Uranium Project (Etango) in Namibia. Two future phase
options have been evaluated: a post ramp-up expansion in throughput capacity to 16 Mtpa (EtangoXP) or an extension of operating life to 27 years (Etango-XT).
Bannerman is currently advancing Front End Engineering and Design (FEED), offtake marketing and
strategic financing workstreams on its base case 8 Mtpa Etango development (Etango-8), which was
the subject of a Definitive Feasibility Study (DFS) (refer Bannerman ASX release dated 6 December
2022, Etango-8 Definitive Feasibility Study). Bannerman remains fully committed to the timely
development of Etango-8, which is a highly attractive standalone project. The Scoping Study evaluation
of the Etango-XP and Etango-XT cases has been undertaken to demonstrate the potential technical
and economic viability of subsequent expansion and/or life extension options for Etango post
successful construction and ramp-up of Etango-8.
KEY OUTCOMES
▪ Etango-XP (mine and plant throughput expanded to 16 Mtpa from operational Year 5):
-
LOM U3O8 output of 95.2 Mlbs over 16 years (Etango-8 DFS: 52.6 Mlbs over 15 years)
-
Annual average U3O8 output (post plant expansion) of 6.7 Mlbs (Etango-8: 3.5 Mlbs)
-
Expansion phase capex of US$325M (Etango-8: zero)
-
LOM average all-in-sustaining cash cost (AISC) of US$42.5/lb U3O8 (Etango-8:
US$38.1/lb)
▪ Etango-XT (life extension with mine and plant throughput maintained at 8 Mtpa):
-
LOM U3O8 output of 95.2 Mlbs over 27 years (Etango-8 DFS: 52.6 Mlbs over 15 years)
-
Annual average U3O8 output of 3.5 Mlbs (Etango-8: 3.5 Mlbs)
-
No expansion phase capex (Etango-8: zero)
-
LOM average AISC of US$45.3/lb U3O8 (Etango-8: US$38.1/lb)
▪ All Etango-8 cost estimates (including pre-production capex of approx. US$320M) remain
materially unchanged; increased opex estimates associated with Etango-XP / XT are
predominantly driven by higher requisite strip ratio
Key Financial Outcomes: Etango-8, -XP and -XT Projects
Key Financial Metrics
Etango-8
Etango-XP
Etango-XT
Uranium price (US$/lbs U3O8)
65
65
80
95
65
80
95
Free cashflow (post-tax) (US$M)
695
939
1,804
2,669
984
1,847
2,711
Pre-tax IRR (%)
21.0
20.8
32.2
41.3
22.8
33.5
42.4
Post-tax IRR (%)
17.0
16.9
26.6
34.0
18.6
27.4
34.4
Pre-tax NPV8 from base FID (US$M)
369
445
1,017
1,590
411
862
1,314
Post-tax NPV8 from base FID (US$M)
209
250
615
974
241
526
809
Bannerman Energy Ltd
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008
PO Box 1973, Subiaco, Western Australia 6008
W bannermanenergy.com
T +61 8 9381 1436
E info@bmnenergy.com
▪ Future feasibility work on Etango-XP and Etango-XT options capable of ready fasttracking given all resource drilling, geotechnical, metallurgical, process and
environmental workstreams already complete as part of previous DFS-level project
evaluation.
Commenting on the Etango-XP / XT Scoping Study results, Bannerman Chief Executive Officer,
Gavin Chamberlain, said:
"Developing the world-class Etango Project at an initial 8 Mtpa throughput scale is our core focus. We
undertook the Etango-XP / XT Scoping Study in order to demonstrate the ready technical and financial
viability of expanding or extending our base case Etango operation following its successful construction
and ramp-up.
"As evidenced by the announced outcomes, the Scoping Study has categorically demonstrated this
further growth optionality. In short, the long-term scalability of the world-class Etango resource remains
highly robust under the base case Etango-8 approach to initial project development.”
Bannerman Executive Chairman, Brandon Munro, added:
“I am delighted that we have more formally demonstrated the longer-term optionality delivered by our
large-scale Etango uranium resource. While the XP and XT cases are readily viable at our base case
Etango-8 DFS price assumption of US$65/lb, their economics are clearly supercharged in higher price
scenarios.
“As such, what the Scoping Study emphatically evidences is the significant underlying value residing
in Etango’s huge in-ground leverage to, and scalability with, higher uranium price outlooks. The ability
to enact either the XP or XT plans, post-delivery of the initial Etango-8 development, affords
Bannerman substantial real option value across a range of long-term uranium price outcomes.”
Key Physical Parameters: Etango-8, -XP and -XT Projects
Key Physical Parameters
Unit
Etango-8
Etango-XP
Etango-XT
Life of mine (LOM)
years
15
16
27
Long-term mine and process throughput
Mtpa
8
16
8
Total ore mined and processed
Mt
113.5
210.2
210.2
Total waste mined
Mt
253.3
670.3
670.3
Average strip ratio
x
2.2
3.2
3.2
Average uranium head grade
ppm U3O8
240
234
234
Forecast uranium recovery
%
87.8%
87.8%
87.8%
LOM uranium production
Mlbs U3O8
52.6
95.2
95.2
3.5
4.8
Average annual uranium production
Mlbs U3O8 pa
3.5
5.9 / 6.7^
Peak annual uranium production
Mlbs U3O8 pa
4.1
7.8
^ 5.9 Mlbs pa is LOM average Etango-XP output and 6.7 Mlbs pa is average Etango-XP output post expansion completion
This ASX release was authorised on behalf of the Bannerman Energy Board by:
Brandon Munro, Executive Chairman
Contact
Investors:
Media:
Brandon Munro
Executive Chairman
T: +61 8 9831 1436
info@bmnenergy.com
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Page 3 of 6
Forecast Mine Schedule
Forecast Process Schedule
Forecast Uranium Output
Page 4 of 6
Key Financial Outcomes: Etango-8, -XP and -XT Projects
Key Financial Outcomes
Unit
Etango-8
Etango-XP
Etango-XT
Price Inputs
LOM average uranium price
US$/lb U3O8
65
80
65
80
95
65
80
95
N$
17.56
17.56
17.56
17.56
17.56
17.56
17.56
17.56
NPV8 (post-tax, real basis, ungeared)
US$M
209
436
250
615
974
241
526
809
NPV8 (pre-tax, real basis, ungeared)
US$M
369
725
445
1,017
1,590
411
862
1,314
IRR (post-tax, real basis, ungeared)
%
17.0%
24.6%
16.9%
26.6%
34.0%
18.6%
27.4%
34.4%
US$/N$
Valuation, Returns and Key Ratios
IRR (pre-tax, real basis, ungeared)
%
21.0%
30.0%
20.8%
32.2%
41.3%
22.8%
33.5%
42.4%
Years
4
3
6
5
4
4
3
2
x
1.2
2.3
1.4
3.2
5.0
1.3
2.7
4.1
Sales revenue (gross)
US$M
3,421
4,210
6,187
7,615
9,043
6,187
7,615
9,043
Total operating costs
US$M
1,952
1,978
3,967
4,014
4,060
4,219
4,265
4,312
Project operating surplus
US$M
1,469
2,232
2,220
3,601
4,982
1,968
3,349
4,731
Pre-production + expansion capex
US$M
(317)
(317)
(642)
(642)
(642)
(318)
(318)
(318)
LOM sustaining capex
US$M
(51)
(51)
(82)
(82)
(82)
(96)
(96)
(96)
Project net cashflow (pre-tax)
US$M
1,099
1,863
1,495
2,877
4,258
1,554
2,936
4,317
Project net cashflow (post-tax)
US$M
695
1,172
939
1,804
2,669
984
1,847
2,711
Mining
US$/t mat.
2.4
2.4
2.4
2.4
2.4
2.5
2.5
2.5
Mining
US$/lb U3O8
16.3
16.3
21.8
21.8
21.8
23.1
23.1
23.1
Processing
US$/t ore
5.4
5.4
6.5
6.5
6.5
6.9
6.9
6.9
Processing
US$/lb U3O8
14.9
14.9
14.4
14.4
14.4
15.3
15.3
15.3
G&A and closure costs
US$/lb U3O8
2.6
2.6
2.1
2.1
2.1
2.6
2.6
2.6
Product transport, port, freight, conversion
US$/lb U3O8
1.2
1.2
1.2
1.2
1.2
1.2
1.2
1.2
Total cash operating cost (ex-roy./levies)
US$/lb U3O8
35.0
35.0
39.6
39.6
39.6
42.2
42.2
42.2
Royalties and export levies
US$/lb U3O8
2.1
2.6
2.1
2.6
3.1
2.1
2.6
3.1
Total cash operating cost (excl. sust. capital)
US$/lb U3O8
37.1
37.6
41.7
42.2
42.7
44.3
44.8
45.3
All-in-sustaining-cost (AISC)
US$/lb U3O8
38.1
38.6
42.5
43.0
43.5
45.3
45.8
46.3
Payback period (post-tax, from first prod.)
Pre-tax NPV / Pre-production capex
Cashflow Summary
Unit Cash Operating Costs
Page 5 of 6
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development business listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1. In December 2022, a Definitive
Feasibility Study (DFS)2 was completed on the Etango-8 Project, confirming to a definitive-level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput (for average annual output of 3.5 Mlbs U3O8). Bannerman previously completed
advanced studies on an alternative, larger development pathway – a 20Mtpa development at Etango.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore. All environmental approvals have been received for the
proposed Etango mine and external mine infrastructure, based on a 12-year environmental baseline.
Bannerman was awarded the Mining Licence for Etango in December 2023 and is progressing all key project
workstreams towards a targeted positive Final Investment Decision (FID) in parallel with strengthening
uranium market fundamentals.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda. The Bannerman team has
ample direct experience in the development, construction and operation of uranium projects in Namibia, as
well as extensive links into the downstream nuclear power industry.
Bannerman has long established itself as an Environmental, Social and Governance (ESG) leader in the
uranium and nuclear energy sector. It is also a leader within Namibia on social development and community
engagement and exercises best-practice governance in all aspects of its business. This was recently
recognised with receipt of the 2023 African Mining Indaba’s ESG Award for Community Engagement.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
Page 6 of 6
APPENDIX A - CONSENT FORM OF COMPETENT PERSON
According to the requirements of ASX Listing Rules 5.6, 5.22 and 5.24 and Clause 9 of the JORC Code 2012 Edition (Written
Consent Statement)
Etango Uranium Project, Namibia – Etango-XP and Etango-XT Scoping Study Report ("Technical
Report") for Bannerman Energy Limited
Etango-XP and Etango-XT Scoping Study
March 2024
STATEMENT
The results of the Scoping Study with the Technical Report titled "Etango-XP and Etango -XT Scoping
Study" dated 13 March 2024 (the "Technical Report") by Bannerman Resources Limited ("Bannerman")
on the Etango Uranium Resource that underpins the production targets are based on, and fairly represent,
information and supporting documentation reviewed by Mr Werner K Moeller. Mr Werner K Moeller is
since 2016 a Director and Principal Mining Engineer of Qubeka Mining Consultants CC ("Qubeka") based
in Klein Windhoek, Namibia. Before 2016, he was a director and principal mining engineer at VBKom
Consulting Engineers (Pty) Ltd, based in Centurion, South Africa. He is an active member or fellow of the
following professional associations:
• South African Institute of Mining and Metallurgy - MSAIMM nr. 704793.
• Australian Institute of Mining and Metallurgy - FAusIMM nr. 329888.
• Canadian Institute of Mining, Metallurgy and Petroleum – MCIM nr. 708163;
Mr Werner K Moeller is a graduate of the University of Pretoria, South Africa and holds a Bachelor's
degree, majoring in Mine Engineering (2001) and an Honours degree, majoring in Industrial Engineering
(2002). He is practising as a mining engineer and has practised his profession continuously since 2002.
I, Werner Klaus Moeller, herewith confirm that I am the Competent Person for this Technical Report as
declared in the above document and that:
• I have read and understood the requirements of the 2012 Edition of the Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code, 2012 Edition).
• I am a competent person as defined by the JORC Code, 2012 Edition, and I have more than five
years of experience relevant to the style of mineralisation and type of deposit described in this
Technical Report and the activity for which I am accepting responsibility.
• I am a Fellow of The Australasian Institute of Mining and Metallurgy.
• I have reviewed the Report to which this Consent Statement applies.
His relevant experience for the purpose of this Technical Report review is:
• Operational experience in numerous mines in Africa and Namibia, including three years at the
Rössing Uranium Mine.
• Mine planning and study experience on a large number of uranium projects, including the Rössing
Uranium Mine, Husab Uranium Mine and Forsys Metals Corp's Norasa Project.
Page 1 of 2
• Project manager for numerous feasibility studies all over Africa.
He has sufficient experience relevant to the style of mineralisation and type of deposit under consideration
and to the activity he is undertaking to qualify as a Competent Person, as defined in the 2012 Edition of the
Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Neither Mr
Werner K Moeller nor Qubeka has a direct or indirect financial interest in, or association with Bannerman,
the properties and tenements reviewed in this statement, apart from standard contractual arrangements for
reviewing this Technical Report and other previous independent consulting work. Qubeka has been paid a
fee for the time spent reviewing this Technical Report. The present and past arrangements for services
rendered to Bannerman do not compromise Qubeka's independence with respect to this declaration. He
has disclosed to the reporting company the entire nature of the relationship between myself and the
Company, including any issue that investors could perceive as a conflict of interest.
I verify that the Technical Report is based on and fairly and accurately reflects the information in the
Technical Report in the form and context in which it appears.
CONSENT
I consent to the release of documentation relating to the Technical Report and this Consent Statement by
the directors of Bannerman Energy Limited.
[Signature of Competent Person]
Dated at Windhoek, Namibia, on 13th March 2024.
Werner Moeller BEng(Mining), BEng(Hons)(Industrial), MSAIMM, FAusIMM, MCIM
Professional Membership: Fellow, Australian Institute of Mining & Metallurgy (AusIMM) | Membership Number: 329 888
Director Qubeka Mining Consultants CC
Appendix B - Scoping Study Report
Bannerman Mining Resources (Namibia) (Pty) Ltd
1587P2 Etango XP and XT Concept Study
Report
Scoping Study Report
Document No. 1587P2-0000-BA10-RPT-0001
Revision: F
B
2024-01-30
C
2024-02-19
D
2024-03-08
E
2024-03-09
Issued for Client Review
Issued for Client
Contributions
Updated for Client
Approval
Issued for Client Approval
PJC
BVH
PJC
BVH
PJC
BVH
PJC
BVH
Approved
Rev
Date
Description
Prepared
Reviewed
Per
approvals
matrix
Per
approvals
matrix
Client
Revision History Tracking Record*
Item
Page
Section
Comments
THIS PAGE INTENTIONALLY LEFT BLANK.
* Use after Rev. 0
Page 2 of 90
Table of Contents
1.
Executive Summary ......................................................................................... 9
1.1
Project Overview ....................................................................................................................... 9
1.2
OPEX Summary ...................................................................................................................... 11
1.3
CAPEX Summary .................................................................................................................... 12
1.4
Economic Analysis ................................................................................................................. 12
1.5
Risk and Opportunities ........................................................................................................ 16
1.6
Conclusions and Recommendations .............................................................................. 16
2.
Study Team ..................................................................................................... 17
3.
Tenement Status ............................................................................................ 17
4.
Geology and Mineral Resource Estimate .................................................... 18
4.1
Local Geology ......................................................................................................................... 18
4.2
Mineral Resource ................................................................................................................... 19
5.
Mining Studies ............................................................................................... 21
5.1
Pit Optimisation & Design ................................................................................................. 21
5.1
Mining Method and Schedule .......................................................................................... 26
5.2
Fleet Selection ........................................................................................................................ 29
5.3
Geotechnical............................................................................................................................ 30
5.4
Hydrogeological .................................................................................................................... 31
6.
Processing ....................................................................................................... 31
6.1
Metallurgical Test work ....................................................................................................... 31
6.2
Process Flowsheet ................................................................................................................. 31
6.3
Mass Balances ......................................................................................................................... 34
6.4
Processing Assumptions ..................................................................................................... 34
6.5
Proposed 16Mt/a Expansion Process Plant Layout ................................................... 35
7.
Infrastructure ................................................................................................. 36
7.1
On-site Infrastructure........................................................................................................... 36
7.2
Power ......................................................................................................................................... 37
7.3
Water ......................................................................................................................................... 37
Page 3 of 90
7.4
7.3.1
Fresh Water Supply ............................................................................................................................. 37
7.3.1
Construction Water Supply ............................................................................................................. 38
Roads ......................................................................................................................................... 39
7.4.1
C28Main Road ...................................................................................................................................... 39
7.4.2
Site Access Road .................................................................................................................................. 39
7.5
Port and Acid Handling Infrastructure ........................................................................... 40
8.
Environmental and Social ............................................................................. 41
8.1
Overview ................................................................................................................................... 41
8.2
Summary of ESIA ................................................................................................................... 42
8.3
Environmental and Social Management System ....................................................... 42
9.
Operating Cost ............................................................................................... 43
9.1
Mining Operating Cost ........................................................................................................ 43
9.2
Process Plant Operating Cost ........................................................................................... 45
9.3
G&A and External Infrastructure Operating Cost ...................................................... 48
10.
Capital Cost ..................................................................................................... 50
10.1
Mining Capital Cost .............................................................................................................. 50
10.2
Process Plant ........................................................................................................................... 51
10.3
10.2.1
Basis of Estimate .................................................................................................................................. 51
10.2.2
Process Plant Capital Cost Summary ........................................................................................... 53
Owner’s Cost ........................................................................................................................... 54
10.3.1
External Infrastructure ....................................................................................................................... 54
10.3.2
G&A Owner’s Cost .............................................................................................................................. 57
10.3.3
Other Owner’s Cost ............................................................................................................................ 58
10.3.4
Contingency ........................................................................................................................................... 59
10.3.5
Owner’s Pre-Production Capital Cost Summary ..................................................................... 60
10.3.6
Staying-in-Business Costs-Process Plant ...........