Quarterly Activities Report
Released
Released
Announcement PDF
Bannerman Energy Ltd W bannermanenergy.com
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008 T +61 8 9381 1436
PO Box 1973, Subiaco, Western Australia 6008 E info@bmnenergy.com
Quarterly Activities Report
FOR THE PERIOD ENDED 30 JUNE 2026
Bannerman Energy Ltd (ASX: BMN, OTCQX: BNNLF, NSX: BMN) (Bannerman or the Company)
is pleased to report on continued strong progress in both the early works program at the Etango
Uranium Project (Etango or Etango Project) and towards completion of the transformational strategic
financing transaction with CNNC Overseas Limited (CNOL).
HIGHLIGHTS
Strategic financing
• Progressive satisfaction of key conditions precedent (CPs) for the CNOL strategic
investment (of up to US$321.5 million) and joint venture agreement.
• Satisfaction of residual CPs and transaction completion expected during Q3 2026;
a positive Final Investment Decision (FID) on Etango is targeted shortly thereafter.
Etango early works progress
• Early works construction activities tracking to overall budget and schedule:
‒ Contractor workforce on site exceeds 560 personnel and 1.1 million LTI-free hours
achieved on the project to date.
‒ Bulk earthworks contract advancing in line with schedule with approx. 92%
complete; focus remains the freshwater pond, wet plant terraces and leach pad.
‒ Production of heap leach drainage aggregate continues to deliver on-spec material,
with approx. 29% of total requirement completed.
‒ Concrete construction activities continue across key dry plant infrastructure areas,
with major processing facilities now beginning to take shape; total of 10,800m3
concrete has been cast, representing approx. 60% of the Phase 1 and 2A packages.
• Detailed design and procurement activities on schedule:
‒ Civil and mechanical design for dry plant approx. 94% complete and aligned with
schedule requirement for issue of construction drawings.
‒ Wet plant design also remains aligned with schedule requirement for issue of
construction drawings later this year.
• Long-term infrastructure and utilities supply activities progressing strongly:
‒ Permanent water supply agreement executed with NamWater.
‒ Phase 1 of permanent water supply pipeline installation now approx. 87% complete.
Corporate and market
• Strong quarter-end cash balance of A$53.1M and liquid assets valued at A$11.5M.
• Long-term uranium price outlook remains strong, with the term price increasing to
US$97/lb U3O8 (+US$4/lb) by quarter end.
Page 2 of 13
Bannerman Managing Director and Chief Executive Officer, Gavin Chamberlain, commented:
“The June quarter further demonstrated the discipline and methodical approach being applied to the
development of Etango. Early works continue to track to overall schedule and budget, reflecting the
capability of our project team and contractors, and the strong focus on execution risk that underpins
every stage of the development programme.
“At the same time, we continue to make good progress towards completion of the CNOL strategic
investment and joint venture transaction. Our engagement with CNOL has been highly constructive
and collaborative, reinforcing the strong alignment between the parties and our shared commitment to
the successful development of Etango.
“With the project footprint increasingly visible on site, engineering and infrastructure activities
advancing to plan, and a clear pathway towards transaction completion and FID, Etango continues to
build momentum from a position of strong project readiness.”
CNOL Strategic Financing
Transaction background
During the March quarter, Bannerman executed landmark binding investment subscription and joint
venture documentation with CNOL for the funding, development and operation of the Etango Project
(refer Bannerman ASX release dated 12 February 2026, Etango Strategic Financing with Global
Nuclear Utility, CNNC).
CNOL is a subsidiary of Shenzhen Stock Exchange listed China National Uranium Corporation (CNUC)
and part of leading integrated global nuclear utility, China National Nuclear Corporation (CNNC).
The transaction provides Bannerman with a clear, debt-free pathway to fund construction of Etango,
reducing financing risk while preserving meaningful offtake and financial flexibility. It also establishes
a strongly aligned long-term partnership with CNOL, supported by pro rata project funding and market-
based offtake for 60% of production with a Tier-1 nuclear industry partner.
The binding documentation with CNOL provides for:
1. Formation of an incorporated joint venture through Bannerman’s UK subsidiary, Bannerman
Energy (UK) Ltd (JVCo), by way of CNOL’s subscription for newly issued shares in JVCo, resulting
in JVCo ownership of 55% by Bannerman and 45% by CNOL upon completion. JVCo holds a 95%
interest in the Etango Project.
2. Initial investment of US$294.5 million by CNOL into JVCo upon completion.
3. Provision for additional investment by CNOL of up to US$27 million upon completion, to reimburse
Bannerman for CNOL’s 45% share of project-related expenditure incurred between 1 July 2025
and completion. These funds will be paid directly to Bannerman and will therefore be available to
it (including to meet its 55% share of any future funding and/or working capital requirements).
4. Life-of-mine offtake entitlement for CNOL covering 60% of actual production from Etango.
The key agreements supporting the transaction are:
• Share Subscription Agreement (SSA), which details the mechanics of CNOL’s investment into
JVCo; and
• Shareholders Agreement (SHA), which will be executed upon completion of the share
subscription and sets out the governance principles for JVCo (and its subsidiaries) as well as
key offtake terms.
A full-form offtake agreement (based on the binding offtake terms set out in the SHA) is to be
documented post-completion and prior to the commencement of production from Etango.
Page 3 of 13
Progress update
During the June quarter, Bannerman and CNOL worked collaboratively through the established
transaction Steering Committee, supporting coordination across technical, commercial and
governance workstreams ahead of completion. Engagement with relevant regulatory authorities and
other stakeholders also continued.
Completion of the SSA is subject to satisfaction (or waiver, as applicable) of the following CPs (with
the current status of these CPs, as endorsed by the Steering Committee, also noted):
• Completion of filings with the relevant Chinese government authorities (NDRC and Ministry of
Commerce) and foreign exchange registration (in progress);
• CNUC shareholder approval (satisfied);
• Receipt of clearance from the Namibian Competition Commission (satisfied);
• Requisite amendment to the OEF funding agreement to reflect new proportionate ownership
of JVCo (satisfied);
• Execution of key Etango Project infrastructure supply contracts (satisfied); and
• Customary conditions that any other regulatory approvals jointly determined by the parties to
be required are obtained and no legal or regulatory restraint being issued or made by any court
preventing completion of the transaction (satisfied and/or no restraint).
Satisfaction of residual CPs followed by transaction completion is expected during Q3 2026.
In parallel, the Etango early works programme continued to advance during the quarter (see section
below), maintaining project momentum. Site early works, detailed engineering, procurement and long
lead infrastructure activities continued in accordance with the approved development schedule,
supporting Etango’s readiness for targeted FID following completion of the CNOL transaction.
Etango Uranium Project (Bannerman 95% ownership)
Ongoing safety focus
The contractor workforce on site exceeds 560 personnel across four Namibian contractors delivering
earthworks, civil construction, aggregate production and infrastructure works.
During May 2026, the Bannerman Mining Resources Namibia team and its contract partners achieved
the significant milestone of one million LTI-free hours on the Etango Project. This achievement extends
Bannerman's unbroken LTI-free record and reflects the strong safety culture embedded across all
project activities.
Safety leadership initiatives, workforce engagement programmes and ongoing awareness campaigns
continue to reinforce Bannerman’s proactive approach to risk management and safe work practices.
Long lead construction activities and purchase orders
Manufacturing instructions: Long lead items
Five additional instructions to commence manufacturing of mechanical items for the dry plant area
were issued during the quarter. These orders were previously placed to secure vendor data for design
purposes. The manufacturing and delivery of this equipment is aligned with current schedule
requirements.
Page 4 of 13
Bulk earthworks
The bulk earthworks contract continues to advance in line with schedule and budget expectations and
stands at approximately 92% complete.
Activities remain concentrated on the heap leach pad and associated process solution ponds, while
work on the wet plant terraces has continued to expand. As these areas become increasingly defined,
the overall project footprint is becoming clearly visible across the site.
Figure 1: In addition to the heap leach pad earthworks, works have continued on the wet plant terraces and solution
ponds.
Heap leach pad drainage aggregate
Production of heap leach drainage aggregate continues to deliver material that meets required
specifications. Blasting, crushing and screening by local Namibian contractor, Tulela Mining &
Construction (Pty) Ltd, remains well coordinated with the broader construction programme and
stockpiles continue to build ahead of future placement on the heap leach pad.
Aggregate production has reached approximately 29% of total volume required and remains an
important enabling activity supporting future heap leach pad construction.
Phase 1 and Phase 2A concrete contracts
Concrete construction activities by local Namibian contractor, K Neumayer Civil Contractors (Pty) Ltd,
continue across key dry plant infrastructure areas, with major processing facilities now beginning to
take shape across the Etango Project site.
The Phase 1 contract covers construction of the primary crusher structure, which forms the first stage
of the processing circuit. Works have continued to advance with foundations complete and structural
concrete elements progressing above ground level.
Page 5 of 13
Figure 2: Below ground level view of the primary crusher building structure that has reached above ground level.
The Phase 2A contract encompasses the concrete structures within the dry plant, including the
stockpile tunnel, secondary and tertiary crushing and screening facilities, the fine ore silo and
associated conveyor infrastructure. Construction activities across these areas continue to progress,
with the stockpile tunnel walls and wing walls advancing, while concrete works at the crushing and
screening facilities and fine ore silo continue in line with schedule.
Figure 3: Concrete structures for the secondary and tertiary screening progressing towards completion.
Page 6 of 13
As activity progresses across both phases, permanent infrastructure is becoming increasingly visible
on site, reinforcing the strong execution of the early works programme and the continued advancement.
Overall, approximately 60% of total concrete volume for these contracts has been poured, with a total
of 10,800m3
concrete cast so far.
Figure 4: Aerial view of the stockpile tunnel where the concrete roof and wing walls are advancing.
The gatehouse is also taking shape, with construction progressing on schedule and to the required
quality standards. As part of Bannerman's commitment to local procurement and economic
development, the gatehouse is one of several non-critical construction works subcontracted to local
Namibian-owned SME contractors, creating opportunities for smaller local businesses to contribute to
the development of Etango.
Figure 5: Aerial view of the Etango gate house being built by local Namibian-owned SME contractors.
Page 7 of 13
Infrastructure and utilities supply
Water
In early June 2026, Bannerman signed the definitive permanent water supply agreement for Etango
with NamWater. This agreement covers the requisite supply of water for operation of the initial Etango-
8 development (which is set to produce an average of 3.5 Mlbs U308 for 15 years).
Figure 6: Abraham Nehemia, CEO of NamWater and Bannerman Mining Resources Namibia Interim-CEO Danie van
Aswegen signing the definitive permanent water supply agreement.
Construction of Phase 1 of the permanent water supply pipeline continues to progress strongly, with
pipeline installation and associated infrastructure advancing across multiple work fronts. Fabrication of
the bridge across the Swakop River has commenced and all thrust blocks and structural concrete has
been completed. The final backfilling for underground pipe sections is in progress.
Namibian contractor, AN Construction cc, is undertaking this work, which is now at approximately 87%
of completion.
Figure 7: Installation of concrete pedestals for the permanent Etango water pipeline is underway.
Page 8 of 13
Power
A definitive power supply agreement with NamPower has been signed. Detailed design of the
dedicated feeder bay for Etango at NamPower’s Kuiseb substation is progressing.
The Engineering, Procurement and Construction Management (EPCM) consultant for these works is
now expected to be appointed during Q3 2026.
Acid
Detailed design activities for the acid storage and handling facility at Walvis Bay port continue to
advance. Local Namibian consultant, Windhoek Consulting Engineers, is progressing engineering and
design works, which are on schedule at approximately 69% complete. Supporting geotechnical
investigations and site development activities also continue to progress.
Figure 8: 3D model of the Acid Storage Facility at Walvis Bay Port, Namibia.
Detailed design
Dry plant
Civil and mechanical design for the dry plant is approximately 94% complete. The structural steel
drawings are well advanced and on schedule. Tenders for the structural, mechanical, piping and
platework (SMPP) were issued to the market in the quarter and adjudications are underway. Progress
remains aligned with the schedule requirement for issue of final construction drawings.
Figure 9: 3D modelling showing secondary and tertiary crushing bins. Figure 10: 3D model showing the agglomeration structure.
Wet plant
Focus is shifting to completion of ‘issued for construction’ concrete details and readiness for Phase 3
concrete works implementation. Structural steel drawings are then set to follow for the SMPP
(structural, mechanical, piping and platework) works.
In the interim, the earthworks terrace is progressing in the area where the wet plant is to be located.
Detailed engineering of the wet plant model is approximately 28% complete and remains aligned with
the schedule requirement for issue of some of the final concrete construction drawings later this year.
Page 9 of 13
Offtake marketing
Bannerman’s marketing strategy is designed to systematically build a portfolio of uranium sales
agreements with leading counterparties. This measured approach supports the Company’s long-term
objectives by balancing price exposure and revenue stability, optimising pricing opportunities, and
ensuring Bannerman remains agile and responsive to shifting market dynamics.
As announced in February 2026, and outlined above, the Company has agreed material terms for a
cornerstone offtake arrangement with CNOL, under which CNOL will purchase 60% of Etango
production on arm’s-length, market-based pricing terms. CNOL offtake volumes are priced based on a
combination of prevailing spot and term uranium price indices. Payment terms are considered to be
significantly superior to market standards and are expected to reduce required working capital.
Bannerman will retain responsibility for marketing the remaining 40% of production, which it intends to
place progressively over time with a diversified group of counterparties, under strict confidentiality ring-
fencing arrangements. This approach is consistent with the Company’s expectation of continued
strengthening in term uranium market fundamentals, supporting the disciplined layering of additional
offtake commitments.
Bannerman actively engages with a broad range of utilities, financial institutions, traders, and other key
market participants in relation to this residual offtake, building on the initial offtake agreements
executed with Tier 1 utilities in September 2025.
Committed expenditure and project schedule
The Company continues to take a disciplined approach to project expenditure. As of 30 June 2026,
Bannerman has completed approximately A$69.31
million of Etango early works programs. Early works
commitments (as at 30 June 2026) total a further approximately A$36.2 million.
All key workstreams remain on track for a targeted positive FID on Etango promptly following
completion of the CNOL strategic investment and joint venture transaction.
Corporate
Strong liquidity
Bannerman’s cash balance at 30 June 2026 was A$53.1 million (31 March 2026: A$69.9 million), with
no debt (other than typical creditor balances) or convertible instruments.
As part of its treasury and future sales risk management activities, Bannerman also holds liquid assets,
in the form of units in the Sprott Physical Uranium Trust (SPUT). At 30 June 2026, the market value of
liquid assets held by Bannerman was approximately A$11.5 million.
Bannerman also holds approximately 101.3 million shares in Namibia Critical Metals Inc (TSXV:NMI),
owner of the Lofdal Heavy Rare Earth Project in Namibia. At 30 June 2026, this shareholding had a
market value of approximately A$22.7 million.
1
Project expenditure is incurred by the Company’s Namibian subsidiary, which has a Namibian dollar (NAD) functional currency, with
the majority of costs denominated in NAD. These amounts are translated into Australian dollars (AUD) for reporting purposes.
Accordingly, reported AUD amounts are subject to exchange rate movements and may not directly reflect underlying activity during
the period. For the March quarter, the movement in reported expenditure includes an exchange impact of approximately A$1.7m.
Page 10 of 13
Cashflow disclosures
Total property, plant and equipment expenditure for the quarter was A$10.4 million, which relates
predominantly to the Etango early works programs. Total exploration and evaluation expenditure for
the quarter was A$8.2 million, primarily directed towards detailed design and early construction works
for Etango.
For the purpose of item 6.1 of Appendix 5B, aggregate payments during the quarter to related parties
totalled A$320,237, comprising directors’ fees and salaries.
Bannerman Mining Resources (Namibia) (Pty) Ltd finalised a VAT refund for the September to
December 2025 quarter of N$51.5 million (approx A$4.4 million) which is reflected as a positive cash
inflow of A$1.242 million under Administration and Corporate Costs for the quarter.
Cancellation and issue of securities
During the quarter, the Company issued the following securities:
§ Exercise of Options: 79,095 unlisted Zero Exercise Price Options (ZEPOs) were exercised for NIL
consideration in accordance with the terms of the EIP.
Issued securities
At the date of this report, the Company has 207,811,582 fully paid ordinary shares and 2,642,365
unlisted options on issue. The options are subject to various performance targets and continuous
employment periods.
Uranium Market2
Spot U₃O₈ prices remained relatively stable during the June 2026 quarter, opening at US$84.50/lb and
trading within a range of US$83.50/lb to US$87.00/lb. The spot price closed the quarter at US$85.25/lb,
with a quarterly average price of US$85.67/lb.
The long-term price reference continued to strengthen over the quarter, increasing from US$93.00/lb
at 31 March 2026 to US$97.00/lb at 30 June 2026. This movement reinforces the distinction between
a broadly range bound spot market and a firmer long-term contracting market, where utility
procurement remains focused on security of supply, counterparty reliability, jurisdiction and reduced
exposure to future spot price volatility.
This ASX release was authorised on behalf of the Bannerman Board by:
Gavin Chamberlain, Managing Director and Chief Executive Officer
27 July 2026
2
Uranium price references, including spot, term and historical series, are quoted from TradeTech and UxC.
Page 11 of 13
Contact
Investors:
Emma Culver
Investor Relations Manager
T: +61 8 9831 1436
eculver@bmnenergy.com
Media:
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of the Company, the Directors, and the management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting, or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
Page 12 of 13
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development business listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1
. In December 2022, a Definitive
Feasibility Study (DFS)2
was completed on the Etango-8 Project, confirming to a definitive-level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput (for average annual output of 3.5 Mlbs U3O8). In March 2024, a scoping study3
demonstrated the capacity to expand annual production to 6.7 Mlbs U3O8.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore. All environmental approvals have been received for the
proposed Etango mine and external mine infrastructure, based on a 12-year environmental baseline.
Bannerman was awarded the Mining Licence for Etango in December 2023 and is progressing all key project
workstreams towards a targeted positive Final Investment Decision (FID) in parallel with strengthening long-
term uranium market fundamentals.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda. The Bannerman team has
ample direct experience in the development, construction and operation of uranium projects in Namibia, as
well as extensive links into the downstream nuclear power industry.
Bannerman has long established itself as an Environmental, Social and Governance (ESG) leader in the
uranium and nuclear energy sector. It is also a leader within Namibia on social development and community
engagement and exercises best-practice governance in all aspects of its business. This was recognised
with receipt of the 2023 African Mining Indaba’s ESG Award for Community Engagement.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
Page 13 of 13
3. Refer to Bannerman’s ASX release dated 18 March 2024, Etango-XP and Etango-XT Scoping Study.
Forward Looking Statements
The information in this announcement is not intended to guide any investment decisions in Bannerman
Energy Ltd. This material contains certain forecasts and forward-looking information, including possible
or assumed future performance, costs, production levels or rates, reserves and resources, prices and
valuations and industry growth and other trends. Such forecasts and information are not a guarantee
of future performance and involve many risks and uncertainties, as well as other factors. Actual results
and developments may differ materially from those implied or expressed by these statements and are
dependent on a variety of factors. The Company believes that it has a reasonable basis for making the
forward-looking statements in the announcement, based on the information contained in this and
previous ASX announcements.
Bannerman is not aware of any new information or data that materially affects the information included
in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply
and have not materially changed.
Competent Person’s Statement
The information in this announcement as it relates to Exploration Results is based on, and fairly
represents, information and supporting documentation prepared by Mr Marthinus Prinsloo. Mr Prinsloo
is a full-time employee of Bannerman Energy Ltd and is a Member of the Australasian Institute of
Mining and Metallurgy (AusIMM). Mr Prinsloo has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration, and to the activities, which he is undertaking.
This qualifies Mr Prinsloo as a “Competent Person” as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ and a Qualified
Person as defined by Canadian National Instrument 43-101. Mr Prinsloo consents to the inclusion in
this announcement in the form and context in which it appears. Mr Prinsloo holds shares and
performance rights in Bannerman Energy Ltd.
Listing Rule 5.3.3 Tenement Schedule:
BANNERMAN ENERGY LTD CONSOLIDATED BASIS
SCHEDULE OF INTERESTS IN MINING TENEMENTS
Project
Mining tenements
held
Location of
tenements
Beneficial %
interest at end of
the quarter
Change in the
quarter
Etango
Mining Licence
(ML) 250
Namibia 95% -