Demonstration Plant Phase 2 Success
Released
Released
Announcement PDF
STOCK EXCHANGE
ANNOUNCEMENT
23 November 2015
DEMONSTRATION PLANT PHASE 2 SUCCESS
Bannerman Resources Limited (ASX:BMN; TSX:BAN; NSX:BMN) is pleased to report further positive results
from Phase 2 of the Etango Heap Leach Demonstration Plant Program. The results continue to strongly
support the assumptions and projections incorporated in the Etango Definitive Feasibility Study (“DFS”)
and DFS Optimisation Study.
PHASE 2 HIGHLIGHTS
Fast and high leach extraction on a 60 tonne sample – within 20 days average total leach
extraction of 93% for the two cribs and 91% for the columns (compared to the DFS
projection for a scaled up heap of 87%).
Low sulphuric acid consumption – on average 15 kg/tonne (compared with the DFS
projection of 18 kg/tonne).
Material properties – visual observations during the unloading of the cribs again
confirmed uniform percolation through the material and integrity of the agglomerate.
Once again, no noticeable reduction in leach extraction performance was observed
between the larger scale cribs and the smaller columns – which increasingly indicates that
DFS scale-up factors could be conservative.
Capability building – growing metallurgical database that now reflects large scale testing
of 180 tonnes of material since commencement of the heap leach demonstration plant
program in April 2015.
Bannerman’s Chief Executive Officer, Len Jubber, said:
“The Etango heap leach demonstration plant program continues to strongly support the DFS (2012) and
DFS Optimisation Study (2015) assumptions. The team in Namibia has now done large scale testing on 180
tonnes of ore which substantially de-risks the planned utilisation of heap leaching at the Etango deposit.
We are excited by the results which point to additional potential to unlock further value in the Etango
Project.”
Len Jubber
Chief Executive Officer
23 November 2015
www.bannermanresources.com
BANNERMAN RESOURCES LIMITED ABN 34 113 017 128
Corporate Office Unit 1 ■ 2 Centro Avenue ■ Subiaco Western Australia 6008
Post PO Box 1973 ■ Subiaco Western Australia 6904 T +61 8 9381 1436 F +61 8 9381 1068
For further information please contact:
Len Jubber
Chief Executive Officer
Perth, Western Australia
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Robert Dalton
Financial Controller & Company Secretary
Perth, Western Australia
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Spyros Karellas
Investor Relations
Toronto, Ontario, Canada
Tel: +1 416 800 8921
spyros@pinnaclecapitalmarkets.ca
About Bannerman - Bannerman Resources Limited is an ASX, TSX and NSX listed exploration and development company with
uranium interests in Namibia, a southern African country which is a premier uranium mining jurisdiction. Bannerman’s principal
asset is its 80%-owned Etango Project situated near Rio Tinto’s Rössing uranium mine, Paladin’s Langer Heinrich uranium mine
and CGNPC’s Husab uranium mine currently under construction. A definitive feasibility study (dfs) and dfs optimisation study
has confirmed the technical, environmental and financial (at consensus long term uranium prices) viability of a large open pit
and heap leach operation at one of the world’s largest undeveloped uranium deposits. In 2015, Bannerman completed the dfs
optimisation study and is conducting a large scale heap leach demonstration program to provide further assurance to financing
parties, generate process information for the detailed engineering design phase and build and enhance internal capability.
More information is available on Bannerman’s website at www.bannermanresources.com.
Page 2 of 2
Etango Uranium Project
Heap Leach Demonstration Program
Phase 2 - November 2015
KEY OBSERVATIONS, RESULTS & PRELIMINARY CONCLUSIONS – Phase 2
1.
Demonstrating the design and projected performance reflected in the Definitive Feasibility Study (“DFS”)
Fast and high average leach extraction of 93% for the two cribs (compared to the DFS projection for a
scaled up heap of 86.9%) and 91% for the four columns within 20 days. Average sulphuric acid
consumption was 15kg/tonne (compared to the DFS projection of 17.6kg/tonne).
Visual observations during the unloading of the cribs again confirmed uniform percolation through the
material and integrity of the agglomerate.
Testing continues to confirm the simple chemistry and efficient leaching nature of the granite host rock
and uranium mineralisation.
2.
Further enhancing project knowledge
Improved the safe handling of the sulphuric acid by way of further reducing manual handling.
Platform scales installed under all of the pregnant liquor solution tanks to further enhance the
metallurgical accounting and hence process control ability.
The metallurgical database continues to grow dramatically with the further testing of 60 tonnes of ore in
the two cribs and 0.8 tonnes of material in the 4 column tests. The total sample tested in Phase 1 and
Phase 2 now amounts to approximately 182 tonnes.
3.
Pursuing value engineering
Rapid and uniform percolation, coupled with rapid and high leach extraction at a larger scale point
towards the potential to further optimise the heap leach configuration.
Surprisingly no noticeable reduction in leach extraction performance was observed between the larger
scale cribs and the smaller columns. This poses the question as to the appropriate scale up factors to be
used in the detailed engineering of the heap leach operation. Further work is required to address this
matter.
SUMMARY OF METALLURGICAL PERFORMANCE – Phase 2
Phase 2
Parameter
CRIB 5
Column
5A
Column
5B
CRIB 6
Column
6A
Column
6B
Sample Mass (dry tonnes)
30.3
0.184
0.184
30.3
0.179
0.176
Head Grade (ppm)
179.7
165.8
173.1
177.7
174.0
163.4
Tails Grade (ppm)
12.4
14.2
16.3
13.9
13.5
14.9
Uranium Extracted (%)
93.1
91.4
90.6
92.2
92.3
90.9
Acid Consumption (kg/t)
15.3
16.4
15.3
14.6
15.9
15.1
Page 2 of 8
INTRODUCTION
The Etango Project is one of the world’s largest undeveloped uranium deposits, located in the Erongo uranium mining
region of Namibia which hosts the Rössing and Langer Heinrich mines and the Husab Project which is currently under
construction by the Chinese stated owned enterprise, China General Nuclear Power Company (CGNPC). Etango is 73km
by road from Walvis Bay, one of southern Africa’s busiest deep water ports through which uranium has been exported
for over 35 years. Road, rail, electricity and water networks are all located nearby.
HISTORY OF FEASIBILITY STUDY
Bannerman completed a Definitive Feasibility Study (“DFS”) and Environmental and Social Impact Assessment (“ESIA”)
on the Etango Project in 2012. The respective studies, as announced to the market on 10 April 2012, confirmed the
technical, economic and environmental viability of the project at historical term uranium prices. In 2012 Bannerman
also received environmental approval for the Etango Project.
Bannerman announced on 8 April 2014 the progression to a heap leach demonstration plant program as an integral
step in progress towards the project’s detailed engineering and financing phases. The program is specifically aimed at:
Demonstrating the design and projected performance reflected in the DFS,
Further enhancing project knowledge, and
Pursuing value engineering.
On 22 September 2014 Bannerman announced award of the major contracts to construct and operate the Etango Heap
Leach Demonstration Plant. Activities at the site commenced in early October, with completion of the construction and
official opening on 24 March 2015. On 15 July 2015 Bannerman announced the successful commissioning of the
demonstration plant and the favourable results from Phase 1 of the program.
DEMONSTRATION PLANT PROGRAM
Phase
Objective(s)
Activities
Schedule
Completed in
June 2015
Quarter
1
Commissioning of Plant.
Commissioning
Validate leaching assumptions in
DFS.
Open cycle operation of all cribs and
columns.
Identify issues and correct plant and
operating procedures as required.
Operate 2 cribs and 4 columns.
Utilize same blended sample in both
cribs.
Demonstrate consistent operation of
plant.
Validate leaching assumptions in
DFS.
Simulate the heap leach pad cycle to
generate Pregnant Leach Solution
(PLS).
Operate three cribs in closed cycle.
Analyse the possible build-up of
deleterious elements.
Assess the possible impacts of the
build-up of deleterious elements
emanating from the recycling of
solution.
Generate and store sufficient PLS to
enable the validation of SX assumptions
in Phase 4.
4
Demonstrate the solvent extraction
process and assumptions in the DFS.
Solvent Extraction
& Value
Engineering
Operate SX plant in laboratory in
Swakopmund.
Conduct optimisation studies.
Primarily utilize 8 columns to evaluate
various opportunities to improve the
project economics.
5
Conduct optimisation studies
Primarily utilize 8 columns to evaluate
various opportunities to improve the
project economics.
2
Reproducibility
3
Solution Recycle
Value Engineering
Completed in
September
2015 Quarter
Underway in
December
2015 Quarter
March 2016
Quarter
June 2016
Quarter
Page 3 of 8
PLANT OVERVIEW
The photograph below shows the plant site from the north east. The plant is self-sufficient with respect to electricity
and operates on a continuous cycle. The cribs are able to be operated in open (i.e. individually) or closed cycle (i.e. in
series) circuit. The latter allows simulation of the full scale operation of heap leach pads, as defined in the DFS.
Acid leaching of agglomerated ore stacked to 5m occurs in four 2m x 2m x 6m leach cribs. In addition to the cribs, eight
5m high columns (as shown below) with an internal diameter of 0.185m enable parallel leaching. This arrangement
enables direct comparison of the leaching performance of the respective 200kg and 30 tonne samples, and hence an
assessment of the scale–up factors as well as the opportunity to conduct optimisation studies on smaller volumes.
The gates on the front of the cribs (as shown below) allow for the progressive stacking from the bottom up, instead of
dropping the material in at the top. Thereby simulating the practice envisaged in the full scale operation.
The original 3,000 tonne bulk sample (shown on the right below) was sourced from the northern end of the Etango ore
body (as shown on the left below).
Page 4 of 8
SUMMARY OF PHASE 2 OPERATIONS
Phase 2 entailed the open circuit heap leach operation of two cribs and four columns. The stacking procedure was
similar to that in Phase 1. After stacking, the cribs and columns were left to cure for 1 day, before initiating the leach
irrigation phase. This period was one third of that in Phase 1 as it was decided that due to the rapid percolation the
extra curing period was not required.
Leach solution was introduced at the top of each crib via dripper lines. The photograph on the right below shows
improved design in the dripper feed system to improve the irrigation consistency across the cribs.
Leach irrigation was conducted for 20 days followed by a post leach drain of 2 days and then a rinse and post rinse drain
phase of 3 days and 5 days respectively. A weak sulphuric acid solution (2g/l) was used as rinse solution.
Sampling and Unloading of Ripios from Cribs and Columns
At the completion of the post rinse drain phase, both cribs and their respective columns were as per Phase 1 again
carefully unloaded to enable taking samples for assaying of uranium and moisture. The location of these samples was
accurately recorded to enable developing three dimensional profiles of the leach performance. The information was
also used to determine the final extraction in each crib.
Integrity of the agglomerates (as shown on the right above) was again clearly evident during the unloading process and
no percolation issues were observed.
Page 5 of 8
Data collection and sampling
Monitoring of the solution inventory was conducted on a daily basis following the installation of larger solution tanks
and therefore holding capacity. The reduction in assaying frequency coupled with the introduction of platform scales
under the tanks improved the operational control of the plant and reduced the potential for human error in the
assaying process. Analytical services were provided by the Bureau Veritas laboratory in Swakopmund.
Head grade samples were taken during ore blending and quartering activities as well as during agglomeration phase as
ore was fed into the agglomeration drum. Agglomerate samples were taken during the agglomeration phase and ripios
(tails) samples during unloading of the cribs.
The assaying of solution and ore samples was also done by the Bureau Veritas laboratory in Swakopmund.
PHASE 2 METALLURGICAL PERFORMANCE
Leach Extraction
On average, approximately 85% uranium extraction was achieved by day 10 and over 90% by day 15 (refer graph
below). Leach irrigation was stopped at day 20 and the overall uranium extraction achieved after the drain, rinse and
post rinse drain phase was approximately 93% (compared with DFS projections for a scaled up heap of 86.9%). The
extraction curves for Crib 5 and 6 are similar in profile to that recoded during Phase 1 and that recorded in previous
column testing. The latter formed the basis of the DFS design of leach irrigation period of 32 days. This provides further
support to the preliminary observation that the initial scale-up interpretations were conservative, and that the leach
time may be shorter than predicted.
Page 6 of 8
Acid Consumption
The rate of acid consumption was similar with previous testing and averaged 15 kg/tonne for the four cribs (compared
with DFS projections of 17.6kg/t).
HEALTH, SAFETY & ENVIRONMENT
The photographs below show the attention to detail with regards to sample storage, general housekeeping and site
security at the demonstration plant site.
Page 7 of 8
TECHNICAL DISCLOSURES
Certain disclosures in this report, including management's assessment of Bannerman’s plans and projects, constitute forward looking statements that
are subject to numerous risks, uncertainties and other factors relating to Bannerman’s operation as a mineral development company that may cause
future results to differ materially from those expressed or implied in such forward-looking statements. Full descriptions of these risks can be found in
Bannerman’s various statutory reports, including its Annual Information Form available on the SEDAR website, sedar.com. Readers are cautioned not
to place undue reliance on forward-looking statements. Bannerman expressly disclaims any intention or obligation to update or revise any forwardlooking statements whether as a result of new information, future events or otherwise.
Mineral Resources that are not Ore Reserves do not have demonstrated economic viability.
Bannerman Resources Limited (“Bannerman”) manages its drilling and assaying activities in accordance with industry standard quality
assurance/quality control (QA/QC) procedures. Samples are collected by Bannerman personnel and prepared in accordance with specified
procedures at the relevant assay laboratories. Drill samples were analysed for uranium by the Bureau Veritas Laboratory in Swakopmund, Namibia.
Bureau Veritas is an International Laboratory Group with operations in 140 countries, including Ultratrace and Amdel in Australia. Assay QA/QC
involves the use of assay standards (sourced from African Mineral Standards (AMIS) in Johannesburg, made from Bannerman pulp rejects and crosschecked through umpire laboratories for which the round robin reports are available), field duplicates, blanks and barren quartz flushes. A third party
“umpire” laboratory (Genalysis in Perth) is used to cross-check and validate approximately 5% of the assay results in accordance with standard
procedures. Sample coarse rejects are retained and approximately 5% of samples are re-submitted for further assay verification. All sample pulps,
half-core and rock-chip samples are retained at Bannerman’s Goanikontes Warehouse Facility (GWS) on site.
The information in this report relating to the Ore Reserves of the Etango Project is based on information compiled or reviewed by Mr Leon Fouché.
Mr Fouché is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Fouché is employed by Bannerman Resources. Mr Fouché has
sufficient experience relevant to the style of mineralisation and types of deposits under consideration and to the activity which is being undertaken to
qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves”, and a Qualified Person as defined by Canadian National Instrument 43-101.
The information in this report that relates to Mineral Resources or Ore Reserves was prepared and first disclosed under the 2004 JORC Code. It has
not been updated since to comply with the 2012 JORC Code on the basis that the information has not materially changed since it was last reported.
All material assumptions and technical parameters underpinning the estimates of mineral resources continue to apply and have not materially
changed.
All material assumptions detailed in this report and underpinning the production target and forecast financial information in the DFS (as previously
announced on 10 April 2012 and reported on 30 January 2014 in compliance with Listing Rule 5.16 and 5.17) continue to apply and have not
materially changed.
Page 8 of 8