Quarterly Activities Report
Released
Released
Announcement PDF
Quarterly Activities Report
FOR THE PERIOD ENDED 30 JUNE 2025
Bannerman Energy Ltd (ASX: BMN, OTCQX: BNNLF, NSX: BMN) (Bannerman or the Company)
is pleased to report on continued strong progress at its Etango Uranium Project (Etango) during the
quarter, with significant developments across a range of key workstreams. The Company is advancing
towards a targeted positive Final Investment Decision (FID) on Etango, market conditions permitting.
HIGHLIGHTS
Outstanding safety record with 1 million LTI-free manhours achieved in June.
Etango early works construction activities tracking in line with budget and schedule:
Construction power overhead infrastructure erected and connected to grid.
Installation of site water distribution infrastructure complete.
Heap leach pad bulk earthworks advancing well and excavation of leach ponds
commenced.
Detailed design work on Etango process plant progressing in line with schedule,
with dry plant engineering approximately 58% complete at quarter end.
Manufacture of key long lead item, High Pressure Grinding Rolls tertiary crusher,
on schedule, with factory acceptance testing set for September 2025.
Permanent power supply agreement in agreed form and awaiting final execution.
Successful A$85 million equity placement, significantly enhancing financial flexibility
in advancing Etango towards FID.
Following the institutional placement settlement in early July 2025, Bannerman held
cash and liquid assets of approximately A$140 million.
Residual Etango early works commitments of approximately A$23M (at 30 June 2025),
with further early works commitments expected over coming months.
Offtake marketing and development financing workstreams advancing well, with
competitive positioning and flexibility also enhanced via recent equity raising.
Long-term uranium price outlook remains positive, with the term price closing the
quarter steady at US$80/lb U3O8.
Bannerman Executive Chairman, Brandon Munro, commented:
"We continued to make excellent progress on the staged development of our Etango Project during
the quarter. Early construction works are advancing on schedule and on budget. Critically, this
development work is being undertaken safely and to extremely high construction standards.
“Our further strengthened cash balance is a powerful enabler for us to execute our streamlined strategy
of financing and constructing Etango. In saying this, we continue to maintain our disciplined approach.
Further early works commitments are expected to be made over coming months, in line with
Bannerman’s gated approach to project expenditure, reflecting strengthening term uranium market
fundamentals and advancement towards an optimised FID on the world-class Etango Project.”
Bannerman Energy Ltd
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008
PO Box 1973, Subiaco, Western Australia 6008
W bannermanenergy.com
T +61 8 9381 1436
E info@bmnenergy.com
Etango Uranium Project (Bannerman 95% ownership)
Outstanding safety record
Etango has now been operating for over 15 years without a lost time injury (LTI). During June 2025,
this resulted in Bannerman surpassing 1 million LTI-free manhours.
This is a tribute to the resolute safety focus of the Bannerman Mining Resources Namibia team, and
all the consultants and contractors dedicated to working safely with them.
Long lead construction activities
Bulk earthworks
The bulk earthworks contract for Etango was awarded in August 2024. Execution of this key 24-month
contract continues to advance according to schedule.
The terracing for the construction laydown, as well as secondary and tertiary crushers, has been
completed. The construction of the heap leach pad is advancing well, and the excavation of leach
ponds has also commenced.
Figure 1: Heap leach pad earthworks advancing strongly (inset: 3D rendering of plant design from same perspective)
Site access road
At quarter end, the Etango site access road was approximately 89% complete, ahead of schedule
against a planned progress to that point of approximately 79%, despite minor damage during the recent
rain event. The interlocking paving is nearing completion and all culverts placed. Current work in
execution is the widening of the intersection at the C28 intersection and the final backfilling around
culverts. Forecast completion of this contract is the end of Q1 FY26.
Page 2 of 11
Figure 2: Widening of C28 intersection entrance area to improve safety as vehicles enter site access road.
Figure 3: Site access parking area nearing completion.
Heap leach pad drainage
The contract for the blasting, crushing, and placement of the drainage layer on the Etango heap leach
pads has been placed in order to secure costs and supply of the mobile crushing equipment required
for the contract. The final contract, to commence with drilling, blasting and crushing, is to be placed
once the equipment is on site.
Page 3 of 11
Construction power
The contract for build of the construction power facilities was awarded in October 2024. The key
elements of these works included construction of all the permanent 33kV overhead powerlines on the
Etango site and the temporary connection to the local electrical distributor in the Erongo Region. These
elements have now been successfully completed and commissioned.
The mini sub-stations required to connect site offices to the power grid were delivered in June. All
residual work on this contract is expected to be completed during Q1 FY26.
Figure 4: Power grids on site now live with safety
precautions to prevent vehicles crossing under installed
lines
Figure 5: The first early works mini sub-station has
arrived on site.
Construction water
Installation of site water distribution infrastructure is complete, and the final pressure testing of the site
water network is set to be completed during Q1 FY26.
Long lead items
Manufacture of the High-Pressure Grinding Rolls tertiary crusher, a key identified long lead item for the
Etango process plant, commenced in May 2024 and remains ahead of schedule, with delivery forecast
for end of 2025. Factory acceptance testing is scheduled to be carried out in September 2025, at the
manufacturing facility in Germany.
Off-site infrastructure and utilities supply
Utility arrangements for the construction period have been fully secured, ensuring uninterrupted access
to both water and power throughout the build. Discussions around long-term supply for the operational
phase are progressing well and have reached an advanced point in line with the Etango development
timeline.
Water
A letter of intent was signed with NamWater in October 2024, securing the full operational water supply
for Etango’s initial 15-year mine life, following commercial discussions that began in 2021. A back-toback letter of intent was also signed between NamWater and the Erongo Desalination Plant operator
to secure the source supply.
The final step in this commercial process is execution of the binding supply agreement between
NamWater and Bannerman, which is planned to be signed upon Bannerman taking a positive Final
Investment Decision on Etango. The draft supply agreement is currently with NamWater for further
comments.
Page 4 of 11
The responsibility for the water line design and installation lies with Bannerman. The design for the
water line has been completed and the tenders for construction have been received. These tenders
are currently under adjudication.
Power
A commercial proposal for the permanent operational power supply to the Etango site has been
received from NamPower and accepted by Bannerman, reflecting a definitive supply solution agreed
between the parties. The full-form supply agreement is now in an agreed form, has been executed by
Bannerman and is pending final execution by NamPower.
The responsibility for the overhead power line design and installation lies with Bannerman. The design
has been completed and the preparation of tender documents and appointment of the consultant to
manage this process are the next steps.
Acid
The site lease agreement for the planned acid storage and import/export facility at Walvis Bay port has
been reviewed and sent back to Namport for finalisation. Bannerman has also submitted the
Environmental and Social Impact Assessment for this facility.
Detailed design
Detailed engineering is advancing steadily under the leadership of Wood Group PLC, in collaboration
with Bannerman’s Namibian owner’s team, using certified vendor drawings obtained prior to finalising
equipment orders. Progress now extends across both the dry and wet plants, with design and
procurement activities advancing in line with the Etango development schedule.
Dry plant
Civil and mechanical design for the dry plant has advanced significantly. Detailed modelling and Issued
For Construction concrete drawings are now complete for the primary crusher, stockpile tunnel and
secondary/tertiary crushing areas. This is aligned with Bannerman’s strategy of awarding the dry area
first for concrete construction.
Detailed engineering on the dry plant (inclusive of all disciplines) was approximately 58% complete at
quarter end.
Figure 5: Primary crushing design
Figure 6: Secondary and tertiary crushing build design
Page 5 of 11
Wet plant
Detailed review and confirmation of all process and mass balance calculations is in progress.
Mechanical layouts are largely complete. Mechanical procurement packages have been put to market
in line with design schedule requirements.
Detailed engineering on the wet plant (inclusive of all disciplines) was approximately 13% complete at
quarter end.
Financing
The Etango financing process sees Bannerman evaluating and progressing various funding sources,
including project/corporate debt as well as potential offtake and joint venture opportunities with
strategic counterparties who can add value to the Etango Project. As previously advised, Azure Capital
and Vermilion Partners (both global affiliates of French financial services institution, Natixis) are
advising on and assisting with the execution of the optimal funding mix for Etango.
This process continues to advance in line with overall project scheduling and requisite financial
commitment. The final choice of funding mix will be a direct function of the cost of various alternatives
weighed against respective requisite levels of offtake coverage (and key terms), covenants and
security.
Importantly, Bannerman’s recent A$85 million equity placement delivers substantial benefits to the
overall Etango financing workstream. These benefits include the further strengthening of competitive
positioning in this process, preservation of the Company’s ability to continue making early works
commitments in line with targeted project scheduling, and delivery of a significant reduction in the
residual development financing requirement for Etango.
Offtake marketing
Bannerman’s product marketing strategy is driven by a detailed understanding of utility requirements
and preferences. The Company continues to actively engage with a broad range of utilities, financial
institutions, traders, and other key market participants.
Bannerman’s well-established position with respect to offtake marketing is that it will preserve the longterm underlying value of Etango by only committing to contracting its planned uranium output on price
(and other terms) that are considered representative of long-term market fundamentals and producer
opportunity. It is anticipated that such offtake commitments will be progressively ‘layered in’ to an
expanding sales portfolio over time, in line with ongoing anticipated strengthening in term uranium
market fundamentals. In planned execution of such a strategy, Bannerman is now well advanced in
discussions with select top-tier utility counterparties in respect of several initial term contracts covering
limited volumes.
Committed expenditure and project schedule
Bannerman continues to take a disciplined approach to project expenditure. As of 30 June 2025,
Bannerman has completed approximately A$25 million of Etango early works programs. Residual early
works commitments (as at 30 June 2025) total a further approximately A$23 million.
Completion of the recent equity raising is a key enabler for further early works construction
commitments to be made over coming months. The initial focus of these further commitments is on the
contracts required to install the drainage layer on the heap leach pad and the concrete construction
contract for the primary crusher. These commitments are set to be made in line with Bannerman’s
gated approach to project expenditure, considering prevailing term uranium market dynamics and
relative progress in offtake contracting activities.
All key workstreams remain on track for a targeted positive FID on Etango.
Page 6 of 11
Corporate
Equity placement
On 26 June 2025, Bannerman announced that it had received firm commitments for a single tranche
placement to institutional and sophisticated investors of approximately A$85 million (before costs)
through the issue of approximately 26.6 million fully paid ordinary shares at an issue price of A$3.20
per share (Placement).
The Placement was strongly supported by existing shareholders and a selection of new, high-quality
domestic and global institutional investors. Settlement of the Placement occurred on Thursday 3 July
2025. The Placement utilised the Company’s existing issuance capacity under ASX Listing Rule 7.1.
Canaccord Genuity (Australia) Limited, Shaw and Partners Limited and Jett Capital Advisors LLC acted
as Joint Lead Managers and Joint Bookrunners to the Placement. Canaccord Genuity (Australia)
Limited acted as Global Co-Ordinator to the Placement. Euroz Hartleys Limited and Wallabi Group
acted as Co-Managers to the Placement.
Strong liquidity
Bannerman’s cash balance at 30 June 2025 was A$46.2 million (31 March 2025: A$68.8 million), with
no debt (other than typical creditor balances) or convertible instruments.
Following receipt of net funds from the equity placement announced on 26 June 2025 and settled on
3 July 2025, Bannerman’s cash balance as at 4 July 2025 was A$127.6 million.
As part of its treasury and future sales risk management activities, in late June Bannerman acquired
434,000 units in the Sprott Physical Uranium Trust (SPUT) at a total cost of approximately US$7.5
million (approx. A$11.5 million), as part of the bought deal financing that was announced by SPUT on
17 June 2025 and settled by Bannerman on 27 June 2025. At 30 June 2025, the value of this SPUT
holding was approximately A$12.5 million.
The ownership of SPUT units delivers a liquid synthetic physical uranium exposure that provides risk
management support to the Company’s product sales strategy, without significantly compromising
financial flexibility in the short and medium term. SPUT ownership provides a close proxy for physical
uranium ownership that, in Bannerman’s circumstances, offers a number of important advantages.
These include simplicity, liquidity, enhanced divisibility, and greater fungibility – all of which delivers
greater financial flexibility than owning physical uranium at converter storage facilities.
Cashflow disclosures
Total exploration and development expenditure for the quarter was A$10.0 million, primarily directed
towards detailed design and early construction works for Etango.
For the purpose of item 6.1 of Appendix 5B, aggregate payments during the quarter to related parties
totalled A$139,780 comprising directors’ fees and salaries.
Cancellation and issue of securities
Bannerman did not issue or cancel any securities during the quarter. Subsequent to quarter end, the
Company issued 26,562,500 new fully paid ordinary shares in settlement of the A$85 million equity
placement announced on 26 June 2025.
Issued securities
At the date of this report, the Company has 205,403,260 fully paid ordinary shares, 2,039,608 unlisted
performance rights, and 2,262,633 unlisted options on issue. The performance rights and options are
subject to various performance targets and continuous employment periods.
Page 7 of 11
Uranium Market
Quarterly update
Market Dynamics & Price Movements
The uranium spot market exhibited notable price movements and volatility over the quarter, opening at
US$64.00/lb and reaching a high of US$78.65/lb, before closing the period at US$78.50/lb. This was
primarily influenced by significant buying activity from financial entities, particularly the Sprott Physical
Uranium Trust (SPUT), which raised approximately US$200 million in June and subsequently acquired
around 2.05 million pounds U₃O₈. Long-term prices held steady around US$80.00/lb, supported by
consistent utility contracting and increased market engagement through various active Requests for
Proposals (RFPs).
Strategic Developments in Major Markets
China authorised construction for ten new reactors, continuing robust nuclear growth with projections
of nuclear capacity increases of 10 GW per annum, while Kazakhstan confirmed a construction site for
its inaugural nuclear plant, reflecting growing regional diversification. Europe's Euratom forecasted
demand to average 28 million pounds annually from 2025-2034, up from approximately 25 million
pounds annually at present. The growth outlook also remains strong in the Middle East, particularly in
the UAE and Saudi Arabia, driven by strategic energy diversification policies. Similarly, India's
ambitious nuclear expansion continues, supported by new reactor builds and increased investment
aimed at meeting rapidly growing electricity demands.
Geopolitical & Energy Security
Geopolitical issues notably impacted market stability, with Niger's government nationalising Orano's
Somair mine amid alleged contractual violations, intensified sanctions targeting Russian uranium
imports, ongoing conflict in Ukraine and tensions in the Middle East related to Iran’s nuclear
programme. These geopolitical dynamics reinforce the strategic value of secure and diversified
uranium supply sources, benefiting stable jurisdictions and projects such as Etango.
Small Modular Reactors (SMRs) & Technological Developments
Technological advancements included TVA’s progress on a GE Hitachi SMR at Clinch River,
Tennessee, and Estonia’s Fermi Energia advancing site selection for an SMR-based nuclear plant.
Additionally, Westinghouse partnered with Google Cloud, employing AI to streamline AP1000 reactor
construction and operations, illustrating significant technological strides in the nuclear sector.
Tech Industry Demand and Investment in Nuclear
Rising electricity demand from data centres and AI operations led tech giants Amazon, Microsoft, and
Google to actively pursue nuclear-generated electricity agreements. Google's commitment to investing
US$25 billion over two years in data centre infrastructure further underscored this growing sectoral
reliance on nuclear energy.
Regulatory Factors, Including Legislative and Policy Developments
Regulatory activities intensified, including the U.S. Senate's Sanctioning Russia Act of 2025, targeting
immediate curtailment of Russian uranium imports. U.S. President Trump's executive orders
streamlined reactor licensing and construction procedures, setting an 18-month maximum for Nuclear
Regulatory Commission (NRC) licensing decisions, aimed at accelerating new reactor deployments
before 2029. These executive orders also focused on boosting domestic nuclear fuel production,
reducing reliance on foreign supply chains, and reinforcing the U.S. position in international nuclear
energy markets.
Page 8 of 11
This ASX release was authorised on behalf of the Bannerman Board by:
Brandon Munro, Executive Chairman
29 July 2025
Contact
Investors:
Media:
Brandon Munro
Executive Chairman
T: +61 8 9831 1436
info@bmnenergy.com
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of the Company, the Directors, and the management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting, or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
Page 9 of 11
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development business listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1. In December 2022, a Definitive
Feasibility Study (DFS)2 was completed on the Etango-8 Project, confirming to a definitive-level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput (for average annual output of 3.5 Mlbs U3O8). In March 2024, a scoping study3
demonstrated the capacity to expand annual production to 6.7 Mlbs U3O8.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore. All environmental approvals have been received for the
proposed Etango mine and external mine infrastructure, based on a 12-year environmental baseline.
Bannerman was awarded the Mining Licence for Etango in December 2023 and is progressing all key project
workstreams towards a targeted positive Final Investment Decision (FID) in parallel with strengthening longterm uranium market fundamentals.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda. The Bannerman team has
ample direct experience in the development, construction and operation of uranium projects in Namibia, as
well as extensive links into the downstream nuclear power industry.
Bannerman has long established itself as an Environmental, Social and Governance (ESG) leader in the
uranium and nuclear energy sector. It is also a leader within Namibia on social development and community
engagement and exercises best-practice governance in all aspects of its business. This was recognised
with receipt of the 2023 African Mining Indaba’s ESG Award for Community Engagement.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
3. Refer to Bannerman’s ASX release dated 18 March 2024, Etango-XP and Etango-XT Scoping Study.
Page 10 of 11
Forward Looking Statements
The information in this announcement is not intended to guide any investment decisions in Bannerman
Energy Ltd. This material contains certain forecasts and forward-looking information, including possible
or assumed future performance, costs, production levels or rates, reserves and resources, prices and
valuations and industry growth and other trends. Such forecasts and information are not a guarantee
of future performance and involve many risks and uncertainties, as well as other factors. Actual results
and developments may differ materially from those implied or expressed by these statements and are
dependent on a variety of factors. The Company believes that it has a reasonable basis for making the
forward-looking statements in the announcement, based on the information contained in this and
previous ASX announcements.
Bannerman is not aware of any new information or data that materially affects the information included
in this ASX release, and Bannerman confirms that, to the best of its knowledge, all material
assumptions and technical parameters underpinning the estimates in this release continue to apply
and have not materially changed.
Competent Person’s Statement
The information in this announcement as it relates to Exploration Results is based on, and fairly
represents, information and supporting documentation prepared by Mr Marthinus Prinsloo. Mr Prinsloo
is a full-time employee of Bannerman Energy Ltd and is a Member of the Australasian Institute of
Mining and Metallurgy (AusIMM). Mr Prinsloo has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration, and to the activities, which he is undertaking.
This qualifies Mr Prinsloo as a “Competent Person” as defined in the 2012 Edition of the ‘Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ and a Qualified
Person as defined by Canadian National Instrument 43-101. Mr Prinsloo consents to the inclusion in
this announcement in the form and context in which it appears. Mr Prinsloo holds shares and
performance rights in Bannerman Energy Ltd.
Listing Rule 5.3.3 Tenement Schedule:
BANNERMAN ENERGY LTD CONSOLIDATED BASIS
SCHEDULE OF INTERESTS IN MINING TENEMENTS
Project
Mining tenements
held
Location of
tenements
Beneficial %
interest at end of
the quarter
Change in the
quarter
Etango
Mining Licence
(ML) 250
Namibia
95%
-