Quarterly Activities Report
Released
Released
Announcement PDF
Quarterly Activities Report
FOR THE PERIOD ENDED 30 SEPTEMBER 2023
Bannerman Energy Ltd (ASX: BMN, OTCQX: BNNLF, NSX: BMN) (Bannerman or the Company)
is pleased to report its progress during the quarter, which saw a sharp rise in the U3O8 spot price and
a positive flow-on effect into capital markets. With this backdrop, the Company continued to advance
the Front-End Engineering and Design for its flagship Etango Uranium Project1 in Namibia (Etango)
while focusing on prudent cost control and project timeliness.
HIGHLIGHTS
▪
▪
Etango Project:
‒
Front End Engineering and Design (FEED) is progressing to schedule.
‒
Mining Licence (ML) application advancing with grant expected H2 CY2023.
‒
Targeting positive Final Investment Decision (FID) during H1 CY2024.
Inaugural 2023 Sustainability Report:
‒
ESG credentials and sustainability performance for the fiscal year ended 30 June 2023.
‒
Future Sustainability Plans and Commitments.
‒
Three Core Pillars: People, Planet and Performance.
▪
Substantial cash balance of A$39.9M at quarter end and zero debt.
▪
Uranium spot price continued its rise during the period, finishing the quarter
above US$73/lb.
▪
Global investment in new and extended life reactors continues to strengthen
sector fundamentals as utilities pursue long-term, multi-year supply contracts
that emphasise the importance of a secure supply and the need for uranium
deliveries from stable jurisdictions free from geopolitical conflicts.
Bannerman Managing Director and Chief Executive Officer, Brandon Munro, said:
“It has been an exciting quarter as we report continued progress on the Etango FEED against the
backdrop of a significant rise in the U3O8 spot price. This momentum continues to reflect favourable
uranium market fundamentals, which have also been broadly mirrored in uranium capital markets.
These dynamics continue to move in our favour as we advance discussions with prospective offtake
customers and evaluate the range of project finance options potentially available to us in this
environment.
“In September, we published our inaugural Sustainability Report for the 2023 financial year. This report
demonstrates our organisation-wide commitment to People, Planet and Performance.”
1
Bannerman advised of the completion of a Definitive Feasibility Study (DFS) for an 8Mtpa development of its flagship Etango Uranium
Project in Namibia in an ASX announcement dated 6 December 2022. Bannerman is not aware of any new information or data that
materially affects the information included in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply and have not materially changed.
Of the Mineral Resources scheduled for extraction and recovery in the DFS production plan, 100% are classified as Measured or
Indicated. Bannerman confirms that there are no Inferred Resources included in the DFS production schedule.
Bannerman Energy Ltd
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008
PO Box 1973, Subiaco, Western Australia 6008
W bannermanenergy.com
T +61 8 9381 1436
E info@bannermanenergy.com
Etango Uranium Project (Bannerman 95%)
All key workstreams advancing
Overall FEED activities for the Etango Project are progressing to plan and budget. Updates on key
workstreams during the quarter include:
•
Process Engineering: Process Flow Diagrams for the heap leach, ion exchange (IX), precipitation,
product drying and packaging, and reagents have been developed and reviewed. Process design
criteria for the comminution circuit and agglomeration were completed. Process information input
to mechanical data sheets for front-end vendor packages have also been completed.
•
Mechanical Engineering: Data sheets for all priority vendor packages were developed and
reviewed, and the primary crusher RFQ issued to market.
•
Electrical, Instrumentation and Control: Administrative and process telecommunications network
architecture was developed, including network routing and integration of external and fixed plant
networks. Reviews were held on conveyor instrumentation design and further green initiatives
under investigation.
•
Civil, Infrastructure and Earthworks: Bulk earth works calculations and material take-offs for
compilation of bill of quantities are now predominantly complete. Layout and general arrangement
drawings for bulk earth works and plant infrastructure have also been developed and reviewed.
•
Greenhouse Gas Emissions: Calculation of the DFS design greenhouse gas emissions was
completed and an additional study to identify options to further reduce emissions has been
completed. These options are now being evaluated in the FEED designs. A climate change risk
assessment, including both physical and transitional risks, has also been completed.
•
Long Lead Items: All early works contracts (temporary power, temporary water and access road)
are now ready for award, pending grant of the Etango Mining Licence.
Financing
As previously advised, Bannerman has commenced the early phases of the financing process for
Etango. In targeting the optimal financing mix for Etango, this process includes evaluating and
progressing a range of funding sources, including conventional project debt, as well as potential offtake
and joint venture opportunities with strategic counterparties.
Azure Capital and Vermilion Partners (both affiliates of the French financial services institution Natixis)
have been appointed to advise Bannerman on this process.
Offtake marketing
Bannerman’s product marketing strategy is centred on a detailed understanding of utility requirements
and preferences. The Company’s appointment of highly experienced nuclear executive, Ms Olga
Skorlyakova, to the role of Vice President, Market Strategy (refer to Bannerman ASX release dated 29
June 2023, Uranium Marketing and Nuclear Fuel Strategy Appointment), coincided with an escalating
level of engagement from utilities. This is consistent with the observed uranium market tightening over
the last two months and the meaningful rise of the spot price to over US$70/lb by quarter end.
Bannerman’s well-established position with respect to offtake marketing is that the company will not
diminish the long-term underlying value of Etango by committing to contracting its planned uranium
output on price (and other terms) that it considers unrepresentative of long-term market fundamentals
and producer opportunity. However, with yellowcake term contract liquidity and pricing building
momentum in line with tightening uranium market fundamentals, the threshold for undertaking such
contracting activities is becoming closer to being reached.
Key Bannerman representatives attended the World Nuclear Symposium 2023, held in London from 6
- 8 September. This provided a further forum for more extensive face-to-face engagement with key
Page 2 of 7
nuclear utility representatives and leaders.
Permitting and Targeted FID
All Environmental Clearance Certificates and National Heritage consents have been received and the
Etango Project is fully permitted in this regard.
The Etango Mining Licence (ML) application was submitted to the Ministry of Mines and Energy (MME)
in August 2022. Following the submission of the DFS in December 2022, Bannerman has been working
with the MME towards grant of the ML.
While the MME has advised that it has seen a significant uplift in mineral licence applications during
this period, it is Bannerman’s understanding that the Etango ML application is now in an advanced
stage of consideration. Grant of the ML, expected during H2 CY2023, will represent satisfaction of the
final non-market prerequisite to proceed with comprehensive offtake contracting and project financing
activities.
Bannerman’s strategy remains unchanged: advancing FEED and other key workstreams on Etango to
deliver the currency of quotation and overall development shovel-readiness while maintaining strong
balance sheet liquidity and strategic patience with respect to the satisfaction of key external factors.
This approach, along with favourable uranium market conditions, is advancing Etango towards a
targeted positive Final Investment Decision, uranium market permitting, during H1 CY2024.
Construction of the Etango Project is expected to take approximately 34 months (including detailed
design).
2023 Sustainability Report
Bannerman’s inaugural 2023 Sustainability Report, published on 29 September 2023, provides a
comprehensive account of our ESG credentials and sustainability performance for the fiscal year
ending 30 June 2023, together with future sustainability plans and commitments.
The report presents Bannerman’s sustainability strategy; highlighting our approach to environmental,
social and governance (ESG) factors, which include the health, safety and well-being of our employees,
our commitment to the communities in which we work and the financial sustainability of our business.
Each element of our strategy and responsibility to stakeholders is presented in the context of three
core pillars: People, Planet and Performance.
Corporate
Strong quarter-end cash balance of A$39.9 million
Bannerman’s cash balance at 30 September 2023 was A$39.9 million (30 June 2023: A$42.6 million).
The Company has no debt (other than typical creditor balances) or convertible instruments.
Total exploration and development expenditure for the quarter was A$2.3 million, which included FEED
work on the Etango Project.
Management continues to maintain a focus on prudent cost control and project timeliness. For the
purpose of item 6.1 of Appendix 5B, the aggregate payments during the quarter to related parties
(totalling A$224,833) were comprised of directors’ fees and salary.
Cancellation and issue of securities during the quarter
There were no Bannerman securities cancelled or issued during the September Quarter.
Page 3 of 7
Issued securities
At the date of this report, the Company has on issue 150,510,660 fully paid ordinary shares, 2,779,118
performance rights and 1,735,166 unlisted options. The performance rights and options are subject to
various performance targets and continuous employment periods.
Uranium Market
The quarter saw U3O8 spot prices increase by almost 23% compared to the previous quarter, rising
from US$56.00/lb to close at US$73.15/lb, the highest level observed since pre-Fukushima in 2011.
Increased utility demand, low inventories, and supply threats drove this price surge. The supply of
primary uranium remained tight due to supply constraints caused by the Russian invasion of Ukraine
political instability in Niger and reductions in production guidance by large producers.
China remains the largest single growth market, with 24 new reactors in construction, increasing its
current fleet of 55 reactors. Nuclear energy accounts for 5% of China's electricity, which is set to
increase to 10% by 2035 and 18% by 2060. The State Council approved the construction of six new
reactor units on July 31st, including the Ningde, Shidaowan, and Xudabao plants. China aims to
generate 400 GWe by 2060, 7.5 times more than the current capacity of 53.3 GWe.
New reactors are being pursued in many European countries, in particular France, which has plans to
construct six new EPR2 reactors, with an option for an additional eight. Countries such as Sweden,
Bulgaria, Slovenia, Romania, Czech Republic, and Hungary are either considering expanding their
nuclear programs or progressing towards building new units. In Poland, Polish and US officials have
signed an agreement to proceed with the construction of Poland's first nuclear power plant at the
Lubiatowo-Kopalino site in the Pomerania region; under the contract, Westinghouse and Bechtel, in
cooperation with PEJ, will complete a site-specific design for a plant that will include three AP1000
reactors.
In Japan, Unit 1 and Unit 2 of the Takahama NPP in Fukui Prefecture became the nation’s 11th and
12th reactors to resume operations, after a shutdown of over 12 years.
South Korea authorised the operation of Unit 2 of the Shin Hanul Nuclear Power Plant and has
announced its intention to resume the construction of Units 3 and 4. The Ministry of Trade, Industry,
and Energy aims to increase power supply capacity and meet the growing demand from high-tech
industries by building new nuclear power plants. The 11th Basic Plan for Long-term Electricity Supply
and Demand (2024-2038) has set a goal of exporting ten nuclear power plants by 2030 and developing
a small modular reactor (SMR) in Korea.
Vogtle 3, the USA's first newly constructed nuclear power plant in over 30 years, began commercial
operation. The start-up of Vogtle 4 is expected in the first quarter of 2024.
The increased market volatility clearly indicates the market's fragility, which leads to heightened tension
and uncertainty. In response, utilities are refining their procurement plans, reassessing their portfolios,
and seeking to diversify their sources of supply. They are also reevaluating their inventory policies and
stock-building strategies to ensure operational sustainability and reliability.
To mitigate risk, utilities are increasingly pursuing long-term, multi-year supply contracts while
emphasising the importance of a secure supply and the need for uranium deliveries from stable
jurisdictions free from geopolitical conflicts.
The conflict between Russia and Ukraine has had some implications for uranium supplies from
Kazakhstan, the largest producer of uranium. Furthermore, concerns about security of supply have
intensified following a coup d'état in Niger in late July, raising questions about future uranium
production in the country. Considering these factors, it is anticipated that U 3O8 contracting will
accelerate in the next 6-12 months.
Overall, the long-term outlook for the uranium market remains robust. The fundamentals continue to
strengthen, indicating the strong potential for an ongoing positive trajectory for the industry.
Page 4 of 7
This ASX release was authorised on behalf of the Bannerman Board by:
Brandon Munro, Managing Director and Chief Executive Officer
23 October 2023
Contact
Investors:
Media:
Brandon Munro
CEO and Managing Director
T: +61 9831 1436
info@bmnenergy.com
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of the Company, the Directors, and the management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting, or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
2
Preliminary Economic Assessment on the Lofdal Rare Earths Project Namibia dated October 1, 2014 authored by David S. Dodd, B.
Sc (Hon) FSAIMM - The MDM Group, South Africa, Patrick J.F. Hannon, M.A.Sc., P.Eng. and William Douglas Roy, M.A.Sc., P.Eng.
- MineTech International Limited, Canada, Peter Roy Siegfried, MAusIMM (CP Geology) and Michael R. Hall, B.Sc (Hons), MBA,
MAusIMM, Pr.Sci.Nat, MGSSA - The MSA Group, South Africa. The PEA should not be considered to be a pre-feasibility or feasibility
study, as the economics and technical viability of the Project has not been demonstrated at this time. The PEA is preliminary in nature
and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied
to them that would enable them to be categorised as Mineral Reserves. Furthermore, there is no certainty that the PEA will be realised.
3
A NI 43-101 compliant report entitled Preliminary Economic Assessment on the Lofdal Heavy Rare Earths 2B-4 Project, Namibia (“the
Report”) will be filed by NMI on SEDAR within 45 days of NMI’s announcement of 3 October 2022. SGS Canada Inc. is the principal
author under the supervision of Michael Archer who is a Qualified Person in accordance with NI 43-101 – Standards of Disclosure for
Mineral Projects. Sections of the Report dealing with property description and location, accessibility, climate, local resources,
infrastructure and physiography, history, geological setting and mineralisation, deposit types, exploration, drilling, sample preparation,
analyses and security and data verification were completed by The MSA Group under the supervision of Jeremy Witley, (BSc Hons,
MSc (Eng.)) and Swinden Geoscience Consultants under the supervision of Scott Swinden, (Ph.D P.Geo), who are Qualified Persons
in accordance with NI 43-101 – standards of disclosure for mineral projects. The section of the Report dealing with mineral resource
estimates was completed by The MSA Group under the supervision of Jeremy Witley, (BSc Hons, MSc (Eng.)). Sections of the Report,
dealing with mining methods and mine capital and operating costs were completed by SGS Canada under the supervision of Bill van
Breugel (BaSc Hons, P.Eng.) who is a Qualified Person in accordance with NI 43-101 – Standards of Disclosure for Mineral Projects.
Sections of the Report, dealing with mining design and schedules were completed by BBMC RSA under the supervision of Johann
Hager (BEng Hons, MEng Mining, P.Eng.) who is a Qualified Person in accordance with NI 43-101 – Standards of Disclosure for
Mineral Projects. Each of Michael Archer, Jeremy Witley, Scott Swinden, Johann Hager, and Bill van Breugel reviewed and approved
the technical disclosure of the NMI press release dated 3 October 2022. Rainer Ellmies, PhD, MScGeol, EurGeol, AusIMM and Vice
President of Namibia Critical Metals Inc., is the Company’s Qualified Person and has reviewed and approved the geological data in
that press release.
Page 5 of 7
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development company listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia. Bannerman has long established itself as an
Environmental, Social and Governance (ESG) leader in the uranium and nuclear energy sector.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1. In December 2022, a Definitive
Feasibility Study (DFS)2 was completed on the Etango Project, confirming to a definitive level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput. Bannerman previously completed advanced studies on an alternative, larger
development pathway - a 20Mtpa development at Etango was the subject of a DFS completed in 2012 and
a DFS Optimisation Study completed in 20153.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure, and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda.
Etango has environmental approvals for the proposed mine and external mine infrastructure, based on a
12-year environmental baseline. Bannerman is a leader within Namibia on social development and
community engagement and exercises best-practice governance in all aspects of its business.
The Bannerman team has ample direct experience in the development, construction, and operation of
uranium projects in Namibia, as well as extensive links into the downstream nuclear power industry.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango- Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
3. Refer to Bannerman’s ASX release dated 11 November 2015, Outstanding DFS Optimisation Study Results.
Page 6 of 7
Forward Looking Statements
The information in this announcement is not intended to guide any investment decisions in Bannerman
Energy Ltd. This material contains certain forecasts and forward-looking information, including possible
or assumed future performance, costs, production levels or rates, reserves and resources, prices and
valuations and industry growth and other trends. Such forecasts and information are not a guarantee
of future performance and involve many risks and uncertainties, as well as other factors. Actual results
and developments may differ materially from those implied or expressed by these statements and are
dependent on a variety of factors. The Company believes that it has a reasonable basis for making the
forward-looking statements in the announcement, based on the information contained in this and
previous ASX announcements.
Bannerman is not aware of any new information or data that materially affects the information included
in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply
and have not materially changed.
Competent Person’s Statement
The information in this announcement as it relates to Exploration Results is based on, and fairly
represents, information and supporting documentation prepared by Mr Marthinus Prinsloo. Mr Prinsloo
is a full-time employee of Bannerman Energy Ltd and is a Member of the Australasian Institute of
Mining and Metallurgy (AusIMM). Mr Prinsloo has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration, and to the activities, which he is undertaking.
This qualifies Mr Prinsloo as a “Competent Person” as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ and a Qualified
Person as defined by Canadian National Instrument 43-101. Mr Prinsloo consents to the inclusion in
this announcement in the form and context in which it appears. Mr Prinsloo holds shares and
performance rights in Bannerman Energy Ltd.
Listing Rule 5.3.3 Tenement Schedule:
BANNERMAN ENERGY LTD CONSOLIDATED BASIS
SCHEDULE OF INTERESTS IN MINING TENEMENTS
Project
Mining tenements
held
Location of
tenements
Beneficial %
interest at end of
the quarter
Change in the
quarter
Etango
Mineral Deposit
Retention Licence
(MDRL) 3345
Namibia
95%
-
Page 7 of 7