Quarterly Activities Report
FOR THE PERIOD ENDED 31 DECEMBER 2025
Bannerman Energy Ltd (ASX: BMN, OTCQX: BNNLF, NSX: BMN) (Bannerman or the Company)
is pleased to report on continued strong progress at its Etango Uranium Project (Etango) during the
quarter, with significant developments across a range of key workstreams. The Company is advancing
towards a targeted positive Final Investment Decision (FID) on Etango, market conditions permitting.
HIGHLIGHTS
• Outstanding safety record with Etango LTI-free for 16 years.
• Etango early works construction activities tracking to overall budget and schedule:
− Site contractor workforce progressively increased to over 370 personnel.
− Bulk earthworks contract progressing well and approx. 51% complete, major
focus remains construction of heap leach pads.
− Blasting, crushing and screening of heap leach drainage aggregate advancing to
schedule and on-spec.
− Phase 1 and Phase 2A concrete contracts placed and commenced, with
foundations for both primary crusher and stockpile tunnel already poured.
− High-Pressure Grinding Rolls (HPGR) tertiary crusher successfully
manufactured, transported and delivered to site.
• Detailed design and procurement activities advancing well:
− Detailed model review (M2) for dry plant successfully completed; civil and
mechanical design for dry plant approx. 92% complete.
− Wet plant design currently focused on validation test work; detailed engineering
of wet plant approx. 23% complete.
• Long-term infrastructure and utilities supply activities progressing strongly:
− Phase 1 of permanent water supply pipeline installation approx. 16% complete.
• Strong quarter-end cash balance of A$89.3M and liquid assets valued at A$12.7M.
− Enables continued stage-gated approach to awarding early works contracts.
− Early works commitments stand at approx. A$42.1M (at 31 December 2025).
• Long-term uranium price outlook remains strong, with the term price increasing to
US$87/lb U3O8 by quarter end.
Bannerman Executive Chairman, Brandon Munro, commented:
“Bannerman continued to progress Etango’s early works programme during the December 2025
quarter, with key construction activities and delivery of long-lead equipment advancing in line with
schedule and budget. This progress reflects disciplined execution and effective leadership across the
project team as engineering and procurement activities continue to meet key milestones.
“Uranium market fundamentals strengthened further over the quarter. While spot pricing remained
volatile, long term price indicators improved and policy support is increasingly translating into reactor
life extensions, restarts, and new build commitments – reinforcing utility focus on long term supply
security. With advancing early works and a strong balance sheet, Bannerman is well positioned as
market conditions continue to align toward a targeted Final Investment Decision on Etango.”
Page 2 of 14
Etango Uranium Project (Bannerman 95% ownership)
Ongoing safety focus
On 7 October 2025, Bannerman achieved 16 years without a Lost Time Injury (LTI). Employees and
contractor personnel celebrated this achievement at the Etango construction site.
The contractor workforce on site has now increased to over 370 people, with the ramp-up of personnel
associated with the civil and aggregate mining, crushing and screening contracts progressing to
schedule.
Figure 1: On 7 October 2025, the Bannerman Mining Resources Namibia team and contract partners celebrated the
achievement of 16 years LTI-free.
Long lead construction activities and purchase orders
Bulk earthworks
The bulk earthworks contract now stands at approximately 51% complete and continues to advance
according to schedule.
The key focus area of this contract remains the construction of the heap leach pad.
Page 3 of 14
Figure 2: The heap leach pad earthworks continue to advance on schedule.
Heap leach pad drainage
The blasting, crushing and screening of heap leach drainage aggregate by local Namibian contractor,
Tulela Mining & Construction (Pty) Ltd, is advancing to schedule with drainage material being
stockpiled for later placement on the heap leach pad. The drainage aggregate has been confirmed as
being within the required specification.
Figure 3: Blasting, crushing and screening of the heap leach drainage material.
Page 4 of 14
Phase 1 and Phase 2A concrete contracts
The Phase 1 and Phase 2A concrete contracts were placed with K Neumayer Civil Contractors (Pty)
Ltd, a local Namibian contractor. The Phase 1 contract is for the construction of the primary crusher
structure. The Phase 2A contract is for the main concrete components of the dry plant, being the
stockpile tunnel, secondary and tertiary crushing and screening plants, the fine ore silo and the
associated conveyors.
These works have progressed well, and both the concrete bases of the primary crusher and the
stockpile tunnel have been successfully poured.
Figure 4: The first concrete pour at the primary crusher site has been completed. A total of 500m3 was poured at an
average flow rate of 40m3
per hour.
Page 5 of 14
Figure 5: The 1,200m3
concrete pour at the coarse ore stockpile tunnel is now complete.
Long lead items
The High-Pressure Grinding Rolls (HPGR) tertiary crusher has been successfully delivered to the
Etango site.
Figure 6: The HPRG tertiary crusher has arrived on site at Etango.
Page 6 of 14
Infrastructure and utilities supply
Water
The contract for the installation of Phase 1 of the permanent water supply pipeline is approximately
16% advanced and on schedule. The Namibian contractor, AN Construction cc, is currently focused
on the bases for the base pump station and the pipe bridge over the Swakop River.
The permanent water supply agreement has been reviewed by Bannerman and is now with Namwater
for finalisation.
Figure 7: The permanent water supply pipeline bridge base to cross the Swakop River is nearing completion.
Power
A definitive power supply agreement is in place with NamPower. Detailed design of the dedicated
feeder bay for Etango at NamPower’s Kuiseb substation has commenced.
The Engineering, Procurement and Construction Management (EPCM) consultant for these works is
expected to be appointed during Q1 2026.
Acid
Local Namibian consultant, Windhoek Consulting Engineers, is progressing detailed design of the acid
storage and handling facility at Walvis Bay port. On-site geotechnical activities commenced in October
2025.
Page 7 of 14
Detailed design
Design and procurement activities are advancing in line with the Etango Project schedule.
Detailed engineering is being done by Wood Group PLC (Wood), in collaboration with Bannerman’s
Namibian owner’s team, using certified vendor drawings obtained prior to finalising equipment orders.
The detailed model review (M2) by Wood and Bannerman for the dry plant was carried out over
September to November 2025 and comments captured during these sessions are being implemented.
This is set to allow the engineering team to submit the structural steel drawings and details for tender
of the structural, mechanical, piping and platework (SMPP) dry plant works during Q1 2026.
Dry plant
Civil and mechanical design for the dry plant has further advanced and is now approximately 92%
complete. The concrete drawings for both Phase 1 and Phase 2A have already been issued for
construction in line with schedule. The structural steel drawings are also now well advanced and on
schedule. This follows the achievement of the 3D model review milestone, which has allowed
associated updates to be incorporated and go to tender.
Figure 8: Dry plant detailed design drawings: Transfer point between primary crusher and overland conveyors.
Page 8 of 14
Figure 9: Dry plant detailed design drawings: Primary crusher installation.
Wet plant
Detailed design of the wet plant continues with the focus now being design validation test work. On
completion of this validation test work, focus will shift to completion of ‘issued for construction’ concrete
details and readiness for Phase 3 concrete works implementation. Structural steel drawings are then
set to follow for the SMPP works. In the interim, the earthworks terrace has commenced in the area
where the wet plant is to be located. Detailed engineering of the wet plant is now approximately 23%
complete.
Financing
The Etango financing process sees Bannerman evaluating and progressing various funding sources,
including project/corporate debt as well as potential offtake and joint venture opportunities with
strategic counterparties who can add value to Etango. As previously advised, Azure Capital and
Vermilion Partners (both global affiliates of French financial services institution, Natixis) are advising
on and assisting with the execution of the optimal funding mix for Etango.
This process continues to advance in line with overall project scheduling and requisite financial
commitment. The final choice of funding mix will be a direct function of the cost of various alternatives
weighed against respective requisite levels of offtake coverage (and key terms), covenants and
security.
Offtake marketing
Bannerman’s product marketing strategy is to progressively but flexibly secure a top-tier portfolio of
uranium sales agreements that align with long-term market fundamentals, while balancing price
exposure and revenue stability. This approach is underpinned by prevailing strong inbound interest
from nuclear power utilities and other market participants across key jurisdictions, reflecting Etango’s
strategic significance as a source of future supply diversification.
Page 9 of 14
Bannerman’s phased project development approach ensures that its offtake marketing activities are
aligned with project advancement and financial strategy, enabling the Company to effectively respond
to evolving market conditions while maintaining a strong position as a future supplier of choice in the
global uranium sector. Consistent with such an approach, it is anticipated that offtake commitments for
Etango will be progressively ‘layered in’ to an expanding sales portfolio over time, in line with ongoing
anticipated strengthening in term uranium market fundamentals.
The Company continues to actively engage with a broad range of utilities, financial institutions, traders,
and other key market participants. This follows the execution of two initial offtake agreements with Tier
1 utilities in September 2025 (refer Bannerman ASX release dated 5 September 2025).
Committed expenditure and project schedule
Bannerman continues to take a disciplined approach to project expenditure. As of 31 December 2025,
Bannerman has completed approximately A$48.5 million of Etango early works programs. Early works
commitments (as at 31 December 2025) total a further approximately A$42.1 million.
All key workstreams remain on track for a targeted positive FID on Etango, market conditions
permitting, during the next 6-12 months.
Corporate
Strong liquidity
Bannerman’s cash balance at 31 December 2025 was A$89.3 million (30 September 2025: A$111.8
million), with no debt (other than typical creditor balances) or convertible instruments.
As part of its treasury and future sales risk management activities, Bannerman also holds liquid assets,
in the form of units in the Sprott Physical Uranium Trust (SPUT). At 31 December 2025, the value of
liquid assets held by Bannerman was approximately A$12.7 million.
Cashflow disclosures
Total property, plant and equipment expenditure for the quarter was A$12.4 million, which relates
predominantly to the Etango early works programs. Total exploration and evaluation expenditure for
the quarter was A$7.1 million, primarily directed towards detailed design and early construction works
for Etango.
For the purpose of item 6.1 of Appendix 5B, aggregate payments during the quarter to related parties
totalled A$216,187 comprising directors’ fees and salaries.
Annual General Meeting
The Company held its Annual General Meeting on 13 November 2025, with all resolutions put to the
meeting passed by poll.
Cancellation and issue of securities
During the quarter, the Company issued and cancelled the following securities:
▪ Issue of Options: 687,082 unlisted Zero Exercise Price Options (ZEPOs) were granted in
accordance with the NEDSIP and EIP as approved by shareholders on 13 November 2025.
▪ Conversion of Performance Rights: 2,034,008 fully paid ordinary shares were issued upon
conversion of unlisted performance rights in accordance with the terms of the Employee
Incentive Plan (EIP).
Page 10 of 14
▪ Exercise of Options: 201,955 unlisted Zero Exercise Price Options (ZEPOs) were exercised
for NIL consideration in accordance with the terms of the EIP.
▪ Cancellation of Options: 33,997 unlisted employee performance options, pursuant to the
terms of the EIP, were forfeited and cancelled following non-satisfaction of the relevant
performance criteria.
Issued securities
At the date of this report, the Company has 207,670,532 fully paid ordinary shares and 2,734,054
unlisted options on issue. The options are subject to various performance targets and continuous
employment periods.
Strategic Holding in Namibia Critical Metals – Exercise of Warrants
Bannerman maintains a strategic shareholding in Namibia Critical Metals Inc. (TSX-V: NMI).
On 26 November 2025, the Company was issued a further 3,671,428 shares in Namibia Critical Metals
Inc. (NMI) following the exercise of 3,671,428 free-attaching warrants at an exercise price of C$0.05
per share. Subsequently, on 19 December 2025, the Company was issued a further 3,983,333 shares
in NMI following the exercise of 3,983,333 free-attaching warrants at an exercise price of C$0.10 per
share.
These transactions increased the Company’s interest in NMI from 43.0% to 43.5%.
Uranium Market
Quarterly update1
The uranium market maintained strong upward momentum through Q4 2025, supported by rising
global nuclear demand and persistent structural supply constraints. While spot prices softened toward
the end of December, closing the quarter at US$81.70/lb, they rebounded early in the new year,
exceeding US$85/lb by mid-January 2026. Despite continued spot volatility, long-term prices further
strengthened, ending the quarter at US$87.00/lb.
Expanding Reactor Pipeline Strengthens Uranium Demand Outlook
In October 2025, Brookfield Asset Management and Cameco Corporation announced a strategic
partnership linked to an estimated US$80 billion programme supporting deployment of 10-13
Westinghouse AP1000 reactors. Westinghouse has indicated an objective to have 10 AP1000 units
under construction by 2030. The scale, capital intensity, and long development timelines of the
programme reflected renewed confidence in large-scale Gen III+ reactor deployment in Western
markets.
Brookfield also resumed discussions with Santee Cooper regarding completion of the two unfinished
AP1000 units at South Carolina’s V.C. Summer site, indicating renewed consideration of previously
stalled projects.
In parallel, the United States and Japan announced a US$550 billion investment framework focused
on nuclear power and energy infrastructure. Japan indicated potential funding of up to US$332 billion
for U.S. projects, including prospective deployment of Westinghouse AP1000 and GE Vernova Hitachi
BWRX-300 reactors, alongside manufacturing expansion and grid modernisation. While not a
1
Uranium price references, including spot, term and historical series, are quoted from TradeTech and UxC. All other market
commentary is Bannerman’s synthesis of information monitored during the quarter from multiple industry and public sources, including
TradeTech, UxC, World Nuclear Association, IAEA, EIA, producer and utility disclosures, and government releases.
Page 11 of 14
construction mandate, the framework improved long-term capital availability and supply-chain
preparedness for future reactor deployment.
Long-term visibility was also enhanced by India’s passage of landmark nuclear legislation in December
2025, opening the sector to private and foreign participation. The reform enables private ownership
and operation of nuclear plants, allows foreign involvement through government-approved joint
ventures, and introduces capped, reactor-size-based nuclear liability with enhanced supplier
protections. These changes established a clearer framework for nuclear development as India targets
100 GW of nuclear capacity by 2047, implying investment requirements in excess of US$200 billion.
Newcomer Countries Signal Rising Nuclear Interest
Nuclear policy activity broadened beyond established markets during Q4 2025, with several newcomer
countries advancing early-stage civil nuclear initiatives. Ethiopia launched a nuclear energy
programme focused on potential development of a large-scale plant, while Mongolia continued
reviewing proposals for its first nuclear facility as a long-term response to power shortages and coal
dependence. Vietnam also indicated renewed intent to advance new-build planning. In Africa, Rwanda
and Senegal joined the pledge to triple global nuclear capacity by 2050 at COP30 in Belém. Namibia
approved its first national nuclear industry strategy, establishing a policy and regulatory framework to
support potential future nuclear power development. Together, these developments point to a widening
geographic base for long-term nuclear growth.
Reactor Life Extensions and Restarts
Regulatory and operator actions during Q4 2025 continued to support retention and recovery of existing
nuclear generation capacity across several key markets.
In the United States, Constellation Energy confirmed a US$1 billion U.S. Department of Energy loan
supporting the planned 2027 restart of the Crane Clean Energy Center (formerly Three Mile Island Unit
1). In total during 2025, the U.S. Nuclear Regulatory Commission authorised 13 reactor licence
renewals, preserving approximately 12 GWe of existing nuclear capacity.
In Europe, Operators of the Almaraz Nuclear Power Plant submitted a request to extend the operating
licences of Units 1 and 2 to 2030, initiating a formal review of Spain’s 2019 nuclear phase-out schedule,
which currently sets closures for 2027 and 2028.
In Asia, authorities in Japan approved restarts at the Kashiwazaki-Kariwa Nuclear Power Plant Units
6 and 7 and at Tomari Unit 3, continuing the phased return of previously idled capacity. South Korea
also approved a 10-year licence extension for the Kori Nuclear Power Plant Unit 2, extending operation
through April 2033.
In Africa, the operating licence for Koeberg Nuclear Power Station Unit 2 was extended by 20 years,
following a similar approval for Unit 1 in 2024, securing continued operation of the continent’s only
nuclear power station.
Investment Funds Continue to Tighten Physical Uranium Supply
Physical uranium investment vehicles continued to purchase material volumes from the spot market in
2025. By year end, the Sprott Physical Uranium Trust held 74.8 Mlbs of U₃O₈, having acquired 8.57
Mlbs of U₃O₈ from the market during the year. Yellow Cake plc increased its holdings to 23 Mlbs of
U₃O₈, including volumes acquired through the exercise of its 2025 Kazatomprom purchase option. The
continued accumulation of physical uranium by investment vehicles remained a notable factor in
tightening available spot supply during the year.
Hyperscalers Expand Nuclear Power Commitments for AI Growth
Rising hyperscaler demand for reliable, long-duration electricity translated into new nuclear power
commitments during Q4 2025. Meta Platforms reinforced its long-term nuclear strategy through
agreements with Vistra, a large U.S. power producer with a substantial nuclear portfolio, and advanced
reactor developers TerraPower and Oklo, to support AI data-centre expansion. The agreements are
expected to secure up to 6.6 GW of clean energy by 2035 for Meta’s 1-GW Prometheus campus in
Page 12 of 14
New Albany, Ohio, including Natrium reactors, power from existing and uprated nuclear plants, and a
planned Oklo nuclear campus. The commitments build on Meta’s earlier 20-year nuclear power
contract with Constellation Energy in Illinois.
Comparable demand signals were reflected in U.S. utility planning. NextEra Energy advanced plans to
restart the 615 MW Duane Arnold Energy Center under a 25-year power purchase agreement with
Google to supply expanding cloud and AI operations. The plant is targeted to return to service by Q1
2029, subject to regulatory approval, and the partners also indicated interest in additional U.S. nuclear
projects.
This ASX release was authorised on behalf of the Bannerman Board by:
Brandon Munro, Executive Chairman
29 January 2025
Contact
Investors:
Emma Culver
Investor Relations Manager
T: +61 8 9831 1436
eculver@bmnenergy.com
Media:
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of the Company, the Directors, and the management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting, or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
Page 13 of 14
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development business listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1. In December 2022, a Definitive
Feasibility Study (DFS)2 was completed on the Etango-8 Project, confirming to a definitive-level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput (for average annual output of 3.5 Mlbs U3O8). In March 2024, a scoping study3
demonstrated the capacity to expand annual production to 6.7 Mlbs U3O8.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore. All environmental approvals have been received for the
proposed Etango mine and external mine infrastructure, based on a 12-year environmental baseline.
Bannerman was awarded the Mining Licence for Etango in December 2023 and is progressing all key project
workstreams towards a targeted positive Final Investment Decision (FID) in parallel with strengthening long-
term uranium market fundamentals.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda. The Bannerman team has
ample direct experience in the development, construction and operation of uranium projects in Namibia, as
well as extensive links into the downstream nuclear power industry.
Bannerman has long established itself as an Environmental, Social and Governance (ESG) leader in the
uranium and nuclear energy sector. It is also a leader within Namibia on social development and community
engagement and exercises best-practice governance in all aspects of its business. This was recognised
with receipt of the 2023 African Mining Indaba’s ESG Award for Community Engagement.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
3. Refer to Bannerman’s ASX release dated 18 March 2024, Etango-XP and Etango-XT Scoping Study.
Page 14 of 14
Forward Looking Statements
The information in this announcement is not intended to guide any investment decisions in Bannerman
Energy Ltd. This material contains certain forecasts and forward-looking information, including possible
or assumed future performance, costs, production levels or rates, reserves and resources, prices and
valuations and industry growth and other trends. Such forecasts and information are not a guarantee
of future performance and involve many risks and uncertainties, as well as other factors. Actual results
and developments may differ materially from those implied or expressed by these statements and are
dependent on a variety of factors. The Company believes that it has a reasonable basis for making the
forward-looking statements in the announcement, based on the information contained in this and
previous ASX announcements.
Bannerman is not aware of any new information or data that materially affects the information included
in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply
and have not materially changed.
Competent Person’s Statement
The information in this announcement as it relates to Exploration Results is based on, and fairly
represents, information and supporting documentation prepared by Mr Marthinus Prinsloo. Mr Prinsloo
is a full-time employee of Bannerman Energy Ltd and is a Member of the Australasian Institute of
Mining and Metallurgy (AusIMM). Mr Prinsloo has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration, and to the activities, which he is undertaking.
This qualifies Mr Prinsloo as a “Competent Person” as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ and a Qualified
Person as defined by Canadian National Instrument 43-101. Mr Prinsloo consents to the inclusion in
this announcement in the form and context in which it appears. Mr Prinsloo holds shares and
performance rights in Bannerman Energy Ltd.
Listing Rule 5.3.3 Tenement Schedule:
BANNERMAN ENERGY LTD CONSOLIDATED BASIS
SCHEDULE OF INTERESTS IN MINING TENEMENTS
Project
Mining tenements
held
Location of
tenements
Beneficial %
interest at end of
the quarter
Change in the
quarter
Etango