Macquarie Australia Conference 2026 Presentation
Released
Released
Announcement PDF
Bannerman Energy Ltd W bannermanenergy.com
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008 T +61 8 9381 1436
PO Box 1973, Subiaco, Western Australia 6008 E info@bmnenergy.com
ASX ANNOUNCEMENT
6 May 2026
Macquarie Australia Conference 2026 Presentation
Bannerman Energy Ltd (ASX:BMN, OTCQX:BNNLF, NSX:BMN) (Bannerman or the Company) is
pleased to release a copy of the presentation to be provided by Executive Chairman, Mr Brandon
Munro to delegates at the Macquarie Australia Conference being held from 5 to 7 May 2026 in Sydney,
Australia.
This ASX release was authorised by:
Brandon Munro, Executive Chairman
Contact
Investors:
Emma Culver
Investor Relations Manager
T: +61 8 9831 1436
eculver@bmnenergy.com
Media:
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of the Company, the Directors, and the management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting, or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
Etango: The World’s Next Uranium Mine
MACQUARIE AUSTRALIA CONFERENCE, MAY 2026
ASX:BMN, OTCQX:BNNLF AND NSX:BMN
Delivering Bannerman as a production business for the long-term:
Construction funded, strongly price leveraged, strategically partnered
2
Of the Mineral Resources scheduled for extraction and recovery in the Etango-8 Definitive Feasibility Study (DFS) and Etango-XP / XT Scoping Study (Scoping Study), 100% are classified as Measured or Indicated.
Bannerman Energy Ltd (Bannerman, the Company) confirms that there are no Inferred Resources included in the Etango-8 DFS or Etango-XP / XT Scoping Study production schedules.
The Mineral Resources underpinning the Ore Reserve and production target in the Etango-8 DFS (and the production target in the Etango-XP / XT Scoping Study) have been prepared by a competent person in accordance
with the requirements of the JORC Code (2012). The Competent Person’s Statement is found overleaf. For full details of the Mineral Resource estimate, please refer to the ASX release dated 6 December 2022, “Etango-8
Definitive Feasibility Study”. Bannerman confirms that it is not aware of any new information or data that materially affects the Mineral Resource estimate included in that release. All material assumptions and technical
parameters underpinning the Mineral Resource estimate in that ASX release continue to apply and have not materially changed.
This release contains a series of forward-looking statements. Generally, the words "expect," “potential”, "intend," "estimate," "will" and similar expressions identify forward-looking statements. By their very nature forward-
looking statements are subject to known and unknown risks and uncertainties that may cause our actual results, performance or achievements, to differ materially from those expressed or implied in any of our forward-looking
statements, which are not guarantees of future performance. Statements in this release regarding Bannerman’s business or proposed business, which are not historical facts, are forward-looking statements that involve risks
and uncertainties, such as Mineral Resource estimates, Ore Reserve estimates, market prices of metals, capital and operating costs, changes in project parameters as plans continue to be evaluated, continued availability of
capital and financing and general economic, market or business conditions, and statements that describe Bannerman’s future plans, objectives or goals, including words to the effect that Bannerman or management expects
a stated condition or result to occur. Forward-looking statements are necessarily based on estimates and assumptions that, while considered reasonable by Bannerman, are inherently subject to significant technical,
business, economic, competitive, political and social uncertainties and contingencies. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties.
Actual results in each case could differ materially from those currently anticipated in such statements. Investors are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date they
are made.
Bannerman has concluded that it has a reasonable basis for providing these forward-looking statements and the forecast information included in this ASX release. This includes a reasonable basis to expect that it will be able
to fund the development of Etango upon successful delivery of key development milestones as and when required. The detailed reasons for these conclusions are outlined in the ASX release dated 6 December 2022,
“Etango-8 Definitive Feasibility Study”, in the section titled, “Funding pathway”. While Bannerman considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be
correct or that the range of outcomes indicated by the DFS will be achieved.
To achieve the range of outcomes indicated in the DFS, pre-production funding in excess of US$353M will likely be required. There is no certainty that Bannerman will be able to source that amount of funding when required.
It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of Bannerman’s shares. It is also possible that Bannerman could pursue other value realisation
strategies such as a sale, partial sale or joint venture of the Etango Project. These could materially reduce Bannerman’s proportionate ownership of the Etango Project.
For full details of the Etango-8 DFS and Etango-XP / XT Scoping Study, please refer to ASX releases dated 6 December 2022, “Etango-8 Definitive-Feasibility Study” and 18 March 2024, “Etango-XP and Etango-XT Scoping
Study”. In addition, please refer to ASX release dated 11 June 2024, “Etango-8 FEED Complete and Costs Updated; Detailed Design Commenced”. Other than the updated capital and operating costs expressed in the 11
June 2024 release, Bannerman confirms that it is not aware of any new information or data that materially affects the information included in the releases of 6 December 2022 and 18 March 2024. All material assumptions
and technical parameters underpinning the estimates in those ASX releases continue to apply and have not materially changed.
CAUTIONARY STATEMENT
Important notices
3
Forward Looking Statements
This presentation includes various forward looking statements which are identified by the use of forward looking words such as
“may”, “could”, “will”, “expect”, “believes”, “intend”, “plan”, “estimate”, “anticipate”, “continue”, and “guidance”, or other similar
words and may include, without limitation statements regarding plans, strategies and objectives of management, anticipated
production or construction commencement dates and expected costs or production outputs. Statements other than statements of
historical fact may be forward looking statements. Bannerman believes that it has reasonable grounds for making all statements
relating to future matters attributed to it in this presentation.
Forward looking statements inherently involve known and unknown risks, uncertainties and other factors that may cause the
Company’s actual results, performance and achievements to differ materially from any future results, performance or
achievements. Relevant factors may include, but are not limited to, changes in commodity prices, foreign exchange fluctuations
and general economic conditions, increased costs and demand for production inputs, the speculative nature of exploration and
project development, including the risks of obtaining necessary licences and permits and diminishing quantities or grades of
resources or reserves, political and social risks, changes to the regulatory framework within which the Company operates or may
in the future operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel,
industrial relations issues and litigation. Investors should note that any reference to past performance is not intended to be, nor
should it be, relied upon as a guide to any future performance.
Forward looking statements are based on the Company and its management’s good faith assumptions relating to the financial,
market, regulatory and other relevant environments that will exist and affect the Company’s business and operations in the future.
The Company does not give any assurance that the assumptions on which forward looking statements are based will prove to be
correct, or that the Company’s business or operations will not be affected in any material manner by these or other factors not
foreseen or foreseeable by the Company or management or beyond the Company’s control.
Although the Company attempts to identify factors that would cause actual actions, events or results to differ materially from those
disclosed in forward looking statements, there may be other factors that could cause actual results, performance, achievements or
events not to be anticipated, estimated or intended, and many events are beyond the reasonable control of the Company.
Accordingly, readers are cautioned not to place undue reliance on forward looking statements. Actual results, values, performance
or achievements may differ materially from results, values, performance or achievements expressed or implied in any forward
looking statement. None of Bannerman, its officers or any of its advisors make any representation or warranty (express or implied)
as to the accuracy or likelihood of fulfilment of any forward looking statement, or any results, values, performance or achievements
expressed or implied in any forward looking statement except to the extent required by law.
Forward looking statements in this release are given as at the date of issue only. Subject to any continuing obligations under
applicable law or any relevant stock exchange listing rules, in providing this information the Company does not undertake any
obligation to publicly update or revise any of the forward looking statements or to advise of any change in events, conditions or
circumstances on which any such statement is based.
Competent Person Statement
The information in this release relating to the Mineral Resources and Ore Reserves was reported in accordance with the 2012
Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) and the
ASX Listing Rules in a release to the ASX dated 6 December 2022 titled “Etango-8 Definitive Feasibility Study”.
The Competent Person responsible for the reporting of the Mineral Resources in the release of 6 December 2022 is Mr Ian
Glacken, a Fellow of the Australasian Institute of Mining and Metallurgy.
The Competent Person responsible for the reporting of the Ore Reserves in the release of 6 December 2022 is by Mr Werner K
Moeller, a Member of The Australasian Institute of Mining and Metallurgy, a Member of the South African Institute of Mining and
Metallurgy and a Member of the Canadian Institute of Mining, Metallurgy and Petroleum.
Other than the additional information presented in its ASX release dated 11 June 2024 titled “Etango Feed Complete, Costs
Updated, Detailed Design”, Bannerman confirms that it is not aware of any new information or data that materially affects the
information included in the release of 6 December 2022, that all material assumptions and technical parameters underpinning the
estimates in that release continue to apply and have not materially changed, and that the form and context in which the Competent
Persons’ findings are presented have not been materially modified.
FORWARD LOOKING AND COMPETENT PERSON STATEMENTS
Important notices
4
Building Etango: the world’s next uranium mine
Funding and offtake solution: Transformational partnership with CNNC
ABOUT BANNERMAN ENERGY
Globally significant resource endowment with scale and scalability
Low technical risk with strong technical and commercial viability
Strong social licence to operate in Namibia, a proven uranium jurisdiction
Proven team with deep uranium experience
Early works construction advancing towards first production in 2028
5
ABOUT BANNERMAN ENERGY
Corporate snapshot
CAPITAL STRUCTURE
ASX share price (4 May 2026) A$4.08
Shares on issue 207.7 M
Market capitalisation A$847 M
Options and performance rights 2.7 M
Average daily volume (ASX 3-month) 1.4 M
SHARE PRICE (ASX: BMN)
SUBSTANTIAL SHAREHOLDERS (%)
MM Asset Management (11.8%)
Sprott Asset Management (11.1%)
Paradice (8.2%)
Global X (5.7%)
Other institutional (7.3%)
Board & Management (2.5%)
Retail (53.4%)
EQUITY ANALYST COVERAGE
BALANCE SHEET
Cash (at 31 Mar 26) A$70 M
SPUT holding (TSX:U.UN, as at 31 Mar 26) A$13 M
Nam. Critical Metals holding (TSXV:NMI, at 31 Mar) A$30 M
Debt Zero
$0.00
$1.00
$2.00
$3.00
$4.00
$5.00
$6.00
Apr-25
May-25
Jun-25
Jul-25
Aug-25
Sep-25
Oct-25
Nov-25
Dec-25
Jan-26
Feb-26
Mar-26
Apr-26
HNW / Retail (53.4%)
Transformational financing delivers
premier uranium exposure
FUNDING & OFFTAKE SOLUTUON
Construction funded with optimal finance solution
Majority ownership and debt-free execution pathway
Arm’s length, market-priced cornerstone offtake
Strategic partnership with global leader
6
With the stockpile tunnel foundation completed, focus now shifts to the tunnel and wing walls.
OVERVIEW OF CNNC GROUP
A Tier-1 global nuclear partner
7
7
Husab
Rössing
(68.6%)
Etango
Existing CNNC
Group Uranium
Mine Interests
in Namibia
Langer Heinrich
(25%)
A leading global integrated nuclear business group
27 commercial nuclear reactors in operation
One of the world’s largest consumers of uranium
Successful operation of nearby Rössing Mine since 2019
Clear potential to deliver substantial technical and economic
efficiencies
7
18 reactors under construction/approved
TRANSACTION OVERVIEW
Strategic partnership delivering debt-free
Etango funding
Binding transformational JV investment
– Subscription: US$294.5M cash into JVCo
– Reimbursement: up to US$27M cash to
BMN
Bannerman Energy Ltd
(ASX:BMN)
Bannerman Energy
(Netherlands) BV
Bannerman Energy
(UK) Ltd (JVCo)
Bannerman Mining Resources
(Namibia) (Pty) Ltd
Etango Project
CNNC Overseas Limited
(CNOL)
China National Nuclear
Corporation (CNNC)
China National Uranium
Corporation (CNUC)
One Economy Foundation
(OEF)
100%
55%
45%
95%
5% loan carried
100%
69.9%
Binding cornerstone offtake
– 60% of life-of-mine production
– Pricing based on future term and spot price
indices; no floors or ceilings
– Highly attractive payment and delivery terms
8
Delivers requisite construction funding for Etango
9
OPTIMISED FUNDING APPROACH
US$353M
Etango CBE pre-
production capital
cost estimate1
US$294.5M
CNOL investment
into JVCo at
completion3
1. Refer Bannerman ASX release dated 11 June 2024, “Etango-8 FEED Complete and Costs Updated; Detailed Design Commenced”
2. Forecast JVCo other spend and working capital requirement remains subject to ongoing refinement and review
3. SHA direct subscription proceeds for 45% interest in JVCo, payable at completion
4. SHA maximum 45% share reimbursement for project spend from 1 July 2025 to transaction completion, payable by CNOL to BMN at completion (US$27M)
5. Indicative gross capital and other works spend from 1 July 2025 to transaction completion (based on maximum 45% share reimbursement payable by CNOL to BMN at completion)
Etango pre-production
capital spent to 30 June
2025
US$10M
Etango / JVCo other
spend and working
capital requirement2
CNOL 45% share of
further requisite JVCo
contributions
BMN 55% share of
further requisite JVCo
contributions
Etango funding position
(unaudited, pro forma at completion) Indicative Etango
project works spend
by BMN from 1 July
2025 to completion
(based on grossed up
maximum CNOL
reimbursement)5
Maximum CNOL
reimbursement to
BMN for spend from 1
July 2025 to
completion (US$27M)4
US$60M
China dominates world reactor growth
10
WHY CHINA
China
Rest of
World
CNNC
Rest of
China
Source: Reactors under construction as per World Nuclear Association, Current & Future Generation
RU IN
ETANGO URANIUM MINE
Two stage development – Strong uranium price
leverage with low execution risk
11
11
11
Vast body of previous technical work across
resource drilling, geotechnical, metallurgical and
environmental studies
Conventional open pit mining and heap
leach processing
Proven management and technical team
with deep in-country and uranium operating
experience
Namibia a premier uranium jurisdiction with
expansion fully permitted
ETANGO-XP
6.7 Mlbs U3O8 output pa
Total Resource: 210.2Mt
ETANGO-8
3.5 Mlbs U3O8 output pa
Total Resource: 113.5Mt
INVESTMENT HIGHLIGHTS
Etango-8 – Stage One:
Early works underway,
operating by 2028
12
12
15 years
Initial mine life
8 Mtpa
Throughput capacity
113.5 Mt
Total ore throughput
87.8%
Processing yield
240 ppm
Average U3O8 head grade
3.5 Mlb
Average U3O8 output p.a.
12
US$35.8/lb
Cash opex excl royalties1
US$353M
Pre-production capex1
For full details of the Etango-8 DFS, please refer to ASX release dated 6 December 2022, “Etango-8 Definitive-Feasibility Study”. In addition, please refer to ASX release dated 11 June 2024, “Etango-8 FEED Complete
and Costs Updated; Detailed Design Commenced”. Other than the updated capital and operating costs expressed in the 11 June 2024 release, Bannerman confirms that it is not aware of any new information or data that
materially affects the information included in the 6 December 2022 release. All material assumptions and technical parameters underpinning the estimates in the 6 December 2022 release continue to apply and have not
materially changed. Note that the estimates presented on this slide incorporate the updated cost estimates from the Control Budget Estimate contained in the ASX release dated 11 June 2024. All estimates presented on
this slide are expressed on a 100% project basis and pre targeted CNOL transaction completion.
390
2,537
3,301
614
837
1,774
2,698
4,079
5,461
544
905
1,263
INVESTMENT HIGHLIGHTS
Outstanding base and expansion price leverage
Both Etango-8 and Etango-XP deliver outstanding forecast returns (100% basis)
13
1,500
3,000
4,500
6,000
-
Net cashflow (pre-tax, 15-year LOM)
US$95/lb
US$80/lb US$110/lb
US$M
400
800
1,200
1,600
-
Post-tax NPV (8%)
US$95/lb
US$80/lb US$110/lb
US$M
Etango-8 Etango-8 Etango-8 Etango-8 Etango-8 Etango-8
Etango-XP
Etango-XP
Etango-XP
Etango-XP
Etango-XP
Etango-XP
For full details of the Etango-8 DFS, please refer to ASX release dated 6 December 2022, “Etango-8 Definitive-Feasibility Study”; For full details of the Etango-XP and Etango-XT Scoping Study, please refer to ASX release
dated 18 March 2024, “Etango-XP and Etango-XT Scoping Study”. In addition, please refer to ASX release dated 11 June 2024, “Etango-8 FEED Complete and Costs Updated; Detailed Design Commenced”. Other than the
updated capital and operating costs expressed in the 11 June 2024 release, Bannerman confirms that it is not aware of any new information or data that materially affects the information included in the 6 December 2022
and 18 March 2024 releases. All material assumptions and technical parameters underpinning the estimates in the 6 December 2022 and 18 March 2024 releases continue to apply and have not materially changed. Note
that the estimates presented on this slide incorporate the updated cost estimates from the Control Budget Estimate contained in the ASX release dated 11 June 2024. All estimates presented on this slide are expressed on a
100% project basis and pre targeted CNOL transaction completion.
Husab
Langer Heinrich
Rossing
Etango
ABOUT BANNERMAN ENERGY
Licence to operate in Namibia, a
stable, highly established uranium
jurisdiction
14
14
Tumas
(Deep Yellow)
Recognised tier-one supplier to global utilities
45-years of uranium production and export
Three large-scale uranium mines; Top 3 global producer
Excellent infrastructure - port, rail and power
Clear mining code and strong rule of law
Strong community and social support for uranium
15
INVESTMENT HIGHLIGHTS
Proven management team with deep in-country and uranium
operating experience
Melvin Yeo | Chief Legal Counsel
• 25+ years’ experience in various legal roles
• Previous senior roles at Wesfarmers Limited & Corrs Chambers Westgarth
• Extensive transactional and operating experience around the world, including Namibia
Werner Ewald | Director - Namibia
• 30+ years' experience in the uranium, diamond and coal mining industries
• Previously was the Mine Manager at the Rössing uranium mine (Namibia)
• Namibian born & based in Swakopmund
• 30+ years’ experience as a chartered accountant
• Previous experience at BHP Iron Ore as global Financial Controller & Special Projects
• Deep M&A and project finance experience
Steve Herlihy | Chief Financial Officer & Joint Company Secretary
Olga Skorlyakova | Vice President, Market Strategy
• 25+ years’ experience in international business development, sales & market strategy
• Held executive roles within the nuclear fuel sector with AREVA (now Orano) & TENEX
• Recently led the WNA Fuel Report Working Group
• 30+ years in project development/construction & contracting
• Former Regional Director, Mining for AMEC (now Wood plc) and COO of Kore Potash
• Project Director for construction of Husab uranium mine
Gavin Chamberlain | Chief Executive Officer
Matt Horgan | Vice President, Corporate Development
• 14 years’ experience working across technical, marketing, commercial, Investor
relations, project development & corporate development/M&A.
• Recent and direct experience in African domiciled mineral assets
• Held executive & senior roles at Peak Rare Earths, Azure Capital & Alcoa
Jeff Pipe | Owner’s Team Project Manager
• 40+ years of project & construction management experience in Africa
• Worked in coal, gold, platinum & diamond mining (both surface & underground works)
• Managing director of Archway Projects for 20 years
Cindy Fraser | Owner’s Team Commercial Manager
• 30 years’ experience in commercial, contract & supply chain areas of major mining
projects, including in Southern Africa
• Vast knowledge of developing & implementing project systems & procedures, along
with contract management, procurement & logistics experience
Andre Alberts | Owner’s Team Technical Manager
• 13+ years’ experience in the mining industry, with an operational background in
hydrometallurgy
• Leading the team of engineers for owner engineering services
• Previously worked at Skorpion zinc refinery & Tschudi copper mine/heap leach
Danie van Aswegan | Interim Chief Executive Officer - Namibia
• 25 years in the mining industry spanning mining, engineering & project management
• High performer known for his passion for leadership & fostering a positive
organisational culture
• Most recently was Head of Projects and Technology Development and a member
of Exco at Debmarine Namibia – a global leader in marine diamond extraction
2026 H1: Early works program to continue
2026 H1: Progressive satisfaction of key CPs
Mid-2026: Transaction completion (targeted)
2026 H2: Etango Final Investment Decision
2026 H2: Full-scale Etango construction
2028: First Etango uranium production (targeted)
Etango FID targeted shortly after transaction
completion
16
TIMELINE AND NEXT STEPS
The primary crusher building foundations are complete with the first level walls complete.
ETANGO URANIUM MINE
Outstanding investment asymmetry ahead of
buoyant uranium price signals
17
17
17
Scale: Etango ore body +200Mlbs
Scalable: Phased development with initial
production readily scalable
Leverage: +90% production exposed to
ceiling free, market prices
Near-term production: early works
construction underway ahead of first
production in 2028
Construction funded: JV funding with strong
industry partner
Offtake enabled: Favourable payment terms
and flexibility from leading global uranium
consumer
Financially robust: No debt burden on mine
and strong balance sheet
De-risked simplicity: Low technical and
execution risk, ample capability, partner
synergies
18
CONTACT DETAILS
Phone: +61 8 9381 1436
Email: info@bmnenergy.com
@BannermanEnergy
@Brandon_Munro
Brandon Munro
Executive Chairman
Emma Culver
Investor Relations Manager
APPENDIX
One of the world’s largest,
most advanced uranium
development assets
Globally large-scale resource endowment
225 Mlbs U3O8 Etango-only Resources1,3
59.9 Mlbs Etango Ore Reserve3
Satellite deposits within trucking distance
Scale plus scalability
Mineral Resource Estimate (55ppm U3O8 cut-off)1,3
Resource category
Tonnes
(Mt)
Grade
(ppm U3O8)
Contained
U3O8 (Mlb)
Measured 32.4 201 14.3
Indicated 345.7 195 148.5
Inferred 140.6 200 62.0
Total 518.6 197 224.9
Mineral Resource Estimate (100ppm U3O8 cut-off)2,3
Resource category
Tonnes
(Mt)
Grade
(ppm U3O8)
Contained
U3O8 (Mlb)
Measured 26.6 226 13.3
Indicated 276.9 223 136.4
Inferred 112.5 230 57.1
Total 416.1 225 206.8
1. November 2021 Mineral Resource Estimate JORC (2012) reported within a US$75 pit shell, 55ppm U
3O8 cut-off
2. November 2021 Mineral Resource Estimate JORC (2012) reported within a US$75 pit shell, 100ppm U
3O8 cut-off
3. For full details of the Mineral Resources and Ore Reserve estimate and disclosures, please refer to ASX release
dated 6 December 2022, “Etango-8 Definitive-Feasibility Study”. The Mineral Resources underpinning the Ore
Reserve have been prepared by a competent person in accordance with the requirements of the JORC Code
(2012). The Competent Person’s Statement(s) are found in the section of this ASX release titled“Competent
Person’s Statement(s)”. Bannerman confirms that it is not aware of any new information or data that materially
affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed
19
20
APPENDIX
Etango-8 DFS and Etango-XP / XT Scoping Study
^ 5.9 Mlbs pa is LOM average Etango-XP output and 6.7 Mlbs pa is average Etango-XP output post expansion completion (after Year 5)
For full details of the Etango-8 DFS and Etango-XP / XT Scoping Study, please refer to ASX releases dated 6 December 2022, “Etango-8 Definitive-Feasibility Study” and 18 March 2024, “Etango-
XP and Etango-XT Scoping Study”. In addition, please refer to ASX release dated 11 June 2024, “Etango-8 FEED Complete and Costs Updated; Detailed Design Commenced”. Other than the
updated capital and operating costs expressed in the 11 June 2024 release, Bannerman confirms that it is not aware of any new information or data that materially affects the information included
in the releases of 6 December 2022 and 18 March 2024. All material assumptions and technical parameters underpinning the estimates in those ASX releases continue to apply and have not
materially changed.
20
Key Metrics Unit Etango-8 Etango-XP (second phase to 16 mtpa) Etango-XT (extended life at 8Mtpa)
Physicals
Total ore mined and processed Mt 113.5 210.2 210.2
Average strip ratio x 2.2 3.2 3.2
Average head grade ppm U3O8 240 234 234
Average annual output Mlbs U3O8 pa 3.5 5.9 / 6.7 ^ 3.5
Peak annual output Mlbs U3O8 pa 4.1 7.8 4.8
Total LOM Output Mlbs U3O8 52.6 95.2 95.2
Valuation, Returns and Key Ratios
LOM average uranium price US$/lb U3O8 65 80 95 65 80 95 65 80 95
US$/N$ N$ 19.28 19.28 19.28 19.28 19.28 19.28 19.28 19.28 19.28
NPV8 (post-tax, real basis, ungeared) US$M 162 390 614 175 544 905 197 484 767
NPV8 (pre-tax, real basis, ungeared) US$M 302 658 1014 339 911 1483 347 799 1251
IRR (post-tax, real basis, ungeared) % 14.1% 21.1% 26.7% 13.5% 22.7% 29.5% 15.7% 23.7% 30.0%
IRR (pre-tax, real basis, ungeared) % 17.5% 25.8% 32.6% 16.8% 27.4% 35.6% 19.1% 28.8% 36.7%
Payback (post-tax, from first prod.) Years 4 3 3 7 5 4 4 3 3
Pre-tax NPV / Pre-production capex x 0.9 1.9 2.9 1.0 2.6 4.2 1.0 2.3 3.5
Cashflow Summary
Sales revenue (gross) US$M 3,421 4,210 4,999 6,187 7,615 9,043 6,187 7,615 9,043
Total operating costs US$M 1,993 2,019 2,045 4,047 4,093 4,140 4,271 4