Quarterly Activities Report
Released
Released
Announcement PDF
Quarterly Activities Report
FOR THE PERIOD ENDED 30 JUNE 2023
Bannerman Energy Ltd (ASX:BMN, OTCQX:BNNLF, NSX:BMN) (Bannerman or the Company) is
pleased to report on a quarter in which it continued to progress Front End Engineering and Design for
the 8Mtpa development1 of its flagship Etango Uranium Project in Namibia (Etango), whilst maintaining
fiscal discipline and strategic patience as uranium sector dynamics continue to build.
HIGHLIGHTS
▪
▪
Etango Project:
‒
Front End Engineering and Design (FEED) progressing to schedule.
‒
Mining Licence (ML) application advancing with grant expected during current quarter.
‒
Targeted positive Final Investment Decision (FID) during H1 CY2024.
Appointment of highly accomplished nuclear industry executive, Ms Olga
Skorlyakova, as VP Market Strategy.
‒
Establishment of this role forms an integral part of building Bannerman’s long term
uranium marketing program, and further enhancing broader organisational readiness
and capability.
▪
Substantial cash balance of A$42.6M at quarter end and zero debt.
▪
Uranium spot prices rose during the period, finishing the quarter above US$56/lb.
▪
Sector fundamentals continue to strengthen, with utilities prioritising
enrichment/conversion services contracting during H1 2023. Term contracting of
U3O8 is expected to accelerate during the current half.
Bannerman Managing Director and Chief Executive Officer, Brandon Munro, said:
“I am delighted to welcome Olga to the Bannerman team. As we continue to advance Etango towards
targeted development and uranium production, Olga’s expertise deepens our nuclear industry profile
and further builds our capability on the uranium marketing front.
“The FEED work on Etango is progressing well and has presented multiple opportunities for further
project de-risking and optimisation. We continue to advance FEED and other key workstreams on
Etango, while maintaining strong balance sheet liquidity and strategic patience with respect to
progressive satisfaction of key external factors – including the anticipated near-term grant of the Etango
ML and strengthening uranium term contract liquidity and pricing dynamics.”
1
. Bannerman advised of the completion of a Definitive Feasibility Study (DFS) for an 8Mtpa development of its flagship Etango Uranium
Project in Namibia in an ASX announcement dated 6 December 2022. Bannerman is not aware of any new information or data that
materially affects the information included in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply and have not materially changed.
Of the Mineral Resources scheduled for extraction and recovery in the DFS production plan, 100% are classified as Measured or
Indicated. Bannerman confirms that there are no Inferred Resources included in the DFS production schedule.
Bannerman Energy Ltd
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008
PO Box 1973, Subiaco, Western Australia 6008
W bannermanenergy.com
T +61 8 9381 1436
E info@bannermanenergy.com
Etango Uranium Project (Bannerman 95%)
All key workstreams advancing
Front End Engineering and Design (FEED) work on the Etango Project is on schedule. Additional
metallurgical testing was done during April 2023 to confirm some of the metallurgical parameters for
the design work. The mine design is complete and the Request For Quotations (RFQs) for the mining
contract will be finalised in Q3 2023. The 3D modelling of the plant is progressing on schedule, with
focus on the front-end crushing circuits. The design and tender process of temporary power and water
supply, as well as the access road to the mine site, is complete. The design of the permanent water
supply line and electrical transmission line are on schedule.
All Environmental Clearance Certificates and National Heritage consents have now been received and
the Etango Project is fully permitted in this regard. The Etango Mining Licence (ML) application was
submitted to the Ministry of Mines and Energy (MME) in August 2022. Following submission of the
DFS in December 2022, Bannerman has been working with the MME towards targeted grant of the
ML.
Parallel uranium marketing and project finance workstreams for Etango are also in progress, as
previously announced.
Targeted FID
As noted above, Bannerman is progressing all critical workstreams with respect to the development of
the Etango Project. Key external factors that remain subject to satisfaction for a positive Final
Investment Decision (FID) are grant of the Etango ML and uranium term contract market
fundamentals/pricing strengthening further.
Bannerman has been working constructively with the MME and understands that it is in an advanced
stage of consideration of the Etango ML application. Grant of the ML is anticipated during the current
quarter and will represent satisfaction of the final non-market prerequisite to proceed with
comprehensive offtake contracting and project financing activities.
While underlying uranium market dynamics continue to firm, utilities have demonstrated a greater focus
on contract enrichment and conversion activities through 2023. Against that backdrop, yellowcake term
contract liquidity and pricing has also improved, but remains restrained in comparison.
Bannerman’s well-established position with respect to offtake marketing is that the company will not
diminish the long-term underlying value of Etango by committing to contracting of its planned uranium
output on price (and other terms) that it considers unrepresentative of long-term market fundamentals
and producer opportunity.
As such, Bannerman’s strategy remains unchanged – advancing FEED and other key workstreams on
Etango to deliver currency of quotation and overall development shovel-readiness, while maintaining
strong balance sheet liquidity and strategic patience with respect to satisfaction of key external factors.
This approach is advancing Etango towards, uranium market permitting, a targeted positive Final
Investment Decision during H1 CY2024. Construction of the Etango Project is expected to take
approximately 34 months (including detailed design).
Corporate
Vice President Market Strategy appointment – Ms Olga Skorlyakova
On 29 June 2023, the Company announced the appointment of Ms Olga Skorlyakova to the role of
Vice President Market Strategy, responsible for the Company’s nuclear industry marketing strategy
and uranium sales. The establishment of this role, and the appointment of an executive with Olga’s
professional background and expertise, forms an integral part of the build and roll-out of Bannerman’s
long term uranium marketing program for Etango.
Olga is a highly accomplished nuclear industry executive with a deep professional experience base
ranging from business development in the nuclear fuel sector to sale of enrichment services. Her
breadth of sector understanding is coupled with an extensive network of relationships formulated over
Page 2 of 7
her 15 years working within the nuclear and uranium industries.
For the past six years Olga has been the Senior Project Manager at the London-based peak industry
body, World Nuclear Association (WNA). This role saw her lead the WNA Fuel Report Working Group
and publish the WNA’s seminal biennial industry publication, The Nuclear Fuel Report: Global
Scenarios for Demand and Supply Availability.
Prior to this Olga was Head of Business Development, Americas, for TENEX, which is one of the
world’s major suppliers of enriched uranium products. Prior to that, she held the role of Deputy Chief
Representative for French integrated nuclear power group, AREVA (now Orano), across business
development and marketing activities in Russia and CIS.
Olga is a UK citizen based in London. She holds a Master of Arts (English) and an Executive MBA
(Antwerp Management School).
Strong quarter end cash balance of A$42.6 million
Bannerman’s cash balance at 30 June 2023 was A$42.6 million (31 March 2023: A$45.3 million). The
Company has no debt (other than typical creditor balances) or convertible instruments.
Total exploration and development expenditure for the quarter was A$2.2 million, which included Front
End Engineering and Design (FEED) work on the Etango Project.
Management continues to maintain a focus on prudent cost control and project timeliness. For the
purpose of item 6.1 of the Appendix 5B, the aggregate payments during the quarter to related parties
(totalling A$218,030) were comprised of directors’ fees and salary.
Cancellation and issue of securities during the quarter
The Company advised during the quarter that the following securities in Bannerman were cancelled or
issued:
151,500 unlisted Zero Exercise Price Options (ZEPO) were issued in accordance with the
EIP and NEDSIP as approved by shareholders on 16 November 2022.
Issued securities
At the date of this report, the Company has on issue 150,510,660 fully paid ordinary shares, 2,779,118
performance rights and 1,735,166 unlisted options. The performance rights and options are subject to
various performance targets and continuous employment periods.
Uranium Market
Uranium spot prices rose through the quarter, opening at US$50.75/lb and gaining 10.7% by the end
of the quarter. In the second week of June, prices peaked at US$57.75/lb, reaching their highest level
since April 2022, when prices declined following the Russian invasion of Ukraine. Despite slight easing
over the remainder of June, spot prices remained above US$56.00/lb by the end of the quarter, closing
at US$56.20/lb.
Underpinned by increasing concerns about the long-term security of nuclear fuel supply, current tight
primary supply capacities, and anticipated demand growth, uranium prices are expected by most
commentators to continue rising. This positive trend is in stark contrast to broader commodity markets,
which have generally declined over the quarter, reflecting increased global interest rates and slowing
economic growth around the world.
At the end of May, a published Bloomberg news article suggested that Namibia was considering greater
nationalised ownership of mineral and petroleum projects. With Namibia containing one of the richest
uranium reserves in the world, supply of uranium from the country forms an integral part of the global
nuclear fuel cycle. Following publication of the article, the Namibian Ministry of Mines and Energy
clarified that the government has no intention of seeking any additional ownership stake from existing
mineral or petroleum license holders, and remains committed to upholding the sanctity of contract. The
Namibian Minister of Mines and Energy, Hon Tom Alweendo, reiterated this stance during his speech
at the African Energy Forum in Paris in early June.
Page 3 of 7
The quarter has seen continued public policy shift towards the incorporation of nuclear energy as a
key baseload energy source of the future, with governments worldwide implementing policies to
develop new reactors, extend the life of existing reactors, and incentivise investment in emerging
technologies, such as Small Modular Reactors (SMRs).
In Japan, parliament passed a bill allowing ageing nuclear reactors to operate beyond the 60-year limit,
resulting in two more reactor restarts at Takahama Nuclear Power Plant by Kansai Electric Power
Company. In South Korea, a construction restart of Shin Hanul Nuclear Power Plant units 3&4 was
announced following the administration's strategy to ensure “restoration of the country’s nuclear power
plant ecosystem”.
Construction is underway on a total of 59 reactors worldwide. In Indonesia, Norway, the Philippines,
and Sri Lanka, plans are currently being considered to introduce nuclear power plants, including both
conventional and SMRs, into their national energy mixes.
In conjunction with reactor development and extension plans, the June quarter has also seen
policymakers place particular focus on the security of the long-term nuclear fuel supply. To this end,
the West is looking to re-examine Russia’s role as one of the world’s top energy exporters, with several
significant public policy announcements made during the quarter, including:
-
The United States (U.S.), France, Japan, Canada, and the United Kingdom formed the Nuclear
Fuel Alliance, with a particular focus on dislodging Russian influence over the international
nuclear energy market.
-
The U.S. Senate Environment and Public Works Committee passed the bipartisan Accelerating
Deployment of Versatile, Advanced Nuclear for Clean Energy (ADVANCE) Act, prohibiting the
possession or ownership of enriched uranium owned, controlled, or organized by Russia or
China (unless the Nuclear Regulatory Commission specifically authorises it). Note, this
legislation must be passed by the House and Senate and approved by President Biden to be
implemented.
These developments, and the intensification of security concerns regarding long-term nuclear fuel
supply, has resulted in utilities reviewing their inventory policies and stock-building, in an effort to
ensure operational sustainability and reliability. Whilst no further actions have been taken yet, and a
ban on nuclear fuel imports transited through Russia was not included in the European Union’s 11th
Package of Russian Sanctions (following the invasion of Ukraine), utilities continue to assess risks to
the supply of nuclear fuel in the current geopolitical environment.
For U3O8 contracting, 2022 was the highest uranium contracting year in a decade. Despite this, the
first half of 2023 has seen some inertia, as utilities look to secure enrichment/conversion services first
before progressing uranium contracts. As a result, U3O8 contracting is anticipated to accelerate in the
next 6-12 months.
According to the Energy Information Administration’s 2022 Uranium Marketing Annual Report, the
maximum anticipated market requirements for the US civilian owner/operators at the end of 2022 is
402 Mlbs U3O8e over the next 10 years. Nearly 45% of these requirements (179 Mlbs U3O8e) remain
unfilled.
In line with shifting public policy, further improvement in public sentiment towards the adoption of
nuclear energy is being witnessed around the world. In the U.S., a recent national survey found that
76% of respondents favour nuclear energy due to its affordability, reliability, efficiency, and
environmental benefits, and 71% of respondents agreed that more nuclear power plants should be
built in the future. In Finland, 68% of the population supports nuclear power, citing climate change as
the predominant reason, whilst in Estonia, 75% of the population is reported to support the construction
of a nuclear power plant.
Overall, these developments indicate that long-term uranium market fundamentals remain strong.
This ASX release was authorised on behalf of the Bannerman Board by:
Brandon Munro, Managing Director and Chief Executive Officer
28 July 2023
Page 4 of 7
Contact
Investors:
Media:
Brandon Munro
CEO and Managing Director
T: +61 8 9831 1436
info@bmnenergy.com
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond
the control of the Company, the Directors and the management. The Directors cannot and do not give any assurance that the results,
performance or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
2
Preliminary Economic Assessment on the Lofdal Rare Earths Project Namibia dated October 1, 2014 authored by David S. Dodd, B.
Sc (Hon) FSAIMM - The MDM Group, South Africa, Patrick J.F. Hannon, M.A.Sc., P.Eng. and William Douglas Roy, M.A.Sc., P.Eng.
- MineTech International Limited, Canada, Peter Roy Siegfried, MAusIMM (CP Geology) and Michael R. Hall, B.Sc (Hons), MBA,
MAusIMM, Pr.Sci.Nat, MGSSA - The MSA Group, South Africa. The PEA should not be considered to be a pre-feasibility or feasibility
study, as the economics and technical viability of the Project has not been demonstrated at this time. The PEA is preliminary in nature
and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied
to them that would enable them to be categorised as Mineral Reserves. Furthermore, there is no certainty that the PEA will be realised.
A NI 43-101 compliant report entitled Preliminary Economic Assessment on the Lofdal Heavy Rare Earths 2B-4 Project, Namibia (“the
Report”) will be filed by NMI on SEDAR within 45 days of NMI’s announcement of 3 October 2022. SGS Canada Inc. is the principal
author under the supervision of Michael Archer who is a Qualified Person in accordance with NI 43-101 – Standards of Disclosure for
Mineral Projects. Sections of the Report dealing with property description and location, accessibility, climate, local resources,
infrastructure and physiography, history, geological setting and mineralisation, deposit types, exploration, drilling, sample preparation,
analyses and security and data verification were completed by The MSA Group under the supervision of Jeremy Witley, (BSc Hons,
MSc (Eng.)) and Swinden Geoscience Consultants under the supervision of Scott Swinden, (Ph.D P.Geo), who are Qualified Persons
in accordance with NI 43-101 – standards of disclosure for mineral projects. The section of the Report dealing with mineral resource
estimates was completed by The MSA Group under the supervision of Jeremy Witley, (BSc Hons, MSc (Eng.)) Sections of the Report,
dealing with mining methods and mine capital and operating costs were completed by SGS Canada under the supervision of Bill van
Breugel (BaSc Hons, P.Eng.) who is a Qualified Person in accordance with NI 43-101 – Standards of Disclosure for Mineral Projects.
Sections of the Report, dealing with mining design and schedules were completed by BBMC RSA under the supervision of Johann
Hager (BEng Hons, MEng Mining, P.Eng.) who is a Qualified Person in accordance with NI 43-101 – Standards of Disclosure for
Mineral Projects. Each of Michael Archer, Jeremy Witley, Scott Swinden, Johann Hager and Bill van Breugel reviewed and approved
the technical disclosure of the NMI press release dated 3 October 2022. Rainer Ellmies, PhD, MScGeol, EurGeol, AusIMM and Vice
President of Namibia Critical Metals Inc., is the Company’s Qualified Person and has reviewed and approved the geological data in
that press release.
3
Page 5 of 7
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development company listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia. Bannerman has long established itself as an
Environmental, Social and Governance (ESG) leader in the uranium and nuclear energy sector.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1. In December 2022, a Definitive
Feasibility Study (DFS)2 was completed on the Etango Project, confirming to a definitive-level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput. Bannerman previously completed advanced studies on an alternative, larger
development pathway - a 20Mtpa development at Etango was the subject of a DFS completed in 2012 and
a DFS Optimisation Study completed in 20153.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda.
Etango has environmental approvals for the proposed mine and external mine infrastructure, based on a
12-year environmental baseline. Bannerman is a leader within Namibia on social development and
community engagement and exercises best-practice governance in all aspects of its business.
The Bannerman team has ample direct experience in the development, construction and operation of
uranium projects in Namibia, as well as extensive links into the downstream nuclear power industry.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
3. Refer to Bannerman’s ASX release dated 11 November 2015, Outstanding DFS Optimisation Study Results.
Page 6 of 7
Forward Looking Statements
The information in this announcement is not intended to guide any investment decisions in Bannerman
Energy Ltd. This material contains certain forecasts and forward-looking information, including possible
or assumed future performance, costs, production levels or rates, reserves and resources, prices and
valuations and industry growth and other trends. Such forecasts and information are not a guarantee
of future performance and involve many risks and uncertainties, as well as other factors. Actual results
and developments may differ materially from those implied or expressed by these statements and are
dependent on a variety of factors. The Company believes that it has a reasonable basis for making the
forward looking statements in the announcement, based on the information contained in this and
previous ASX announcements.
Bannerman is not aware of any new information or data that materially affects the information included
in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply
and have not materially changed.
Competent Person’s Statement
The information in this announcement as it relates to Exploration Results is based on, and fairly
represents, information and supporting documentation prepared by Mr Marthinus Prinsloo. Mr Prinsloo
is a full time employee of Bannerman Energy Ltd and is a Member of the Australasian Institute of
Mining and Metallurgy (AusIMM). Mr Prinsloo has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration, and to the activities, which he is undertaking.
This qualifies Mr Prinsloo as a “Competent Person” as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ and a Qualified
Person as defined by Canadian National Instrument 43-101. Mr Prinsloo consents to the inclusion in
this announcement in the form and context in which it appears. Mr Prinsloo holds shares and
performance rights in Bannerman Energy Ltd.
Listing Rule 5.3.3 Tenement Schedule:
BANNERMAN ENERGY LTD CONSOLIDATED BASIS
SCHEDULE OF INTERESTS IN MINING TENEMENTS
Project
Mining tenements
held
Location of
tenements
Beneficial %
interest at end of
the quarter
Change in the
quarter
Etango
Mineral Deposit
Retention Licence
(MDRL) 3345
Namibia
95%
-