June 2015 Quarterly Activities Report
Released
Released
Announcement PDF
QUARTERLY ACTIVITIES REPORT
For the Period Ended 30 June 2015
During the June 2015 quarter, Bannerman Resources Limited (ASX:BMN, TSX:BAN, NSX:BMN) achieved a
significant milestone, notably the successful commissioning of the Etango Heap Leach Demonstration
Plant and completion of Phase 1 of the Demonstration Plant Program.
HIGHLIGHTS
Phase 1 results strongly support the assumptions and projections incorporated in the Definitive
Feasibility Study (“DFS”).
Post quarter end, commenced with Phase 2 of the Demonstration Plant Program.
Successfully completed A$2 million capital raising.
Cash balance as at 30 June 2015 was A$2.3 million.
On 15 July 2015 Bannerman announced the following positive results from Phase 1 of the Etango Heap
Leach Demonstration Plant Program:
Fast, high and uniform leach extraction on a 121.6 tonne sample – within 20 days average total
leach extraction of 94% for the four cribs (a type of testing not previously conducted) and 93%
for the columns (similar to that achieved in previous laboratory testing).
Uranium Extraction
– CRIB 1
– CRIB 2
– CRIB 3
www.bannermanresources.com
BANNERMAN RESOURCES LIMITED ABN 34 113 017 128
Corporate Office Unit 1 ■ 2 Centro Avenue ■ Subiaco Western Australia 6008
Post PO Box 1973 ■ Subiaco Western Australia 6904 T +61 8 9381 1436 F +61 8 9381 1068
– CRIB 4
Low sulphuric acid consumption – on average less than 16kg/tonne (compared with DFS
projection of 18kg/tonne).
Geotechnical stability - visual observations during the unloading of the cribs confirmed the
uniform percolation through the material, integrity of the agglomerate and geotechnical
stability of the heap.
The similar performance of the four larger scale (30 tonne sample) cribs to the eight (200kg
sample) columns may be an indication of potential upside related to the projection of the
previous column testing results to the full scale heap leach pad performance in the DFS.
Bannerman’s Chief Executive Officer, Len Jubber, said:
“The Company has made significant progress during the quarter with the successful commissioning of the
Heap Leach Demonstration Plant and the announcement of the exciting results from Phase 1 which
strongly support the assumptions and projections incorporated in the DFS. Post quarter end we
commenced Phase 2 which aims to replicate the results in Phase 1.”
“Further, the project optimisation work on the resource modelling and mine planning aspects of the DFS is
progressing well and it is anticipated that updated mineral resource and ore reserves estimates will be
released by the end of the December 2015 quarter.”
“The Etango Project continues to progress and remains one of the very few globally significant uranium
projects that can realistically be brought into production in the medium term. The Heap Leach
Demonstration Plant program further de-risks the Etango development path and will assist Bannerman
to attract JV / funding partners.”
Len Jubber
Chief Executive Officer
29 July 2015
For further information please contact:
Len Jubber
Chief Executive Officer
Perth, Western Australia
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Robert Dalton
Financial Controller & Company Secretary
Perth, Western Australia
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Spyros Karellas
Investor Relations
Toronto, Ontario, Canada
Tel: +1 416 800 8921
spyros@pinnaclecapitalmarkets.ca
About Bannerman - Bannerman Resources Limited is an ASX, TSX and NSX listed exploration and development company with
uranium interests in Namibia, a southern African country which is a premier uranium mining jurisdiction. Bannerman’s principal
asset is its 80%-owned Etango Project situated near Rio Tinto’s Rössing uranium mine, Paladin’s Langer Heinrich uranium mine
and CGNPC’s Husab uranium mine currently under construction. A definitive feasibility study has confirmed the technical,
environmental and financial (at consensus long term uranium prices) viability of a large open pit and heap leach operation at one
of the world’s largest undeveloped uranium deposits. In 2015, Bannerman is conducting a large scale heap leach demonstration
program to provide further assurance to financing parties, generate process information for the detailed engineering design
phase and build and enhance internal capability. More information is available on Bannerman’s website at
www.bannermanresources.com.
Page 2 of 7
ETANGO PROJECT (Bannerman 80%)
Definitive Feasibility Study (completed in 2012)
Bannerman completed a Definitive Feasibility Study (“DFS”) and Environmental and Social Impact Assessment
(“ESIA”) on the Etango project in 2012. The respective studies, as announced to the market on 10 April 2012,
confirmed the technical, economic and environmental viability of the project at historical term uranium prices. In
2012 Bannerman also received environmental approval for the Etango Project.
Heap Leach Demonstration Plant Program
The 18 – 24 month heap leach demonstration plant program, which commenced in April 2015, is an integral step of
the project’s detailed engineering and financing phases.
It is specifically aimed at demonstrating the design and projected performance reflected in the DFS, further
enhancing the project knowledge and pursuing value engineering. The results to date have already gone a significant
way towards achieving these objectives.
On 15 July 2015, Bannerman reported on the key observations, results and preliminary conclusions from Phase 1 of
the Etango Heap Leach Demonstration Plant Program:
1.
Demonstrating the design and projected performance reflected in the DFS
Fast and high average leach extraction of 94% for the cribs and 93% for the columns, within 20
days. The column results were similar to that obtained in previous laboratory testing but the crib
results were better than anticipated (refer second bullet point under heading “3. Pursuing value
engineering” below).
Average sulphuric acid consumption approximately 16kg/tonne (compared with DFS projection of
18kg/tonne).
Visual observations during the unloading of the cribs confirmed uniform percolation through the
material, integrity of the agglomerate and geotechnical stability of the heap.
Testing confirms the simple chemistry and efficient leaching nature of the granite host rock and
uranium mineralisation.
2.
Further enhancing project knowledge
Designed, permitted, constructed and successfully commissioned large scale demonstration plant.
Gaining operating experience including safe handling of sulphuric acid, etc.
Building an understanding of the process control and metallurgical accounting issues associated
with the specific characteristics of the Etango deposit and design flowsheet.
Dramatically increased the metallurgical database through testing of 120 tonnes of ore in 4
separate crib tests and 1.6 tonnes of material in 8 column tests.
3.
Pursuing value engineering
Rapid and uniform percolation without signs of flooding, coupled with rapid and high leach
extraction at a larger scale point towards the potential to further optimise the heap leach
configuration.
Surprisingly no noticeable reduction in leach extraction performance was observed between the
larger scale cribs and the smaller columns. This poses the question as to the appropriate scale up
factors to be used in the detailed engineering of the heap leach operation. Further work is required
to address this matter.
A comprehensive description of the Heap Leach Demonstration Plant Program and the Phase 1 results are included
on the Company’s website.
Page 3 of 7
The following photographs highlight the substantial nature of the plant and demonstration program underway.
Blasted Alaskite Ore
Crib Loading
3,000t Crushed Ore Sample
Reagent Storage & Mixing
Agglomeration
Irrigation
Crib Loading
Pregnant Liquor Solution (PLS)
Project Optimisation
In addition to the positive results from Phase 1, the project optimisation work on the resource modeling and the
mine planning aspects of the DFS is progressing well. It is anticipated that updated mineral resource and ore reserve
estimates will be released by the end of the December 2015 quarter.
Page 4 of 7
URANIUM MARKET
Key news flow during and post the quarter covered significant events in China, USA, Japan and India.
In China, the launching of State Power Investment Corporation (“SPIC”) following the successful merger of China
Power Investment Corporation and State Nuclear Power Technology Corporation created the third major state
owned enterprise focussing on nuclear energy. The other two are China National Nuclear Corporation (“CNNC”) and
China General Nuclear Power Corporation (“CGNPC”). The Chairman of SPIC stated at the launch “SPIC, CNNC and
CGNPC will enjoy strategic cooperation and healthy competition”. All three companies have a presence in Namibia.
The US Energy Information Administration (EIA) stated in its 2014 Uranium Marketing Report that the unfilled
uranium requirements of US utilities continues to rise and based on a survey is expected to be 10.4Mlbs (21%) in
2017, 33.5Mlbs (68%) in 2020 and 47.3Mlbs (90%) in 2024. The USA imports approximately 90% of its uranium.
The loading of fuel into the Sendai reactors in Japan commenced in July and the two reactors are expected to restart
operations in August and October 2015 respectively. Further in April, the Japanese cabinet reaffirmed the role of
nuclear in the future energy mix with the Strategic Energy Plan incorporating 20 – 22% nuclear energy by 2030.This
equates favourably with approximately 25% prior to the Fukushima incident.
In July an Indian government official stated that a proposal had been sent to Cabinet to stockpile 5,000 tonnes of
uranium with the cap likely to increase in coming years. This follows recent announcements regarding uranium
offtake related agreements with Canada, Australia and Kazakhstan.
Another significant future supply shock occurred in May, when Energy Resources of Australia announced that the
company would not proceed with the Ranger underground mine feasibility study in the current uranium price
environment. Majority shareholder Rio Tinto subsequently announced that they would not support the development
of the underground expansion.
Globally, there are currently 437 operable nuclear reactors and 66 under construction. China, currently the largest
constructor of new reactors, continues to ramp up its nuclear energy program in line with its stated goal of
increasing electricity generated from nuclear plants from 23 GW currently to 58 GW by 2020 and 150 GW by 2030. In
terms of reactors, China have 26 reactors in operation, 24 under construction and 180 on order, planned or
proposed.
CORPORATE
Project Financing
The continued support of Resource Capital Funds (“RCF”) as a strategic cornerstone investor in Bannerman, from the
initial investment by Resource Capital Fund IV L.P. (“RCFIV”) in 2008 to the continuing investment by Resource
Capital Fund VI L.P. (“RCFVI”) is a beneficial and positive progression of RCF's confidence in Bannerman.
The opportunity to progress the heap leach demonstration plant program, stemming from prior completion of the
DFS, provides Bannerman with a competitive advantage by favourably positioning the Etango Project for fast track
development in a rising uranium price environment.
The results from Phase 1 of the program strongly support the heap leach assumptions and projections incorporated
in the DFS, and hence therefore also the bankability of the project. The program scheduled for the coming quarters
will focus on similarly demonstrating the solvent extraction component of the flow sheet as well as on value
engineering opportunities identified to date.
Cash Position and Operating Expenditure
Bannerman successfully completed a A$2 million capital raising at an issue price of A$0.052 (C$0.049) per share via a
Share Purchase Plan and Shortfall Placements. Net operating cash outflow during the quarter totalled A$1.3 million.
Bannerman’s cash reserves as at 30 June 2015 totalled A$2.3 million (31 March 2015: A$1.7m).
Issued Securities
At the date of this report, Bannerman has 387,700,833 ordinary shares on issue.
During the quarter, Bannerman issued 4,734,246 shares to RCF in settlement of the March 2015 quarter RCFIV and
RCFVI convertible note interest charges.
Page 5 of 7
The Company issued 29,182,635 shares to participants in the Share Purchase Plan and the Shortfall Placements, to
existing shareholders RCFVI and City Natural Resources High Yield Trust Plc, following commitments of A$1.58
million. The remaining 9,278,845 shares (A$482,500) placement were issued to three directors, namely Ronnie
Beevor, Len Jubber and David Tucker, upon gaining the approval of the Company’s Shareholders at the Extraordinary
General Meeting held on 30 June 2015.
Subsequent to the quarter end, Bannerman issued 4,786,849 ordinary shares to RCF in settlement of the respective
RCFIV and RCFVI convertible note interest charges for the June 2015 quarter.
At 30 June 2015, Bannerman had on issue 20,075,211 performance and share rights and 9,963,600 unlisted share
options following the issue of 1,391,213 performance and share rights to employees and service providers in
accordance the terms of or on terms similar with the Employee Incentive Plan. The performance and share rights and
options are subject to various performance targets and continuous employment periods.
Schedule of Mining Tenements
The Bannerman Group currently holds Exclusive Prospecting Licence 3345 (“EPL”) in Namibia. An application to
renew the EPL, which expired on 26 April 2015, was lodged on 26 January 2015 and is expected to be renewed in due
course.
The delayed renewal is not deemed to be an issue as Regulation 71 (3) (a) from the Minerals (Prospecting and
Mining) Act (Act 33 of 1992) states “an exclusive prospecting license shall not expire during a period during which an
application for the renewal of such license is being considered, until such application is refused or the application is
withdrawn or has lapsed, whichever occurs first……” still applies.
No interests in mining tenements or any beneficial interests in farm-in or farm-out agreements were acquired or
disposed of during the quarter.
Contingencies
On 17 December 2008, the Company entered into a settlement agreement with Savanna Marble CC (“Savanna”)
relating to Savanna’s legal challenge to the Company’s rights to the Etango Project Exclusive Prospecting Licence.
Under the terms of the Savanna settlement agreement, the final tranche payment of A$500,000 and 4.0 million
ordinary shares is due to Savanna upon receipt of the Etango Project Mining Licence. An application was lodged in
December 2009 and as at 30 June 2015 the probability and timing of the grant of the Mining Licence is uncertain.
TECHNICAL DISCLOSURES
Certain disclosures in this report, including management's assessment of Bannerman’s plans and projects, constitute forward looking statements
that are subject to numerous risks, uncertainties and other factors relating to Bannerman’s operation as a mineral development company that
may cause future results to differ materially from those expressed or implied in such forward-looking statements. Full descriptions of these risks
can be found in Bannerman’s various statutory reports, including its Annual Information Form available on the SEDAR website, sedar.com.
Readers are cautioned not to place undue reliance on forward-looking statements. Bannerman expressly disclaims any intention or obligation to
update or revise any forward-looking statements whether as a result of new information, future events or otherwise.
The information in this report relating to the Ore Reserves of the Etango Project is based on information compiled or reviewed by Mr Harry
Warries in April 2012. Mr Warries is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Warries was employed by Coffey Mining
as an independent consultant to the Company at the time of the studies and public release of the results. As Mr Warries is now no longer
employed by Coffey Mining, Coffey Mining has reviewed this report and consent to the inclusion, form and content of the relevant information
herein from the original reports for which Mr Warries’ consent has previously been given. Mr Warries has sufficient experience relevant to the
style of mineralisation and types of deposits under consideration and to the activity which is being undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”, and a Qualified
Person as defined by Canadian National Instrument 43-101.
The information in this report that relates to Ore Reserves was prepared and first disclosed under the 2004 JORC Code. It has not been updated
since to comply with the 2012 JORC Code on the basis that the information has not materially changed since it was last reported. All material
assumptions and technical parameters underpinning the estimates of mineral resources continue to apply and have not materially changed.
All material assumptions detailed in this report and underpinning the production target and forecast financial information in the DFS (as previously
announced on 10 April 2012 and reported on 30 January 2014 in compliance with Listing Rule 5.16 and 5.17) continue to apply and have not
materially changed.
Page 6 of 7
APPENDIX
BACKGROUND ON ETANGO PROJECT (Bannerman 80%)
The Etango Project is one of the world’s largest undeveloped uranium deposits, located in the Erongo uranium
mining region of Namibia which hosts the Rössing and Langer-Heinrich mines and the Husab Project which is
currently under construction by the Chinese state owned enterprise, China General Nuclear Power Company
(CGNPC). Etango is 73km by road from Walvis Bay, one of southern Africa’s busiest deep-water ports through which
uranium has been exported for over 35 years. Road, rail, electricity and water networks are all located nearby.
Definitive Feasibility Study
Key outcomes from the DFS, as announced to the market on 10 April 2012, are as follows:
2004 JORC Code and NI 43-101 compliant Ore Reserves (at 100ppm cut-off) totalling 279.6Mt at an average
grade of 194ppm U3O8 for 119.3 Mlbs of contained U3O8;
Production of 7-9Mlbs U3O8 per year for the first five years and 6-8Mlbs U3O8 per year thereafter, based on an
average processing throughput of 20 Mt per annum and an average recovery rate of 86.9%, which would rank
Etango as a global top 10 uranium only mine;
Cash operating costs of US$41/lb U3O8 in the first 5 years and US$46/lb U3O8 over the life of mine;
At US$75/lb U3O8, the Etango Project generates operating cash flow of US$2.7 billion before capital and tax, and
free cash flow of US$923 million after capital and tax, based on 104Mlbs U3O8 life of mine production;
Pre-production capital cost of US$870 million; and
Minimum mine life of 16 years, with further extensions possible through the inclusion of measured and
indicated resources below the designed pit, and the conversion of existing inferred resources.
All material assumptions detailed in this report and underpinning the production target and forecast financial
information in the DFS (as previously announced on 10 April 2012 and reported on 30 January 2014 in compliance
with Listing Rule 5.16 and 5.17) continue to apply and have not materially changed.
Mining Licence
The Ministry of Environment and Tourism granted formal environmental approval for development of the Etango
Project to Bannerman in the September 2012 quarter. Bannerman also lodged the DFS with the Ministry of Mines and
Energy in the same quarter, in support of the existing Etango Mining Licence application.
Page 7 of 7