Bannerman Resources Limited (ASX|BMN; TSX|BAN; NSX|BMN) and its independent technical consultants (primarily
AMEC Foster Wheeler and Optiro Pty Ltd) have completed an Optimisation Study (“OS”) on the geological modelling and
mine planning aspects of the Etango Definitive Feasibility Study (“DFS”), which was completed in April 2012. The OS also
reflects updated capital and operating cost estimates.
Key outcomes of the OS (at a life-of-mine price of US$75/lb U3O8):
Project net present value (NPV8%) of US$419M (previously US$69M).
Post-tax internal rate of return (“IRR”) of 15% (previously 9%).
Average annual production of 7.2Mlbs U3O8 over an initial 15.7 year open pit mine life;
o
9.2Mlbs U3O8 per annum over the first five full production years (previously 7.9Mlbs).
Average life-of-mine cash operating costs of US$38/lb U3O8 (reduced 17%);
o
US$33/lb U3O8 over the first five full production years (reduced 20%).
Pre-production capital of US$793M including mining fleet (reduced 9%).
Rapid payback from first production (4.4 years) and initial mine life to payback ratio of 3.6 times.
Total operating cash flow of US$3.7B before capital and tax, and free cash flow of US$1.6B after capital and tax.
From production commencement, average annual operating cash flow of US$236M and free cash flow of US$150M.
Peak annual free cash flow of US$392M.
Potential upside from heap leach demonstration plant results and other identified opportunities still to be
incorporated via additional optimisation work.
A detailed summary of the OS results is set out in the attachment to this release. In accordance with Canadian technical
reporting requirements, it is noted that Mineral Resources which are not Mineral Reserves do not have demonstrated
economic viability.
A NI 43-101 report on the OS will be filed in accordance with the requirements.
Bannerman Chief Executive Officer, Len Jubber, said:
“The Optimisation Study has strongly repositioned Etango, demonstrating project economics that are highly competitive
at consensus incentive long term uranium prices. Importantly the work has also confirmed the technical robustness of
the DFS. When coupled with the success of the heap leach demonstration plant, the Optimisation Study clearly places
Etango at the forefront of the global development pipeline of projects likely to produce at or above 2Mlbs U3O8 per
annum.”
“The outstanding improvements in key project metrics reflect the sustained and diligent professionalism of the
Bannerman technical team and independent consultants. The favourable demonstration plant results and unconverted
mineral resources deliver considerable potential to further enhance the economics and longevity of the Etango project.”
www.bannermanresources.com
BANNERMAN RESOURCES LIMITED ABN 34 113 017 128
Corporate Office Unit 1 ■ 2 Centro Avenue ■ Subiaco Western Australia 6008 Post PO Box 1973 ■ Subiaco Western Australia 6904
T +61 8 9381 1436 F +61 8 9381 1068
i
“Importantly, Bannerman has now established a sound project platform for extensive engagement with the global
nuclear industry. The technical and financial credibility that comes with Etango’s advanced stage of study will be of
critical benefit to Bannerman during this educating and marketing process. Moreover, at a time when most uranium
projects are subject to lengthy and uncertain permitting timeframes, it is comforting to be operating in Namibia where 3
major uranium mines have been permitted and largely constructed during the past 10 years.”
“With the growing debate around climate change and the commitment of major players such as the USA and China to
reducing greenhouse gas emission, nuclear energy as a baseload electricity source, is expected to have a central role in
meeting the growth of future energy needs. Whilst wind and solar energy will no doubt have a role to play, there is no
substitute for more nuclear energy when targeting significant reductions in emissions and increases in overall energy
supply.”
“We will continue to move the Etango project forward in a professional manner, looking to capitalise on its advanced
project status and early mover advantage into the consensus forecast improvement in uranium market activity and
pricing.”
Len Jubber
Chief Executive Officer
Cautionary Statement: This announcement has been prepared in accordance with the JORC Code (2012) and the
ASX Listing Rules. Whilst Bannerman has concluded that it has a reasonable basis for providing the forward looking
statements included in this announcement, Bannerman advises that given the current price of U3O8 and the
company’s current market capitalisation (compared to the capital expenditure required in connection with the
Etango project), the production targets and forecast financial information contained in this announcement do not
provide an assurance of economic development at this stage. The stated production target and forecast financial
information contained in this announcement is based on Bannerman’s current expectations of future results or
events and should not be relied upon by investors when making investment decisions.
Conference Call
Len Jubber (Managing Director and CEO) will host a conference call to discuss the Company’s recent activities at
th
9.00am Australian Eastern Daylight Time (“AEDT”) on Thursday 12 November 2015.
The conference call includes Q & A participation. Please dial in five minutes before the conference starts and provide
your name and Conference ID.
Conference ID:
Dial-in numbers:
Australia:
Australia:
China:
Canada
Hong Kong:
Singapore:
United Kingdom:
United States:
675198
1 800 558 698
02 9007 3187
4001 200 659
1855 8811 339
800 966 806
800 101 2785
0800 051 8245
(855) 881 1339
A recording of the conference call will be available on the Company’s website later in the day.
ii
For further information please contact:
Len Jubber
Chief Executive Officer
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Robert Dalton
Financial Controller / Company Secretary
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Spyros Karellas
Investor Relations
Tel: +1 416 433 5696
spyros@pinnaclecapitalmarkets.ca
Michael Vaughan
Media Adviser
Tel: +61 422 602 720
michael.vaughan@fivemark.com.au
About Bannerman - Bannerman Resources Limited is an ASX, TSX and NSX listed exploration and development company with
uranium interests in Namibia, a southern African country which is a premier uranium mining jurisdiction. Bannerman’s principal
asset is its 80%-owned Etango Project situated near Rio Tinto’s Rössing uranium mine, Paladin’s Langer Heinrich uranium mine and
CGNPC’s Husab uranium mine currently under construction. A definitive feasibility study has confirmed the technical, environmental
and financial (at consensus long term uranium prices) viability of a large open pit and heap leach operation at one of the world’s
largest undeveloped uranium deposits. In 2015, Bannerman is conducting a large scale heap leach demonstration program to
provide further assurance to financing parties, generate process information for the detailed engineering design phase and build and
enhance internal capability. More information is available on Bannerman’s website at www.bannermanresources.com.
iii
Etango Uranium Project
Optimisation Study
November 2015
1
BACKGROUND
Bannerman currently owns an 80% interest in Bannerman Mining Resources (Namibia) Pty Ltd which in turn
owns 100% of the Etango project. The projected is located within the Erongo region of Namibia which also
hosts the operating Rössing (Rio Tinto) and Langer Heinrich (Paladin Energy) uranium mines and the Husab
uranium project, which is currently being developed by China General Nuclear Power Corporation.
The project area is approximately 40 km east of the regional town of Swakopmund and approximately 50km
northeast of the deep water port at Walvis Bay.
Uranium mining is well established in Namibia and has been undertaken since 1976. The country is currently
the 5th largest uranium producer in the world and is expected to become the 3rd largest post commissioning
of the Husab project in 2016.
Exploration at the Etango project was commenced in 2006 followed by the Scoping Study in 2007, PFS in 2009,
PFS Update in 2010 and DFS in 2012. The focus of the DFS was to confirm the viability of the lower capital
intensity and lower operating cost heap leaching approach on the Etango deposit. This was successfully
confirmed through the 4 year metallurgical program conducted leading up to completion of the DFS and more
recently during the Heap Leach Demonstration Plant Program which is still ongoing. In turn the DFS
Optimisation Study has focussed on the geology and mining aspects of the project coupled with updates of the
operating and capital cost estimates.
It is important to note that the Optimisation Study does not incorporate the favourable results currently
arising from the Heap Leach Demonstration Plant program. It is planned that results from the demonstration
plant program will be fully evaluated in a processing review to commence in the March 2016 Quarter.
On 11 November 2015 Bannerman announced that the company had, subject to certain conditions being
satisfied including shareholder approval and the renewal of EPL 3345, entered into various agreements to gain
100% ownership of the Etango Project, eliminate the existing A$12 million corporate debt and raise net A$4
million to fund the operation of the heap leach demonstration plant program and corporate working capital
requirements. The proposed elimination of the debt through part conversion into Bannerman shares and the
issuance of a royalty will result in a 1.5% gross revenue royalty on the future gross revenue derived from the
Etango Project.
As these negotiations were conducted after the mine planning was done for the optimisation study the 1.5%
gross royalty was not included in aspects of the mine planning (such as pit optimisation). However, the royalty
has been taken into consideration in the financial modelling of the Optimisation Study. The difference is not
considered to have a material effect on the core mine planning work.
2
KEY OUTCOMES
The key outcomes of the OS on the Etango Uranium Project include:
Table 1 – Key Outcomes of Etango Project DFS Optimisation Study
Units
DFS
Optimisation
Study
Definitive
Feasibility
Study
% Change
US$/lb U3O8
75
75
-
Mine Life
Years
15.7
15.0
4%
Total Mined Ore
Mt
303
280
8%
Life-of-mine stripping ratio
Waste : Ore
2.78 : 1
3.34 : 1
-17%
Annual Processing Throughput
Mt of ore
20
20
-
Processed grade
ppm U3O8
195
194
-
Processed grade (First 5 years of full production)
ppm U3O8
241
207
+16%
%
86.9
86.9
-
Ave. Annual Production for first 5 full production years
Mlbs U3O8 pa
9.18
7.92
+16%
Average Annual Production (U3O8)
Mlbs U3O8 pa
7.20
6.90
+4%
Life-of-mine Production (U3O8)
Mlbs U3O8
113
104
+9%
Pre-production Capital Expenditure
US$ million
793
870
-9%
Sustaining Capital Expenditure
US$ million
282
381
-26%
Average Cash Operating Cost for first 5 years
US$/lb U3O8
33
41
-20%
Average Cash Operating Cost for life-of-mine
US$/lb U3O8
38
46
-17%
Net Present value (8%)
US$ million
419
69
+511%
Internal Rate of Return (at Base Case price)
%pa, post-tax
15%
9%
+66%
Net cash flow breakeven uranium price
US$/lb U3O8
52
61
-15%
Years
4.4
6.0
-27%
Item
Base Case Uranium Price
Processing recovery
Payback (from first production)
Operating cost includes all mining, processing, on-site and off-site infrastructure and general/administrative costs and excludes royalties (3% Government
royalty and third party royalties) and freight and selling-related costs (together approximately US$1.10/lb) which, in accordance with industry accounting
standards, are deducted from revenues for economic modelling purposes.
Figures are presented in US$ in real terms assuming a base date of the December 2011 quarter for the DFS and July 2015 for the OS, unless otherwise stated.
Economic results reflect 100% ownership of the Etango Project ignoring financing structure.
2,000
1,500
1,000
500
(100)
(200)
(300)
(400)
(500)
(600)
(500)
(1,000)
Free cash flow (LHS)
2035
2034
2033
2032
2031
2030
2029
2028
2027
2026
2025
2024
2023
2022
2021
2020
2019
2018
(1,500)
Cumulative free cash flow (US$M)
Cumulative Cash Flow post CAPEX
500
400
300
200
100
2017
Free cash flow (US$m)
The chart below presents the annual and cumulative projected free cash flow for Etango over its initial 15.7
year mine life.
Cumulative free cash flow (RHS)
3
MINERAL RESOURCE AND ORE RESERVE1
Introduction
The primary uranium mineralisation at Etango is confined to leucogranites, locally referred to as alaskites.
These are often sheet-like and predominantly occur as bedding-parallel bodies which dip at between 15 and 40
degrees to the west. The individual sheets may merge to form larger composite plutons or alaskite
stockworks. The Etango mineralisation wraps around the southwestern flank of the Palmenhorst Dome, which
is cored by Mesoproterozoic rocks (1.7 to 2.0 Ga in age).
Uranium mineralisation occurs exclusively in alaskite, although metasediment/alaskite complexes at the
fringes of the main alaskite bodies can be strongly mineralised where alaskite stringers interfinger surrounding
rocks. Not all of the alaskite is mineralised, and six types of body have been identified, with two (types D and
E) hosting the bulk of the known uranium mineralisation. The primary uranium mineralisation occurs as
microscopic disseminations throughout the alaskite as inclusions within other minerals and at crystal
interfaces. The dominant primary uranium mineral at Etango is uraninite (UO 2). There is no evidence for any
discrete enrichment or depletion zones in any uraniferous minerals over any part of the Etango deposit.
Bannerman has completed a total of 945 RC (215,480m), 137 diamond (37,392m) and 21 RAB (1,875m)
drillholes, for a total of approximately 254,747m, in the vicinity of the Etango Project. This drilling provided the
geotechnical, hydrological, structural, lithological and uranium grade data over the Anomaly A, Oshiveli and
Onkelo prospects and the plant site area that are the subject of this resource update.
The Drilling programmes carried out by Bannerman since 2006 have been subject to best practice geological
control, including collar surveys and downhole deviation surveys using both single shot and multiple shot
cameras.
Samples were obtained using both reverse circulation (RC) and diamond drilling (DD) methods. RC drill samples
were collected off the rig cyclone in large plastic bags at 1m intervals. The 1m sample was split in the field by
Bannerman staff using a 75/25 riffle splitter. The 75% sample was placed into a bulk sample bag from which
rock chip samples were taken and placed into a chip tray for logging by the geologist. The primary sample sent
to the laboratory was obtained by splitting the 25% sample until a sample of approximately 500g to 1kg was
obtained. A count per minute (CPM) reading was taken from this sample using a handheld scintillometer and
recorded along with the sample condition (wet, dry, and moist). If the bulk sample was wet, a spear sample
was taken. Intervals of recovered samples selected for analysis, were based on alaskite lithology or
intersections in non-alaskites that had a CPM greater than 300.
Diamond drill core was placed in core trays after drilling and taken to the Bannerman core logging and storage
facility on site at Etango, where it was orientated, measured, logged and marked for sampling by the staff
geologist. Sample intervals were determined by the geologist after logging. The sample lengths were
nominally 1m; however, samples lengths ranging from 0.5 to 1.49m were selected where a lithological
boundary was intersected. No sampling was undertaken across lithological boundaries.
A full QAQC programme, including the use of field, diamond core and pulp duplicates and certified standards,
has been implemented by Bannerman. Assays used in resource estimation are a combination of pressed pellet
X-ray fluorescence analyses and radiometric probe readings. Eight pairs of twinned diamond-RC holes have
drilled by Bannerman since 2006 and assays compare favourably between the paired holes.
Mineral Resource Estimate
The 2015 Mineral Resource update for Etango has evolved considerably from the previously reported (October
2010) estimate, which was the basis of the DFS. The model incorporates an additional 3,419m of drilling across
the deposit. Uranium mineralisation has been defined inside grade envelopes by categorical indicator kriging
using a lower cut-off grade of 50ppm U3O8 and lithological constraints.
In addition to the change in estimation approach, the update considered the relevant operational aspects
associated with open pit uranium mining, most notably the established practice of radiometric haul truck
scanning as a means of discriminating between ore and waste material at the haul truck payload level. This
practice which is unique to uranium mining due to the ability to measure the gamma radiation associated with
the mineralisation has been very effectively implemented at the Rössing and Ranger uranium mines.
1
This report uses the term Ore Reserves consistent with the Australasian Code for Reporting of Exploration Results, Mineral Resources. For the
purpose of this report Mineral Reserves are equivalent to Ore Reserves.
4
In order to model this high selectivity, a Uniform Conditioning (UC) estimation approach has been adopted.
This is a recoverable resource estimation technique based upon ordinary kriging into large blocks (panels)
which seeks to predict the resources available at the time of mining using the assumption of a selective mining
unit (SMU) related to the production rate and equipment.
The uniform conditioning approach effectively determines a tonnage-grade curve of smaller volumes (SMU
scale) within the larger mining panel consistent with the mining method and the use of a radiometric truck
scanner. In the context of the Etango project this approach simulates the range of grades that would be
presented to the truck scanner for each larger mining block.
The cut-off grade for the Etango Mineral resource was reduced to 55ppm to be consistent with the Ore
Reserves cut-off grade.
The Mineral Resource has been classified into Measured, Indicated and Inferred categories on the basis of
geological and grade continuity, drillhole spacing and estimation quality. The Measured category was applied
to blocks which were informed either in pass one or two, where the drill spacing was 25m x 25m or 25m x
50m, and where the slope of regression statistic was generally greater than 0.9. The Indicated category was
applied to blocks estimated in the first or second pass, where the drill spacing was nominally 50m x 50m or
100m x 100m, where the grade tenor was moderately consistent and where the slope of regression was
between 0.3 and 0.9. Any material which did not meet the criteria for Measured or Indicated was allocated to
the Inferred category, apart from extrapolated or laterally-extensive mineralisation which was set to potential
using a number of ‘unclassify’ solids.
The November 2015 Etango Project Mineral Resource Estimate (summarised in the table below) was
incorporated in the Optimisation Study. The estimate includes an updated resource estimate of the Etango
deposit prepared by Optiro whilst the estimates for the Ondjamba and Hyena deposits remain unchanged
from that announced in October 2010. The estimate comprises the following:
Table 2 - Etango Project DFS Optimisation Study Mineral Resources (November 2015)
Mineral Resource Nov 2015
Deposit
Measured
Indicated
Inferred
Cut Off Grade
Tonnes
Grade
In-situ
Tonnes
Grade
In-situ
Tonnes
Grade
In-situ
(U3O8 ppm)
(Mt)
(U3O8
U3O8
(Mt)
(U3O8
U3O8
(Mt)
(U3O8
U3O8
ppm)
(Mlbs)
ppm)
(Mlbs)
ppm)
(Mlbs)
194
14.4
188
150.2
144.5
196
62.5
Etango2
55
Ondjamba3
100
85.1
166
31.3
Hyena4
100
33.6
166
12.3
263.2
182
106.1
Total
33.7
33.7
194
14.4
362
362
188
150.2
Note 2: Refer to the Competent Persons Statement at the end of this document for further information on the Etango Mineral Resource
Estimate. The Etango estimate has been reported in accordance with JORC 2012. The figures may not add due to rounding.
Note 3 & 4: Refer to the Competent Persons Statement at the end of this document for further information on the Ondjamba and Hyena
Mineral Resource Estimates. The Ondjamba and Hyena estimates remain unchanged from the previous declaration and therefore have
been reported in accordance with JORC 2004. The figures may not add due to rounding.
The Etango Project Mineral Resource estimate is reported inclusive of Ore/Mineral Reserves (refer to the next
section) and in accordance with the standards and guidelines in the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (the JORC Code 2012) and the Canadian National
Instrument 43-101. It is noted that Mineral Resources which are not Mineral/Ore Reserves do not have
demonstrated economic viability.
Further details on the basis on which the Etango Mineral Resource Estimate has been compiled are contained
in Sections 1-3 of the accompanying JORC 2012 Table 1.
The October 2010 Etango Project Mineral Resource estimate incorporated in the 2012 DFS is presented below
for comparative purposes.
5
Table 3 - Etango Project DFS Mineral Resources (October 2010)
Mineral Resource Oct 2010
Deposit
Measured
Cut Off Grade
Tonnes
Grade
(U3O8 ppm)
(Mt)
In-situ
Tonnes
Grade
(U3O8
U3O8
(Mt)
ppm)
(Mlbs)
205
28.3
In-situ
Tonnes
Grade
In-situ
(U3O8
U3O8
(Mt)
(U3O8
U3O8
ppm)
(Mlbs)
ppm)
(Mlbs)
200
120.4
45.7
202
20.3
100
Ondjamba
100
85.1
166
31.3
Hyena
100
33.6
166
12.3
164.4
176
63.9
62.7
205
28.3
273.5
Inferred
Etango
Total
62.7
Indicated
273.5
200
120.4
The Mineral Resource estimate was reported at a cut-off grade of 100ppm U3O8. Refer to the Competent Persons Statement at the end of
this document for further information. Figures may not add due to rounding.
The table below sets out the key changes in the October 2010 and November 2015 Mineral Resource
parameters:
Table 4 – Comparison of Key Mineral Resource Parameters
Mineral Resource Estimate
November 2015
Mineral Resource Estimate
October 2010
Approach
Recoverable resource that considers mining
dilution.
Mining dilution considered in mine planning.
Methodology
Ordinary Kriging followed by Localised Uniform
Conditioning (LUC)
Ordinary Kriging (OK)
Delineation of
mineralised zones
Grade shell models, taking into account the
distribution of both mineralisation and host
lithology, generated using a categorical
indicator kriging approach based upon a
50ppm U3O8 cut-off grade.
Manual wire framing of mineralised envelopes
utilising a 75ppm cut-off grade.
Cut-off grade
55 ppm – aligned with Ore Reserve. Cut-off
grade calculated as the mill limiting cut-off as
discussed in the accompanying JORC Table 1.
100 ppm
Block size
Estimated to 25mE x 25mN x 8mRL and
uniform conditioned to 6.25mE x 12.5mN x
4mRL – selected to target the required SMU
size associated with radiometric truck
scanning.
Estimated directly into 25mE x 25mN x 10mRL
sub-celled to 6.25mE x 6.25mN x 1mRL.
Resource constraint
Constrained by USD 75/lb U3O8 Whittle Shell.
No constraint.
Parameter
Ore Reserve Estimate
Bannerman has updated the Ore Reserve following completion of the following work:
Updating the Mineral Resource model (as detailed above),
Updating the operating cost estimates,
Updating the capital cost estimates, and
Updated mining studies including revised open pit designs (including geotechnical review) and mine
schedules.
The updated Ore Reserve of 303.3Mt at 195ppm for 130.1Mlbs U3O8 consists of 11% Proved Reserves and 89%
Probable Reserves as tabulated below. The Proved Ore Reserves is a sub-set of Measured Mineral Resources,
and the Probable Ore Reserve is derived from Indicated Mineral Resources. Inferred resources were treated as
6
waste with no economic contribution to the project. No Measured Resources were downgraded to Probable
Ore Reserves due to uncertainty in modifying factors. Consequently Proved Reserves is based on drill spacing
of 25m x 25m or 25m x 50m and Probable Reserves are based on drill spacing of nominally 50m x 50m or 100m
x 100m.
The accuracy and confidence of modifying factors are generally consistent with feasibility level accuracy with
many of the technical factors remaining unchanged from the previous Definitive Feasibility Study. The capital
cost estimate updates for the fixed plant was done to an accuracy of ±20% which is consistent with a PreFeasibility study level of accuracy (typically -15% +25%).
The Ore Reserve was completed by Bannerman Resources following input from independent consultants as
detailed in the JORC Table 1.
The Ore Reserve estimate represents a 77% conversion rate from Measured and Indicated Resources.
Table 5 - Etango Project DFS Optimisation Study Ore Reserves (November 2015) as at 1 November 2015
Ore
Reserve
Proved
Probable
Total
Nov 2015
Deposit
Etango
Tonnes
Grade
In-situ
Tonnes
Grade
In-situ
Tonnes
Grade
In-situ
(Mt)
(U3O8
U3O8
(Mt)
(U3O8
U3O8
(Mt)
(U3O8
U3O8
ppm)
(Mlbs)
ppm)
(Mlbs)
ppm)
(Mlbs)
196
14
195
116.1
195
130.1
32.3
271
303.3
Figures may not add due to rounding.
The November 2015 Ore Reserve was estimated in accordance with the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves (JORC 2012) and the Canadian National Instrument
43-101 using a cut-off grade of 55ppm U3O8, a processing recovery of 86.9%, a metal price of US$75/lb U3O8
and the OS cost estimates outlined herein.
The metallurgical process together with the associated technical parameters remains unchanged from the DFS.
Initial phases of large column (30t cribs) leach test work support these assumptions. Further details on the
basis on which the Ore Reserves has been estimated are contained in Section 4 of the accompanying JORC
Code 2012 Table 1 appendix.
The maiden April 2012 Etango Project Ore Reserve estimate of 279.6Mt at 194ppm for 119.3Mlbs U3O8 is
tabulated below for reference.
Table 6 - Etango Project DFS Ore Reserves (April 2012) as at 1 November 2015
Ore
Reserve
Proved
Probable
Apr 2012
Deposit
Etango
Total
Tonnes
Grade
In-situ
Tonnes
Grade
In-situ
Tonnes
Grade
(Mt)
(U3O8
U3O8
(Mt)
(U3O8
U3O8
(Mt)
(U3O8
U3O8
ppm)
(Mlbs)
ppm)
(Mlbs)
ppm)
(Mlbs)
194
27.4
193
91.8
194
119.3
64.2
215.3
279.6
In-situ
Figures may not add due to rounding.
The table below sets out the key changes in the maiden 2012 Ore Reserve and the 2015 Ore Reserve
parameters:
7
Table 7 – Comparison of Key Assumptions for Ore Reserves
Parameter
Ore Reserve Estimate
November 2015
Ore Reserve Estimate
April 2012
Resource model
Nov 2015 recoverable Localised Uniform
Conditioning resource model.
October 2010 Ordinary Kriged resource model.
Economic cutoff grade
55 ppm – based on the mill limiting cut-off grade,
reduced to more effectively exploit the deposit.
70 ppm.
SMU
6.25mE x 12.5mN x 4mRL – scaled to account for
dilution associated with the mining method.
6.25mE x 6.25mN x 4mRL following the
regularisation of the 6.25mE x 6.25mN x
1.25mRL sub-blocks.
Mining loss &
dilution
SMU scaled to include dilution during the
resource estimation.
2.6% and 4.9%.
Strip ratio
2.78:1 – reduced as a result of changes in the
cut-off grade and pit design.
3.34:1.
Processing
recovery
86.9% – aligns with the recovery estimate
incorporated in the DFS financial model.
84% during pit optimisation.
86.9% for mine schedule and financial model.
Mining cost
US$1.69 per tonne mined – reflects the change
in crude oil price, explosives and other mining
consumables as in 2015.
US$ 1.97 per tonne mined.
Processing cost
US$6.79 per tonne processed - reflects lower
reagent, consumable and maintenance costs
offset by increased water and electricity costs as
in 2015.
US$7.15 per tonne processed.
General &
Admin Cost
US$ 18.6M per annum reflecting updated
exchange rates and human resources costs.
US$ 21.8M per annum.
MINING
The conventional open pit mining operation comprising 550 tonne hydraulic back-hoe excavators and
220 tonne diesel/electric haul trucks coupled with drilling and blasting on 12 metre benches and mining on 44.5 metre flitches to minimise ore dilution, remains unchanged from the DFS.
The study re-optimised the pit utilising the updated resource model and costs. The geotechnical and
metallurgical parameters remained unchanged from the DFS. The pit optimisation assumed a price of US$75/lb
U3O8 and a discount rate of 8%. No further dilution and mining loss were applied to model as the SMU (of 6.25
m E by 12.5 m N by 4 m RL) utilized in the model is greater than the proposed mining method selectivity
utilizing radiometric truck scanning. The ratio of SMU to truck size corresponds well with what neighbouring
and other open pit uranium mines that employ this technique as reported in the literature.
Practical pit designs were completed which was used in conjunction with the DFS waste dump designs to
produce an optimal mine schedule. The geotechnical parameters applied during the mine design process was
based on a detailed geotechnical study conducted by Coffey mining in 2012 as part of the DFS and which was
informed by 26 geotechnical drill holes drilled to collect rock quality and structural data. The resultant
geotechnical recommendations are suitable for implementation at DFS level of reliability with inter ramp s