Membrane Study initial test work successfully completed
Released
Released
Announcement PDF
STOCK EXCHANGE
ANNOUNCEMENT
6 December 2017
Membrane Study initial test work successfully completed
Bannerman Resources Limited (ASX:BMN; NSX:BMN) (“Bannerman” or the “Company”) is pleased to
announce that the Etango Membrane Study has successfully progressed through the initial test work
phase at the Etango Heap Leach Demonstration Plant, validating the potential for further capital and
operating cost reductions, to be confirmed in the DFS Update.
HIGHLIGHTS
Successful completion of Membrane Study initial test work
o Conducted on-site at Etango Heap Leach Demonstration Plant using membrane pilot test rig
o Supervised by Bannerman technical team and equipment vendors
o Program ran smoothly, according to timeframe and budget
Preliminary lab results ready for evaluation by equipment vendors, outcomes expected early 2018
o Early indications positive, subject to secondary test work and economic evaluation
DFS Update to incorporate any confirmed cost savings
o Potential capital cost savings from smaller Ion Exchange (IX) processing circuit and/or
downstream processing units
o Potential operating cost savings from acid recovery and upgrading tenor of IX eluate solution
On 9 November 2017 Bannerman announced the Etango Processing Optimisation Study (Processing OS),
which reported a substantial decrease in estimated capital costs and the potential for significant
reductions in operating costs at Bannerman’s proposed Etango uranium mine in Namibia. The Processing
OS identified the opportunity to incorporate nano-filtration technology in the processing circuit.
A subsequent desk-top study by the Australian equipment vendors confirmed this potential after reviewing
analytical data from the Etango Heap Leach Demonstration Plant. A membrane pilot test rig was mobilised
to site to undertake an initial test work program, under the supervision of Bannerman’s technical team and
the equipment vendors. The test work used significant volumes of pregnant leach solution obtained from
operation of two cribs at the Demonstration Plant. An IX process was then used to make concentrated
eluate solution which was also used in the test work. The initial test work is now complete.
Bannerman’s Chief Executive Officer, Mr Brandon Munro, said, “Following the success of the Etango
Processing Optimisation Study announced last month, I am delighted with the progress our technical team
has made with the Membrane Study. When you consider the proposed scale of production at Etango, the
possible operating cost savings that membrane technology can deliver is a huge potential value addition to
Etango and Bannerman. This now well established technology has the potential to move the dial at
Etango, so we eagerly await the results from this study, expected early next year.
“Recent production cut announcements from the world’s two largest uranium producers, KazAtomProm
and Cameco, will remove more than 25 million pounds of uranium from 2018 forecast supply. This is
expected to put the uranium market into deficit, which follows 11 consecutive years of surplus that has
driven prices to fundamentally unsustainable levels. Next year promises to be very exciting for our industry
and Etango is exceptionally well positioned given its advanced nature, world-class scale and the substantial
economic uplift we are targeting in the DFS Update.”
www.bannermanresources.com
BANNERMAN RESOURCES LIMITED ABN 34 113 017 128
Corporate Office Unit 1 ■ 2 Centro Avenue ■ Subiaco Western Australia 6008
Post PO Box 1973 ■ Subiaco Western Australia 6904 T +61 8 9381 1436 F +61 8 9381 1068
For further information please contact:
Brandon Munro
Chief Executive Officer
Perth, Western Australia
Tel: +61 (8) 9381 1436
info@bannermanresources.com.au
Robert Dalton
Company Secretary
Perth, Western Australia
Tel: +61 (8) 9381 1436
info@bannermanresources.com.au
Michael Vaughan (Media)
Fivemark Partners
Perth, Western Australia
Tel: +61 422 602 720
Michael.vaughan@fivemark.com.au
About Bannerman - Bannerman Resources Limited is an ASX and NSX listed exploration and development company with
uranium interests in Namibia, a southern African country which is a premier uranium mining jurisdiction. Bannerman’s principal
asset is its 95%-owned Etango Project situated near Rio Tinto’s Rössing uranium mine, Paladin’s Langer Heinrich uranium mine
and CGNPC’s Husab uranium mine. A definitive feasibility study has confirmed the technical, environmental and financial (at
consensus long term uranium prices) viability of a large open pit and heap leach operation at one of the world’s largest
undeveloped uranium deposits. From 2015-2017, Bannerman conducted a large scale heap leach demonstration program to
provide further assurance to financing parties, generate process information for the detailed engineering design phase and
build and enhance internal capability. More information is available on Bannerman’s website at
www.bannermanresources.com.