ASX ANNOUNCEMENT
25 September 2024
Etango Project Update
Bannerman Energy Limited (ASX:BMN, OTCQX:BNNLF, NSX:BMN) (Bannerman or the Company)
is pleased to advise of significant recent progress in the development of its Etango Uranium Project
(Etango Project or Etango).
KEY OUTCOMES
§ Etango mine development continuing, facilitated by recent equity raising and ‘phased
greenlight’ approach:
‒ Front-End Engineering and Design (FEED) and Control Budget Estimate (CBE)
completed in June, delivering significant de-risking of project development and
execution profile.
‒ Construction water supply and site access road early works completed in July –
safely, on time and on budget.
‒ Key 24-month bulk earthworks and construction power contracts awarded.
‒ Tertiary crusher (HPGR) order placed and manufacture commenced; plant detailed
design work advancing.
‒ Ongoing advancement of early works construction and long lead orders.
§ Etango financing process advancing across both project/corporate debt as well as
potential offtake and joint venture opportunities with strategic counterparties.
§ Long term contracting price continues to build, with tightening supply and rising demand
aligned with renewed interest in nuclear power.
§ Commitment to maximising Etango’s leverage to long-term uranium market
fundamentals by targeting offtake contracts that capture the full value of long-term
producer opportunity.
§ Window for targeted positive Etango Final Investment Decision (FID) expanded into 2025.
Commenting on these outcomes, Bannerman Chief Executive Officer, Gavin Chamberlain, said:
“I am pleased with the progress of our current early development works program. Our contract partners
have performed strongly and delivered their scopes effectively, with completion of the initial
construction water supply and site access road facilities earlier this quarter.
“We continue to exercise a gated approach to Etango development, with phased green lighting of
various construction works in-line with advancement across broader project workstreams and financial
capacity. This enables us to maintain critical path timelines whilst also allowing robust management of
execution and market risks.
“To this end, our recent equity raising has facilitated a rapid transition into the next phase of long lead
order and critical path contract awards for Etango. The bulk earthworks contract comprises a large,
lengthy body of work, the commencement of which maintains the Etango mine construction timeline.
The same goes for the commencement of manufacture of key plant items, including the High-Pressure
Grinding Rolls (HPGR), a key component of the Etango plant front-end.”
Bannerman Energy Ltd
Suite 7, 245 Churchill Avenue, Subiaco, Western Australia 6008
PO Box 1973, Subiaco, Western Australia 6008
W bannermanenergy.com
T +61 8 9381 1436
E info@bmnenergy.com
“The Etango financing progress is also advancing, comparing a broader range of conventional and
strategic funding opportunities that reflect growing interest in long-term uranium supply. With our
current robust cash balance, we can take the appropriate time in this area to ensure the optimal overall
funding mix is delivered – a key differentiating feature compared to many developers.
“I am also pleased to see long term contract markets firming further over the last few months. While
the market continues to come to us in this sense, it is also an excellent reminder that the judicious
exercise of patience can bring its rewards. Again, we have the financial runway to progress
development while ensuring our initial offtake contract book is established on terms that are truly
representative of long-term uranium market fundamentals – a strategy that we are firmly committed to
implementing.”
Etango Project Update
Early works and long lead construction activities
The first two early works contracts approved for the Etango Project – the construction water supply
and site access road – were completed in July; safely, on time and on budget. Bannerman thanks its
local contract partners on these projects for their strong and safe performance.
Figure 1: Completed access road to Etango site, showing the junction to the C28 tar highway
Following the completion of these early works, and the financial capacity delivered by the Company’s
recent equity raising, development of Etango has rapidly transitioned to the next phase of long lead
order and critical path contract awards. This approach is in-line with Bannerman’s gated, ‘phased
greenlight’ approach to the construction of the Etango Project.
Page 2 of 7
Figure 2: New culvert installed over the existing water supply pipelines
Figure 3: Completed construction water reservoir delivering 700m3 storage volume
Page 3 of 7
As previously announced, the Etango bulk earthworks contract has been awarded. This award is inline with the existing project schedule and is planned to be a 24-month contract (which lies on the
critical path schedule).
Figure 4: Bulk earthworks contractor’s camp, within Etango ML boundary, being established following contract award
The construction power contract has also been placed in-line with the project schedule. Further, the
construction contract for the roads within the Etango Mining Licence (ML) area has been awarded and
works are progressing ahead of schedule.
The contract for the blasting, crushing, and placing of the drainage layer on the Etango heap leach pad
has been tendered and is being adjudicated. Bannerman has also issued the instruction to commence
manufacture of the High-Pressure Grinding Rolls (HPGR) tertiary crusher.
Negotiations on final supply contracts for both permanent water and power supply have progressed inline with requirements and are now at an advanced stage. Detailed design work on the Etango process
plant continues, as are procurement activities securing engineering details for key mechanical
equipment.
The Environmental Clearance Certificate (ECC) for the Etango ML was also recently renewed until 31
August 2027.
Financing
The Etango financing process sees Bannerman evaluating and progressing various funding sources,
including project/corporate debt as well as potential offtake and joint venture opportunities with
strategic counterparties who can add value to the Etango Project. As previously advised, Azure Capital
and Vermilion Partners (both global affiliates of French financial services institution, Natixis) are
advising on and assisting with the execution of the optimal funding mix for Etango.
Page 4 of 7
This process is progressing well and has been informed at every stage by Bannerman’s commitment
to establishing a highly robust financial base for the Etango Project. The final choice of funding mix will
be a direct function of the cost of various alternatives weighed against respective requisite levels of
offtake coverage (and key terms), covenants and security.
Bannerman’s recent equity raising is a strong enabler in delivering sufficient runway for the Company
to undertake a fulsome process, delivering the best opportunity to arrive at the optimal funding mix.
Offtake contracting
Bannerman’s product marketing strategy continues to be driven by a detailed understanding of utility
requirements and preferences. The Company continues to actively engage with a broad range of
utilities, financial institutions, traders, and other key market participants. This ongoing interaction
ensures a thorough understanding of term contracting dynamics, pricing mechanisms, and other
essential contractual terms and conditions.
It is readily observable that yellowcake term contract liquidity and pricing has continued to build
momentum in recent months, notwithstanding the retraction in spot yellowcake and uranium equities
pricing over the same period.
Bannerman’s well-established position with respect to offtake marketing is that it will preserve the longterm underlying value of Etango by only committing to contracting its planned uranium output on price
(and other terms) that are considered representative of long-term market fundamentals and producer
opportunity. Although the market is developing positively, current term contract conditions have not yet
fully aligned with these criteria.
A natural extension of Bannerman’s position to offtake contracting is the necessary degree of patience
required to maximising the leverage of Etango to long-term uranium market fundamentals. The
exercising of this patience means that Bannerman has elected to expand its projected window for a
targeted positive Final Investment Decision (FID) on Etango into 2025.
The Company is able to comfortably undertake such a strategy as a result of its recent equity raising
and robust cash balance. This enables ongoing execution of the ‘phased greenlight’ approach to
Etango development, whilst maintaining a watch-and-act approach to offtake contracting during this
period.
This ASX release was authorised on behalf of the Bannerman Board by:
Brandon Munro, Executive Chairman
25 September 2024
Contact
Investors:
Media:
Brandon Munro
Executive Chairman
T: +61 8 9831 1436
info@bmnenergy.com
Michael Vaughan
Fivemark Partners
T: +61 422 602 720
michael.vaughan@fivemark.com.au
Page 5 of 7
Important Notices
This announcement contains forward-looking statements which are identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’,
‘targets’, ‘expects’, or ‘intends’ and other similar words that involve risks and uncertainties. These statements are based on an
assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this announcement, are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of the Company, the Directors, and the management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking statements contained in this announcement will actually
occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Directors have no intention
to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new
information, future events or any other factors affect the information contained in this announcement, except where required by law or
the ASX listing rules. The information contained in this announcement does not constitute investment or financial product advice (nor
taxation, accounting, or legal advice), is not a recommendation to acquire Bannerman shares and is not intended to be used or relied
upon as the basis for making an investment decision. This announcement has been prepared without taking into account the investment
objectives, financial situation or needs of any individuals. Before making any investment decisions, prospective investors should
consider the appropriateness of the information having regard to their own investment objectives, financial situation and needs and
should seek legal, accounting and taxation advice appropriate to their jurisdiction. Bannerman is not licensed to provide investment or
financial product advice in respect of Bannerman shares.
Page 6 of 7
ABOUT BANNERMAN ENERGY (ASX:BMN, NSX:BMN, OTCQX:BNNLF)
Bannerman Energy Ltd is a uranium development business listed on the Australian and Namibian stock
exchanges and traded on the OTCQX Market in the US. Its flagship asset is the advanced Etango Uranium
Project located in the Erongo Region of Namibia.
Etango has benefited from extensive exploration and feasibility activity over the past 15 years. The Etango
tenement possesses a globally large-scale uranium mineral resource1. In December 2022, a Definitive
Feasibility Study (DFS)2 was completed on the Etango-8 Project, confirming to a definitive-level the strong
technical and economic viability of conventional open pit mining and heap leach processing of the Etango
deposit at 8Mtpa throughput (for average annual output of 3.5 Mlbs U3O8). In March 2024, a scoping study3
demonstrated the capacity to expand annual production to 6.7 Mlbs U3O8.
Etango’s advanced credentials are further highlighted by the construction and multi-year operation of the
Etango Heap Leach Demonstration Plant, which comprehensively de-risked the conventional acid heap
leach process to be utilised on the Etango ore. All environmental approvals have been received for the
proposed Etango mine and external mine infrastructure, based on a 12-year environmental baseline.
Bannerman was awarded the Mining Licence for Etango in December 2023 and is progressing all key project
workstreams towards a targeted positive Final Investment Decision (FID) in parallel with strengthening
uranium market fundamentals.
Namibia is a premier uranium investment jurisdiction, with a 45-year history of uranium production and
export, excellent infrastructure and support for uranium mining from both government and community. As
the world’s third largest producer of uranium, Namibia is an ideal development jurisdiction boasting political
stability, security, a strong rule of law and an assertive development agenda. The Bannerman team has
ample direct experience in the development, construction and operation of uranium projects in Namibia, as
well as extensive links into the downstream nuclear power industry.
Bannerman has long established itself as an Environmental, Social and Governance (ESG) leader in the
uranium and nuclear energy sector. It is also a leader within Namibia on social development and community
engagement and exercises best-practice governance in all aspects of its business. This was recently
recognised with receipt of the 2023 African Mining Indaba’s ESG Award for Community Engagement.
1 and 2. Refer to Bannerman’s ASX release dated 6 December 2022, Etango-8 Definitive Feasibility Study. Bannerman confirms that it is not aware of
any new information or data that materially affects the information included in that release. All material assumptions and technical parameters underpinning
the estimates in that ASX release continue to apply and have not materially changed.
3. Refer to Bannerman’s ASX release dated 18 March 2024, Etango-XP and Etango-XT Scoping Study.
Page 7 of 7