Investor Presentation
Released
Released
Announcement PDF
Investor
Presentation
INVESTOR PRESENTATION, MARCH 2024
ASX: BMN, OTCQX:BNNLF AND NSX:BMN
CAUTIONARY STATEMENT
Important notices
Of the Mineral Resources scheduled for extraction and recovery in the Etango-8 Definitive Feasibility Study (DFS) production plan, 100% are classified as Measured or Indicated. Bannerman Energy Ltd
(Bannerman, the Company) confirms that there are no Inferred Resources included in the DFS production schedule.
The Mineral Resources underpinning the Ore Reserve and production target in the DFS have been prepared by a competent person in accordance with the requirements of the JORC Code (2012). The
Competent Person’s Statement is found overleaf. For full details of the Mineral Resources estimate, please refer to the ASX release dated 6 December 2022, “Etango-8 Definitive Feasibility Study”.
Bannerman confirms that it is not aware of any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning the
estimates in that ASX release continue to apply and have not materially changed.
This release contains a series of forward-looking statements. Generally, the words "expect," “potential”, "intend," "estimate," "will" and similar expressions identify forward-looking statements. By their
very nature forward-looking statements are subject to known and unknown risks and uncertainties that may cause our actual results, performance or achievements, to differ materially from those
expressed or implied in any of our forward-looking statements, which are not guarantees of future performance. Statements in this release regarding Bannerman’s business or proposed business, which
are not historical facts, are forward-looking statements that involve risks and uncertainties, such as Mineral Resource estimates, Ore Reserve estimates, market prices of metals, capital and operating
costs, changes in project parameters as plans continue to be evaluated, continued availability of capital and financing and general economic, market or business conditions, and statements that describe
Bannerman’s future plans, objectives or goals, including words to the effect that Bannerman or management expects a stated condition or result to occur. Forward-looking statements are necessarily
based on estimates and assumptions that, while considered reasonable by Bannerman, are inherently subject to significant technical, business, economic, competitive, political and social uncertainties
and contingencies. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties. Actual results in each case could differ
materially from those currently anticipated in such statements. Investors are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date they are made.
Bannerman has concluded that it has a reasonable basis for providing these forward-looking statements and the forecast information included in this ASX release. This includes a reasonable basis to
expect that it will be able to fund the development of Etango-8 upon successful delivery of key development milestones as and when required. The detailed reasons for these conclusions are outlined in
the ASX release dated 6 December 2022, “Etango-8 Definitive Feasibility Study”, in the section titled, “Funding pathway”. While Bannerman considers all of the material assumptions to be based on
reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the DFS will be achieved.
To achieve the range of outcomes indicated in the DFS, pre-production funding in excess of US$320M will likely be required. There is no certainty that Bannerman will be able to source that amount of
funding when required. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of Bannerman’s shares. It is also possible that Bannerman
could pursue other value realisation strategies such as a sale, partial sale or joint venture of the Etango-8 Project. These could materially reduce Bannerman’s proportionate ownership of the Etango
Project.
For full details regarding the Etango-8 DFS refer to Bannerman ASX release dated 6 December 2022, “Etango-8 Definitive Feasibility Study”. Bannerman confirms that all material assumptions
underpinning the production target and forecast financial information within the DFS continue to apply and have not materially changed.
2
FORWARD LOOKING AND COMPETENT PERSON STATEMENTS
Important notices
Forward Looking Statements
Competent Person Statement
This presentation includes various forward looking statements which are identified by the use of forward looking words such as
“may”, “could”, “will”, “expect”, “believes”, “intend”, “plan”, “estimate”, “anticipate”, “continue”, and “guidance”, or other similar
words and may include, without limitation statements regarding plans, strategies and objectives of management, anticipated
production or construction commencement dates and expected costs or production outputs. Statements other than statements of
historical fact may be forward looking statements. Bannerman believes that it has reasonable grounds for making all statements
relating to future matters attributed to it in this presentation.
Mineral Resources
Forward looking statements inherently involve known and unknown risks, uncertainties and other factors that may cause the
Company’s actual results, performance and achievements to differ materially from any future results, performance or
achievements. Relevant factors may include, but are not limited to, changes in commodity prices, foreign exchange fluctuations
and general economic conditions, increased costs and demand for production inputs, the speculative nature of exploration and
project development, including the risks of obtaining necessary licences and permits and diminishing quantities or grades of
resources or reserves, political and social risks, changes to the regulatory framework within which the Company operates or may
in the future operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel,
industrial relations issues and litigation. Investors should note that any reference to past performance is not intended to be, nor
should it be, relied upon as a guide to any future performance.
Forward looking statements are based on the Company and its management’s good faith assumptions relating to the financial,
market, regulatory and other relevant environments that will exist and affect the Company’s business and operations in the future.
The Company does not give any assurance that the assumptions on which forward looking statements are based will prove to be
correct, or that the Company’s business or operations will not be affected in any material manner by these or other factors not
foreseen or foreseeable by the Company or management or beyond the Company’s control.
Although the Company attempts to identify factors that would cause actual actions, events or results to differ materially from those
disclosed in forward looking statements, there may be other factors that could cause actual results, performance, achievements or
events not to be anticipated, estimated or intended, and many events are beyond the reasonable control of the Company.
Accordingly, readers are cautioned not to place undue reliance on forward looking statements. Actual results, values, performance
or achievements may differ materially from results, values, performance or achievements expressed or implied in any forward
looking statement. None of Bannerman, its officers or any of its advisors make any representation or warranty (express or implied)
as to the accuracy or likelihood of fulfilment of any forward looking statement, or any results, values, performance or achievements
expressed or implied in any forward looking statement except to the extent required by law.
The information in this release relating to the Mineral Resources (November 2021) of the Etango Project is based on a resource
estimate compiled or reviewed by Mr Ian Glacken, Principal Consultant at Snowden Optiro Pty Ltd and a Fellow of the
Australasian Institute of Mining and Metallurgy. Mr Glacken has sufficient experience that is relevant to the style of mineralisation
and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in
the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”, is an
independent consultant to Bannerman and a Qualified Person as defined by Canadian National Instrument 43-101. Mr Glacken
consents, and provides corporate consent for Snowden Optiro Pty Ltd, to the inclusion in this release of the matters based on his
information in the form and context in which it appears.
Ore Reserves
The information in this release relating to the Ore Reserves (June 2022) of the Etango-8 DFS Project is based on information
compiled or reviewed by Mr Werner K Moeller, a Director since 2016 of Qubeka Mining Consultants CC based in Klein Windhoek,
Namibia. Prior to 2016 Mr. Moeller was a Director of VBKom Consulting Engineers (Pty) Ltd based in Centurion, South Africa from
2008. Mr Moeller is a Member of The Australasian Institute of Mining and Metallurgy (MAusIMM nr. 329888), a Member of the
South African Institute of Mining and Metallurgy (MSAIMM nr. 704793) and a Member of the Canadian Institute of Mining,
Metallurgy and Petroleum (MCIM nr. 708163). He graduated from the University of Pretoria, South Africa and holds a Bachelor
degree, majoring in Mine Engineering (2001) and an Honours degree, majoring in Industrial Engineering (2002). Mr Moeller is a
practising mining engineer, having practiced his profession continuously since 2002, and has sufficient experience relevant to the
style of mineralisation and types of deposits under consideration and to the activity which is being undertaken to qualify him as a
Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves”. He has read and understood the requirements of the 2012 Edition of the Australasian Code for
Reporting of Exploration Results and the Technical Report has been prepared in compliance with that code. Mr Moeller consents
to the filing of this release with any stock exchange and other regulatory authority and any publication by them for regulatory
purposes, including electronic publication in the public company files on their websites accessible by the public. Mr Moeller
furthermore does not have nor does he expect to receive a direct or indirect interest in the Etango property of Bannerman, and he
does not beneficially own, directly or indirectly, any securities of Bannerman or any associate or affiliate of such company. Mr
Moeller consents to the inclusion in this release of the matters based on his information in the form and context in which it
appears.
Forward looking statements in this release are given as at the date of issue only. Subject to any continuing obligations under
applicable law or any relevant stock exchange listing rules, in providing this information the Company does not undertake any
obligation to publicly update or revise any of the forward looking statements or to advise of any change in events, conditions or
circumstances on which any such statement is based.
3
ABOUT BANNERMAN ENERGY
The leading nextgeneration uranium
supplier of choice
Our flagship Etango Project is one of the world’s
largest, most advanced uranium development assets.
Benefiting from its location in Namibia, a highly
established uranium production powerhouse.
Strongly de-risked through extensive drilling, technical
evaluation and process demonstration plant.
Fully permitted with a clear pathway to development.
Readily positioned to capitalise on the unfolding
uranium market recovery.
4
THE LEADING NEXT-GENERATION URANIUM SUPPLIER OF CHOICE
One of the world’s largest,
most advanced uranium
development assets
Globally large-scale resource endowment
225 Mlbs U3O8
Etango-only Resources1,3
Mineral Resource Estimate (55ppm U3O8 cut-off)1,3
Resource category
Tonnes
(Mt)
Grade
(ppm U3O8)
Contained
U3O8 (Mlb)
Measured
32.4
201
14.3
Indicated
345.7
195
148.5
Inferred
140.6
200
62.0
Total
518.6
197
224.9
Mineral Resource Estimate (100ppm U3O8 cut-off)2,3
Resource category
Tonnes
(Mt)
Grade
(ppm U3O8)
Contained
U3O8 (Mlb)
Measured
26.6
226
13.3
Satellite deposits within trucking distance
Indicated
276.9
223
136.4
Inferred
112.5
230
57.1
Scale plus scalability
Total
416.1
225
206.8
59.9 Mlbs Etango Ore Reserve3
1. November 2021 Mineral Resource Estimate JORC (2012) reported within a US$75 pit shell, 55ppm U3O8 cut-off
2. November 2021 Mineral Resource Estimate JORC (2012) reported within a US$75 pit shell, 100ppm U3O8 cut-off
3. For full details of the Mineral Resources and Ore Reserve estimate and disclosures, please refer to ASX release
dated 6 December 2022, “Etango-8 Definitive-Feasibility Study”. The Mineral Resources underpinning the Ore
Reserve have been prepared by a competent person in accordance with the requirements of the JORC Code
(2012). The Competent Person’s Statement(s) are found in the section of this ASX release titled “Competent
Person’s Statement(s)”. Bannerman confirms that it is not aware of any new information or data that materially
affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed
THE LEADING NEXT-GENERATION URANIUM SUPPLIER OF CHOICE
Located in Namibia, a stable,
highly established uranium
production powerhouse
Recognised tier-one supplier to global utilities
45-years of uranium production and export
Three large-scale uranium mines; Top 3 global producer
Excellent infrastructure - port, rail and power
Clear mining code and strong rule of law
Strong community and social support for uranium
6
THE LEADING NEXT-GENERATION URANIUM SUPPLIER OF CHOICE
Systematically de-risked through the uranium cycle
BULL MARKET
Bannerman
lists on the
ASX
BEAR MARKET
Etango 20
NI 43-101
Mtpa Scoping
report
Study released released
BULL MARKET
Etango
20 Mtpa
DFS delivered
Etango DFS
optimisation
study
Nano-filtration
study
Brandon Munro
appointed CEO
and MD
Commenced
Etango scaling
study
Etango heap
leach derisking
Demonstration
plant test work
complete
Etango
processing
optimisation study
Maiden Resource
declared
2005
Etango 20 Mtpa
PFS delivered
2010
Environmental
approval granted
Unfolding
uranium
resurgence
Etango-8
Scoping Study
released
Etango-8 PFS
delivered
Etango-XP
Etango-XT
Scoping Study
released
Etango-8
Mining Licence
granted
Etango-8 DFS
delivered
2015
2020
2025
Daily spot U3O8 price (US$/lb): high US$143/lb, low US$18/lb
7
THE LEADING NEXT-GENERATION URANIUM SUPPLIER OF CHOICE
Upper Scenario for Uranium Supply and Demand (Mlbs U3O8)
The uranium market resurgence is unfolding now
520
455
390
325
Utility contract demand building
Persistent
cumulative supply
gap of approx.
150 million lbs
U3O8
• Rising confidence in medium- and long-term global
uranium demand growth picture
• Emerging Small Modular Reactor (SMR)
technology driving further new demand additions
Fragile supply environment apparent
• Lost decade of uranium exploration and project
development post Fukushima
260
• Producers struggling to match ramping demand,
turning to tight spot market to fill gaps
195
Energy transition powering further growth
130
• National decarbonisation and zero emissions
strategies rapidly building momentum globally
65
• Increasing government support for nuclear power
as a “middle ground” baseload energy source
2022
2024
2026
2028
2030
2032
2034
2036
2038
2040
Supply forecast: Combined U3O8 capacity (existing, restarted, under development, planned and prospective mines + secondary supply)
Demand forecast: Reactor requirements
Supply gap
Source: World Nuclear Association, Nuclear Fuel Report 2023 – 2040
8
THE LEADING NEXT-GENERATION URANIUM SUPPLIER OF CHOICE
Corporate snapshot
CAPITAL STRUCTURE
ASX share price (15 Mar 2024)
PRICE (ASX: BMN)
A$2.99
A$4.00
A$1.19 – A$3.99
A$3.00
Shares on issue
153.0 M
A$2.00
Market capitalisation
A$457 M
12 month share price range
Options and performance rights
4.0 M
Average daily volume (ASX 1-month)
0.6 M
Cash (31 Dec 2023)
Debt
A$35.2 M
Zero
SHARE REGISTER
A$1.00
A$0.00
Ma r 23
Ma y 23
Jul 23
Sep 23
Nov 23
Jan 24
Ma r 24
BOARD OF DIRECTORS
Executive Chairman
Brandon Munro
Chief Executive Officer
Gavin Chamberlain
Lead Independent NED
Alison Terry
Institutional
23%
Independent NED
Ian Burvill
Board and management
4%
Independent NED
Mike Leech
Other (including OTCQX)
73%
Independent NED
Clive Jones
9
INVESTMENT HIGHLIGHTS
The leading nextgeneration uranium
supplier of choice
1
Strong technical and commercial viability demonstrated via Etango-8 DFS
2
Conventional production, technically de-risked through pilot-plant operation
3
Fully permitted with all environmental approvals and Mining Licence in place
4
Long track record of responsibility and sustainability
5
Skilled delivery team with deep Namibian uranium expertise
6
Delivering significant, lasting positive social and environmental impact
10
INVESTMENT HIGHLIGHTS
1. Strong technical and
commercial viability
demonstrated via
Etango-8 DFS
• Conventional open pit mining and heap leach
processing at 8Mtpa throughput
• Informed by vast body of previous technical
work across resource drilling, geotechnical,
metallurgical and environmental studies
15 years
113.5 Mt
Initial mine life
Total ore throughput
8 Mtpa
240 ppm
Throughput capacity
Average U3O8 head grade
87.8%
3.5 Mlb
Processing yield
Average U3O8 output p.a.
US$35/lb
US$317M
Cash opex excl royalties
Pre-production capex
For full details of the Etango-8 DFS, please refer to ASX release dated 6 December 2022, “Etango-8 Definitive-Feasibility Study”. Bannerman confirms that it is not aware of any new information or
data that materially affects the information included in that release. All material assumptions and technical parameters underpinning the estimates in that ASX release continue to apply and have
11
not materially changed
INVESTMENT HIGHLIGHTS
1. Outstanding Etango-8 upside price leverage
Upside DFS case
US$80/lb US$1,172M US$435M
LOM U3O8 price
Further enhanced
project economics
2.9 years
24.6%
Net cashflow (post-tax)
Post-tax NPV8%
Payback (post-tax)
Post-tax IRR
69%
108%
-1.1
+7.6%
US$695M
US$209M
4.1 years
17.0%
Net cashflow (post-tax)
Post-tax NPV8%
Payback (post-tax)
Post-tax IRR
Base DFS case
US$65/lb
LOM U3O8 price
For full details of the Etango-8 DFS, please refer to ASX release dated 6 December 2022, “Etango-8 Definitive-Feasibility Study”. Bannerman confirms that it is not aware of any new information or
data that materially affects the information included in that release. All material assumptions and technical parameters underpinning the estimates in that ASX release continue to apply and have
12
not materially changed
INVESTMENT HIGHLIGHTS
1.Further in-ground
leverage realisable via
subsequent throughput
expansion or life extension
• World-class scale Etango deposit delivers
substantial real option value via scalability with
higher uranium price outcomes
ETANGO-XP
ETANGO-XT
(EXPANDED SCALE)
(EXTENDED LIFE)
Average 6.7 Mlbs U3O8
output pa (post exp.)
Average 3.5 Mlbs U3O8
output pa
16 years
27 years
Mine life
Mine life
• Two future phase development options
•
•
Etango-XP: Mine and plant throughput expanded
to 16 Mtpa from operational Year 5 (expansion
capital US$325M)
LOM U3O8 output
95.2Mlbs
Etango-XT: Life extension with mine and plant
throughput maintained at 8 Mtpa
For full details of the Etango-XP and Etango-XT Scoping Study, please refer to ASX release dated 18 March 2024, “Etango-XP and Etango-XT Scoping Study”. Bannerman confirms that it is not
aware of any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning the estimates in that ASX
13
release continue to apply and have not materially changed
INVESTMENT HIGHLIGHTS
1. Further upside price leverage from Etango-XP / XT
US$95/lb
LOM U3O8 price
Enhancement from Etango-8
(US$80/lb)
US$80/lb
LOM U3O8 price
Enhancement from Etango-8
(US$80/lb)
US$80/lb
LOM U3O8 price
US$2,669M
US$2,771M
US$974M
US$809M
41.3%
34.4%
Net cashflow (post-tax)
Post-tax NPV8%
Post-tax IRR
+128%
+136%
+124%
+86%
+16.7%
+9.8%
US$1,804M
US$1,847M
US$615M
US$526M
26.6%
27.4%
Net cashflow (post-tax)
Post-tax NPV8%
Post-tax IRR
+54%
+58%
+41%
+21%
+2.0%
+2.8%
US$1,172M
US$435M
24.6%
Net cashflow (post-tax)
Post-tax NPV8%
Post-tax IRR
Etango-XP
Etango-XT
Etango-XP
Etango-XT
Etango-8
For full details of the Etango-8 DFS and Etango-XP / XT Scoping Study, please refer to ASX releases dated 6 December 2022, “Etango-8 Definitive-Feasibility Study” and 18 March 2024, “EtangoXP and Etango-XT Scoping Study”. Bannerman confirms that it is not aware of any new information or data that materially affects the information included in those releases. All material
14
assumptions and technical parameters underpinning the estimates in those ASX releases continues to apply and has not materially changed.
INVESTMENT HIGHLIGHTS
2. Conventional production,
technically de-risked
through pilot-plant operation
Proven flow sheet
Fifteen years of technical de-risking
Industrial-scale Heap Leach
Demonstration Plant operated at
site from 2015 validates flowsheet
and key metallurgical parameters
15
INVESTMENT HIGHLIGHTS
3. All environmental approvals received
CONSENT TYPE
DATE
ECC 01608 (Etango Project)
Achieved 5 July 2012
ECC 02193 (linear infrastructure)
Achieved 26 July 2011
ECC 01529 (HL demonstration plant)
Achieved 7 September 2014
ECC APP 3078 (permanent water pipeline)
Achieved 10 August 2022
ECC APP 3058 (electrical transmission line)
Achieved 23 August 2022
ECC 2300287 (temporary water pipeline)
Achieved 16 April 2023
Strongly supported
By our local communities and the
Namibian government
16
INVESTMENT HIGHLIGHTS
3. Mining Licence awarded,
with Etango now fully
permitted ahead of FID
Etango Mining Licence awarded
December 2023
Early-stage works contracts
commenced
Maintains target construction schedule
17
INVESTMENT HIGHLIGHTS
4. Long track record of responsibility and sustainability
Environmental
baseline monitoring
since 2008
Mondesa
Youth
Opportunities
SRT
Conservancy
Tourism
Education
TOSCO
Hospitality
Association of
Namibia
Trade
scholarships
(NIMT)
Peer reviewed, IFC
compliant ESIA and
management plans
2023 African Mining Indaba
ESG Forum Award for
Community Engagement
Early
Learner
Assistance
Program
CTAN
Active
role
modelling
Rehabilitation
of Namib
desert
NCE
Chamber of
Mines
World best
practices
NUA
One
Economy
Foundation
World
Nuclear
Association
PeerReviewed
ESIA
18
INVESTMENT HIGHLIGHTS
5. Skilled delivery team with deep Namibian expertise
Gavin Chamberlain | Chief Executive Officer
Brandon Munro | Executive Chairman
• 30+ years in project development/construction & contracting
• Former Regional Director, Mining for AMEC (now Wood plc)
and COO of Kore Potash.
• Project Director for construction of Husab uranium mine.
• 25+ years’ transactional and capital markets experience as
a corporate lawyer and resources executive.
• Member of World Nuclear Association Advisory Council,
former Chair of WNA Nuclear Fuel Demand Working Group.
• Lived in Namibia for 5+ years.
Steve Herlihy | Chief Financial Officer
Mike Leech | Chairman – Namibia, NED
• 30+ years’ experience as chartered accountant in resources
• Previously global Financial Controller for BHP Iron Ore and
member of BHP’s strategy and innovation leadership team.
• Deep commercial, M&A, project finance experience.
• 30+ years’ mining industry experience, Rio Tinto.
• Deep Namibian uranium operating experience including
former roles as MD and CFO at Rössing Uranium.
• Former President of Namibian Chamber of Mines.
Olga Skorlyakova | Vice President, Market Strategy
Werner Ewald | Managing Director - Namibia
• 25+ years in BD, sales and market strategy in international
business environments (UK, Europe, USA, Asia).
• Executive roles within nuclear fuel sector over last 15 years.
• Co-author, editor, and head of publication of WNA’s “The
Nuclear Fuel Report: Global Scenarios for Demand and
Supply Availability”.
• 30+ years’ experience in uranium, diamond, coal mining.
• Prior to joining BMN was Manager Mining, Rössing Uranium.
• Namibian born Electrical Engineer based in Swakopmund.
19
INVESTMENT HIGHLIGHTS
6. Significant positive social and environmental impact
3.5
Mlbs
U3O8
per annum,
enough to power
7-8 large nuclear
reactors
25
million
tonnes
of coal displaced by our
production
64
million
tonnes
of carbon emissions avoided
from nuclear power using
our uranium (if displacing
coal-fired power)
760
Namibian
jobs
represents well-paid direct jobs and
a multiplier effect of up to
5,000 indirect jobs
20
THE PATHWAY AHEAD
A clearly defined route for
Etango development
Early site works commenced –
1
Access road
enabling controlled access to mine site
with minimal impact on surrounding area
construction access and water supply
US$2M contract awarded to
Namibian-based contractor1
Strategic finance and offtake
workstreams progressing in parallel
2
Temporary water
pipeline
ensures sufficient water onsite when
main earthworks and civil contracts
commence
1) Fully-funded from Bannerman cash reserves of A$37.3 million as of 30 November 2023
21
THE PATHWAY AHEAD
Roadmap to production
Contracting
• ML granted
• Conclude offtake
agreements
Financing
• Obtain strategic /
project financing
• Complete FID
• Long-lead works
• Mine and infrastructure
• HL + IX process plant
Construction
Production
3.5 Mlbs U3O8 p.a. output
6.7 Mlbs p.a.
Expansion
Development phase
Production phase
FID potential expansion
2023
2024
2025
2026
2027
2028
2029
2030
22
THE LEADING NEXT-GENERATION URANIUM SUPPLIER OF CHOICE
Social leadership in the future
supply of raw materials for
emissions free power
Established, unaligned supply jurisdiction
World-class asset and delivery team
Powering a decarbonised future
23
CONTACT DETAILS
Brandon Munro
Executive Chairman
Email: info@bmnenergy.com
Phone: +61 8 9381 1436
@BannermanEnergy
@Brandon_Munro
24