Quarterly Activities Report
Released
Released
Announcement PDF
Quarterly Activities Report
FOR THE PERIOD ENDED 30 SEPTEMBER 2024
Bannerman Energy Ltd (ASX: BMN, OTCQX: BNNLF, NSX: BMN) (Bannerman or the Company)
is pleased to report on the continued progress of its Etango Uranium Project (Etango) during the
quarter, with significant developments across a range of key workstreams. The Company is advancing
towards a targeted Final Investment Decision (FID) on Etango, supported by a strong cash position
and favourable market conditions.
HIGHLIGHTS
•
Etango development progressed in accordance with Bannerman's gated 'phased
greenlight' construction strategy.
•
First phase of early works, including access road and water supply construction,
completed safely, on time and within budget.
•
Completion of A$85 million two-tranche equity placement facilitated next phase
of early construction works, key contract awards and long-lead orders:
‒
Key 24-month bulk earthworks and construction power contracts
awarded.
‒
Tertiary crusher (HPGR) order placed and manufacture commenced; plant
detailed design work advancing.
•
Finance and offtake marketing workstreams advancing, including evaluation of
project/corporate debt as well as potential offtake and strategic JV opportunities.
•
Substantial quarter-end cash balance of A$95.7 million, with zero debt.
•
Long-term uranium price closed the quarter at a 15-year high of US$82/lb U3O8,
reflecting ongoing positive market outlook and building utility contract demand.
Bannerman Executive Chairman, Brandon Munro, commented:
"The September quarter marked another period of strong progress for Bannerman as we advance
Etango towards a Final Investment Decision.
“Our strong balance sheet and flexible approach to project development enables us to exercise a gated
approach to Etango development, with phased green lighting of various construction works in line with
advancement across broader project workstreams and financial capacity. The success of our recent
A$85 million equity placement delivered us the ability to move into the next phase of early construction
and long-lead order activities at Etango, thereby maintaining critical path timelines.
“The Etango financing process also progressed during the quarter, as we compared a range of
conventional and strategic funding opportunities that reflect the growing interest in long-term uranium
supply. Our strong financial position allows us to take the appropriate time in this area to ensure the
optimal overall funding mix is delivered for the benefit of all our stakeholders.
“The unprecedented positive energy at World Nuclear Association’s annual Symposium in September
reflects the further firming of long-term contract markets as the sector enters a seasonally strong
period. We look forward to accessing the benefits of our careful exercise of patience at this early stage
in the uranium cycle.”
Bannerman Energy Ltd
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008
PO Box 1973, Subiaco, Western Australia 6008
W bannermanenergy.com
T +61 8 9381 1436
E info@bannermanenergy.com
Etango Uranium Project (Bannerman 95%)
Early works and long lead construction activities
The first two early works contracts approved for Etango – the construction water supply and site access
road – were completed in July; safely, on time and on budget. Bannerman thanks its local contract
partners for their strong and safe performance on these projects.
Figure 1: Completed access road to Etango site, showing the junction to the C28 tar highway
Following the completion of these early works, and the financial capacity delivered by the Company’s
recent equity raising, development of Etango has rapidly transitioned to the next phase of long lead
order and critical path contract awards. This approach is in-line with Bannerman’s gated, ‘phased
greenlight’ approach to the construction of Etango.
The construction power contract has also been placed in-line with the project schedule. Further, the
construction contract for the roads within the Etango Mining Licence (ML) area has been awarded and
works are progressing ahead of schedule.
The contract for the blasting, crushing, and placing of the drainage layer on the Etango heap leach pad
has been tendered and is being adjudicated. Bannerman has also issued the instruction to commence
manufacture of the High-Pressure Grinding Rolls (HPGR) tertiary crusher.
Negotiations on final supply contracts for both permanent water and power supply have progressed inline with requirements and are now at an advanced stage. Detailed design work on the Etango process
plant continues, as are procurement activities securing engineering details for key mechanical
equipment.
The Environmental Clearance Certificate (ECC) for the Etango ML was also recently renewed for a
customary three year extension until 31 August 2027.
Page 2 of 9
Figure 2: New culvert installed over the existing water supply pipelines
Figure 3: Completed construction water reservoir delivering 700m3 storage volume
Page 3 of 9
As previously announced, the Etango bulk earthworks contract has been awarded. This award is inline with the existing project schedule and is planned to be a 24-month contract (which lies on the
critical path schedule).
Figure 4: Bulk earthworks contractor’s camp, within Etango ML boundary, being established following contract award
Financing
The Etango financing process sees Bannerman evaluating and progressing various funding sources,
including project/corporate debt as well as potential offtake and joint venture opportunities with
strategic counterparties who can add value to Etango. As previously advised, Azure Capital and
Vermilion Partners (both global affiliates of French financial services institution, Natixis) are advising
on and assisting with the execution of the optimal funding mix for Etango.
This process is progressing well and has been informed at every stage by Bannerman’s commitment
to establishing a highly robust financial base for Etango. The final choice of funding mix will be a direct
function of the cost of various alternatives weighed against respective requisite levels of offtake
coverage (and key terms), covenants and security.
Bannerman’s recent equity raising is a strong enabler in delivering sufficient runway for the Company
to undertake a fulsome process, delivering the best opportunity to arrive at the optimal funding mix.
Offtake Marketing
Bannerman’s product marketing strategy continues to be driven by a detailed understanding of utility
requirements and preferences. The Company continues to actively engage with a broad range of
utilities, financial institutions, traders, and other key market participants. This ongoing interaction
ensures a thorough understanding of term contracting dynamics, pricing mechanisms, and other
essential contractual terms and conditions.
It is readily observable that yellowcake term contract liquidity and pricing has continued to build
Page 4 of 9
momentum in recent months, notwithstanding the retraction in spot yellowcake and uranium equities
pricing over the same period.
Bannerman’s well-established position with respect to offtake marketing is that it will preserve the longterm underlying value of Etango by only committing to contracting its planned uranium output on price
(and other terms) that are considered representative of long-term market fundamentals and producer
opportunity. Although the market is developing positively, current term contract conditions have not yet
fully aligned with these criteria.
A natural extension of Bannerman’s position to offtake contracting is the necessary degree of patience
required to maximise the leverage of Etango to long-term uranium market fundamentals. The
exercising of this patience means that Bannerman has elected to expand its projected window for a
targeted positive Final Investment Decision (FID) on Etango into 2025.
The Company is able to comfortably undertake such a strategy as a result of its recent equity raising
and robust cash balance. This enables ongoing execution of the ‘phased greenlight’ approach to
Etango development, whilst maintaining a watch-and-act approach to offtake contracting during this
period.
Corporate
A$85 Million Placement Settled
On 28 June 2024, Bannerman announced that it had successfully raised A$85 million (before costs)
through the receipt of binding commitments for a two-tranche placement to new and existing
institutional and sophisticated investors at A$3.30 per share:
▪
Tranche 1, consisting of 22,927,010 new shares valued at approximately A$75.7 million, was
allocated and settled on 4 July 2024.
▪
Tranche 2, comprising 2,830,765 new shares valued at approximately A$9.3 million, was
granted shareholder approval at a general meeting held on 12 August 2024, with settlement
occurring on 14 August 2024.
The raised funds are to be allocated towards developing the Etango-8 Project, including detailed
design, early works including construction infrastructure and bulk earthworks, and procuring long-lead
items.
Strong Liquidity
Bannerman’s cash balance at 30 September 2024 was A$95.7 million (30 June 2024: A$24.0 million).
The Company has no debt (other than typical creditor balances) or convertible instruments.
Total exploration and development expenditure for the quarter was A$7.6 million, which included FEED
and early works on the Etango Project.
Management continues to maintain a focus on prudent cost control and project timeliness. For the
purpose of item 6.1 of Appendix 5B, the aggregate payments during the quarter to related parties
(totalling A$212,061) were comprised of directors’ fees and salary.
Cancellation and Issue of Securities
During the quarter, the Company issued and cancelled the following securities:
▪
Issue of Ordinary Fully Paid Shares: A total of 25,757,775 fully paid ordinary shares were
issued, consisting of:
Page 5 of 9
o
Tranche 1 of Institutional Placement: 22,927,010 shares issued on 4 July 2024.
o
Tranche 2 of Institutional Placement: 2,830,765 shares issued on 14 August 2024,
following shareholder approval at the General Meeting held on 12 August 2024.
▪
Vesting of Performance Rights: 9,047 fully paid ordinary shares issued upon conversion of
unlisted performance rights in accordance with the terms of the Employee Incentive Plan (EIP)
and Non-Executive Director Share Incentive Plan (NEDSIP).
▪
Conversion of Performance Rights: 9,047 performance rights were converted into fully paid
ordinary shares.
Issued Securities
At the date of this report, the Company has 178,613,558 fully paid ordinary shares, 2,141,468 unlisted
performance rights, and 2,045,164 unlisted options on issue. The performance rights and options are
subject to various performance targets and continuous employment periods.
Uranium Market
During the September 2024 quarter, geopolitical developments, supply constraints, and growing
interest in nuclear energy investments shaped the uranium market.
The long-term contract price increased to US$82.00/lb U3O8, up from US$80.00/lb, building upon its
15-year high and continuing to reflect the growing confidence in nuclear energy's future role in meeting
global energy demands. The U3O8 spot price closed the quarter at US$82.25/lb U3O8, down from
US$85.00/lb at the end of June 2024. The average price for the quarter was US$82.00/lb.
The price changes were driven mainly by continued uncertainties regarding Kazatomprom’s logistical
challenges and potential restrictions on Russian uranium exports. Kazatomprom, the world’s largest
uranium producer, is facing logistical difficulties due to sanctions on its usual transport routes through
Russia. Using an alternative route through Azerbaijan has increased transportation costs and created
delays, limiting Kazatomprom's supply to European markets. These constraints added pressure on
global uranium supply chains.
In addition to these logistical issues, the potential for future restrictions on Russian uranium exports
further exacerbated supply concerns. As a result of both these factors, utilities are increasingly
targeting long-term uranium supply agreements, prioritising supply security amid geopolitical
uncertainties.
The quarter also saw rising demand for nuclear energy from data centres, AI industries, and other
energy-intensive sectors. Notably, Microsoft signed a 20-year power agreement with Constellation to
restart Three Mile Island Unit 1 by 2028, reinforcing the tech industry’s growing reliance on nuclear
energy. Similarly, Oracle announced plans to power a new data centre using three small modular
reactors (SMRs). Google further confirmed its exploration of nuclear power to support its large-scale
data centres, driven by increasing electricity demands due to the rise of artificial intelligence and other
digital technologies.
These announcements underscored nuclear energy's role as a reliable, low-carbon energy source,
especially for industries requiring stable, continuous power.
During Climate Week in New York City, held in late September, 14 leading banks – Barclays, BNP
Paribas, Citi, Deutsche Bank, Goldman Sachs, HSBC, ING, JPMorgan Chase, Morgan Stanley,
MUFG, Santander, Société Générale, Standard Chartered, and UBS – confirmed their commitment to
financing nuclear projects, aligning with global decarbonisation goals and recognising nuclear power’s
role in providing reliable, low-emission electricity.
This collective backing from the financial sector highlights the growing importance of nuclear energy in
Page 6 of 9
the global transition to a low-carbon economy and establishes a pathway for deployment of capital at
scale to meet unprecedented demand growth signals. These institutions align their investment
strategies with net-zero goals, acknowledging nuclear power’s ability to complement intermittent
renewable energy and meet rising electricity demand.
The World Nuclear Association held its annual Symposium in September, which highlighted a string of
positive sector developments to a sell-out forum of professionals from within and outside the nuclear
power industry. The subsequent announcements during Climate Week further cemented nuclear
energy's expanding role in the future energy landscape, driven by both increasing industrial demand
and significant financial support.
This ASX release was authorised on behalf of the Bannerman Board by:
Brandon Munro, Executive Chairman
16 October 2024
Contact
Investors:
Media:
Brandon Munro
Executive Chairman
T: +61 8 9831 1436
info@bmnenergy.com
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of the Company, the Directors, and the management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting, or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
Page 7 of 9
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development business listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1. In December 2022, a Definitive
Feasibility Study (DFS)2 was completed on the Etango-8 Project, confirming to a definitive-level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput (for average annual output of 3.5 Mlbs U3O8). In March 2024, a scoping study3
demonstrated the capacity to expand annual production to 6.7 Mlbs U3O8.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore. All environmental approvals have been received for the
proposed Etango mine and external mine infrastructure, based on a 12-year environmental baseline.
Bannerman was awarded the Mining Licence for Etango in December 2023 and is progressing all key project
workstreams towards a targeted positive Final Investment Decision (FID) in parallel with strengthening
uranium market fundamentals.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda. The Bannerman team has
ample direct experience in the development, construction and operation of uranium projects in Namibia, as
well as extensive links into the downstream nuclear power industry.
Bannerman has long established itself as an Environmental, Social and Governance (ESG) leader in the
uranium and nuclear energy sector. It is also a leader within Namibia on social development and community
engagement and exercises best-practice governance in all aspects of its business. This was recently
recognised with receipt of the 2023 African Mining Indaba’s ESG Award for Community Engagement.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
3. Refer to Bannerman’s ASX release dated 18 March 2024, Etango-XP and Etango-XT Scoping Study.
Page 8 of 9
Forward Looking Statements
The information in this announcement is not intended to guide any investment decisions in Bannerman
Energy Ltd. This material contains certain forecasts and forward-looking information, including possible
or assumed future performance, costs, production levels or rates, reserves and resources, prices and
valuations and industry growth and other trends. Such forecasts and information are not a guarantee
of future performance and involve many risks and uncertainties, as well as other factors. Actual results
and developments may differ materially from those implied or expressed by these statements and are
dependent on a variety of factors. The Company believes that it has a reasonable basis for making the
forward-looking statements in the announcement, based on the information contained in this and
previous ASX announcements.
Bannerman is not aware of any new information or data that materially affects the information included
in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply
and have not materially changed.
Competent Person’s Statement
The information in this announcement as it relates to Exploration Results is based on, and fairly
represents, information and supporting documentation prepared by Mr Marthinus Prinsloo. Mr Prinsloo
is a full-time employee of Bannerman Energy Ltd and is a Member of the Australasian Institute of
Mining and Metallurgy (AusIMM). Mr Prinsloo has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration, and to the activities, which he is undertaking.
This qualifies Mr Prinsloo as a “Competent Person” as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ and a Qualified
Person as defined by Canadian National Instrument 43-101. Mr Prinsloo consents to the inclusion in
this announcement in the form and context in which it appears. Mr Prinsloo holds shares and
performance rights in Bannerman Energy Ltd.
Listing Rule 5.3.3 Tenement Schedule:
BANNERMAN ENERGY LTD CONSOLIDATED BASIS
SCHEDULE OF INTERESTS IN MINING TENEMENTS
Project
Mining tenements
held
Location of
tenements
Beneficial %
interest at end of
the quarter
Change in the
quarter
Etango
Mining Licence
(ML) 250
Namibia
95%
-
Page 9 of 9