Heap Leach Demonstration Plant Strongly Supports Etango DFS
Released
Released
Announcement PDF
STOCK EXCHANGE
ANNOUNCEMENT
15 July 2015
HEAP LEACH DEMONSTRATION PLANT STRONGLY SUPPORTS ETANGO
DEFINITIVE FEASIBILITY STUDY
Bannerman Resources Limited (ASX:BMN; TSX:BAN; NSX:BMN) is pleased to report on the positive results
from Phase 1 of the Etango Heap Leach Demonstration Plant Program. The results strongly support the
assumptions and projections incorporated in the Etango Definitive Feasibility Study (“DFS”).
PHASE 1 HIGHLIGHTS
Fast and high leach extraction on a 121.6 tonne sample – within 20 days average total
leach extraction of 94% for the cribs (not previously conducted) and 93% for the columns
(similar to that achieved in previous laboratory testing).
Further enhanced project knowledge - designed, permitted, constructed and successfully
commissioned large scale demonstration plant.
Low sulphuric acid consumption – on average less than 16 kg/tonne (compared with DFS
projection of 18kg/tonne).
Geotechnical stability - visual observations during the unloading of the cribs confirmed
the uniform percolation through the material, integrity of the agglomerate and
geotechnical stability of the heap.
The similar performance of the four larger scale (30t sample) cribs to the eight (200kg
sample) columns may be an indication of potential upside related to the projection of the
previous column testing results to the full scale heap leach pad performance in the DFS.
Capability building – rapid growth in understanding of the process control and
metallurgical accounting associated with the specific characteristics of the Etango deposit
and design flowsheet.
The 18 – 24 month demonstration program, which commenced in April 2015, is an integral step of the
project’s detailed engineering and financing phases.
It is specifically aimed at demonstrating the design and projected performance reflected in the DFS,
further enhancing the project knowledge and pursuing value engineering. The results to date have already
gone a significant way towards achieving these objectives.
A comprehensive description of the Heap Leach Demonstration Plant Program and the Phase 1 results is
set out in the attachment to this release.
Bannerman’s Chief Executive Officer, Len Jubber, said:
“We could not have asked for a better start to the Etango heap leach demonstration plant program.
www.bannermanresources.com
BANNERMAN RESOURCES LIMITED ABN 34 113 017 128
Corporate Office Unit 1 ■ 2 Centro Avenue ■ Subiaco Western Australia 6008
Post PO Box 1973 ■ Subiaco Western Australia 6904 T +61 8 9381 1436 F +61 8 9381 1068
The scale and quality of the plant, which reflects significant consideration of the environment, has
surprised all of those who have visited the site. Moreover, the results from testing over 120 tonnes of ore
strongly support the definitive feasibility study. The team in Namibia has done a great job. It would be fair
to say that we are very excited about what we have seen to date and look forward to the next stages of the
program.
The location and set-up of the plant provides Bannerman with a real advantage with respect to the ease of
being able to conduct ongoing work to increase the metallurgical knowledge base and conduct further
value engineering.
The Etango Project continues to progress and remains one of the very few globally significant uranium
projects that can realistically be brought into production in the medium term. The Heap Leach
Demonstration Plant program further de-risks the Etango development path and will assist Bannerman
to attract JV / funding partners.”
Len Jubber
Chief Executive Officer
15 July 2015
For further information please contact:
Len Jubber
Chief Executive Officer
Perth, Western Australia
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Robert Dalton
Financial Controller & Company Secretary
Perth, Western Australia
Tel: +61 (8) 9381 1436
admin@bannermanresources.com.au
Spyros Karellas
Investor Relations
Toronto, Ontario, Canada
Tel: +1 416 800 8921
spyros@pinnaclecapitalmarkets.ca
About Bannerman - Bannerman Resources Limited is an ASX, TSX and NSX listed exploration and development company with
uranium interests in Namibia, a southern African country which is a premier uranium mining jurisdiction. Bannerman’s principal
asset is its 80%-owned Etango Project situated near Rio Tinto’s Rössing uranium mine, Paladin’s Langer Heinrich uranium mine
and CGNPC’s Husab uranium mine currently under construction. A definitive feasibility study has confirmed the technical,
environmental and financial (at consensus long term uranium prices) viability of a large open pit and heap leach operation at
one of the world’s largest undeveloped uranium deposits. In 2015, Bannerman is conducting a large scale heap leach
demonstration program to provide further assurance to financing parties, generate process information for the detailed
engineering design phase and build and enhance internal capability. More information is available on Bannerman’s website at
www.bannermanresources.com.
Page 2 of 2
Etango Uranium Project
Heap Leach Demonstration Program
Phase 1 - July 2015
CONTENTS
KEY OBSERVATIONS, RESULTS & PRELIMINARY CONCLUSIONS .....................................................................................3
SUMMARY OF METALLURGICAL PERFORMANCE ...........................................................................................................3
INTRODUCTION .............................................................................................................................................................4
PLANT LAYOUT ..............................................................................................................................................................6
PROCESS OVERVIEW ......................................................................................................................................................7
BULK SAMPLE ........................................................................................................................................................................... 7
COMMINUTION ......................................................................................................................................................................... 8
ORE SAMPLE PREPARATION ......................................................................................................................................................... 9
ORE AGGLOMERATION ............................................................................................................................................................. 10
ORE STACKING AND COLUMN LOADING ....................................................................................................................................... 11
SOLUTION IRRIGATION AND DRAIN .............................................................................................................................................. 11
SAMPLING AND UNLOADING OF RIPIOS FROM CRIBS AND COLUMNS .................................................................................................. 13
DATA COLLECTION AND SAMPLING ............................................................................................................................. 14
LEACH PERFORMANCE ................................................................................................................................................. 14
URANIUM EXTRACTION ............................................................................................................................................................. 14
ACID CONSUMPTION ................................................................................................................................................................ 16
ENVIRONMENTAL MANAGEMENT ............................................................................................................................... 17
TECHNICAL DISCLOSURES ............................................................................................................................................ 18
Page 2 of 18
KEY OBSERVATIONS, RESULTS & PRELIMINARY CONCLUSIONS
1.
2.
3.
Demonstrating the design and projected performance reflected in the Definitive Feasibility Study (“DFS”)
Fast and high average leach extraction of 94% for the cribs and 93% for the columns, within 20 days. The
column results were similar to that obtained in previous laboratory testing but the crib results were better
than anticipated (refer second bullet point under heading “3. Pursuing Value Engineering” below).
Average sulphuric acid consumption approximately 16 kg/tonne (compared with DFS projection of
18kg/tonne).
Visual observations during the unloading of the cribs confirmed uniform percolation through the material,
integrity of the agglomerate and geotechnical stability of the heap.
Testing confirms the simple chemistry and efficient leaching nature of the granite host rock and uranium
mineralisation.
Further enhancing project knowledge
Designed, permitted, constructed and successfully commissioned large scale demonstration plant.
Gaining operating experience including safe handling of sulphuric acid, etc.
Building an understanding of the process control and metallurgical accounting issues associated with the
specific characteristics of the Etango deposit and design flowsheet.
Dramatically increased the metallurgical database through testing of 120 tonnes of ore in 4 separate crib
tests and 1.6 tonnes of material in 8 column tests.
Pursuing value engineering
Rapid and uniform percolation without signs of flooding, coupled with rapid and high leach extraction at a
larger scale point towards the potential to further optimise the heap leach configuration.
Surprisingly no noticeable reduction in leach extraction performance was observed between the larger
scale cribs and the smaller columns. This poses the question as to the appropriate scale up factors to be
used in the detailed engineering of the heap leach operation. Further work is required to address this
matter.
SUMMARY OF METALLURGICAL PERFORMANCE
Columns
Parameter
Units
CRIB 1
Columns
CRIB 2
1A
1B
Columns
CRIB 3
2A
2B
Columns
CRIB 4
3A
3B
4A
4B
Sample Mass
(t)
29.5
0.2
0.2
30.1
0.2
0.2
30.7
0.2
0.2
30.2
0.2
0.2
Head Grade
(ppm)
207
207
207
195
195
195
193
193
193
195
195
195
Contained U3O8
(kg)
6.12
0.04
0.04
5.88
0.04
0.04
5.93
0.04
0.04
5.88
0.04
0.04
Tails Grade
(ppm)
11.8
13.4
14.2
10.7
12.7
12.2
12.9
13.4
12.9
11.6
14.4
14.7
U3O8 in Tails
(kg)
0.35
0.002
0.003
0.321
0.002
0.002
0.40
0.003
0.002
0.35
0.003
0.003
Uranium Extracted
(%)
94.3
93.5
93.2
94.5
93.5
93.8
93.3
93.0
93.3
94.1
92.6
92.4
Page 3 of 18
INTRODUCTION
The Etango Project is one of the world’s largest undeveloped uranium deposits, located in the Erongo uranium mining
region of Namibia which hosts the Rössing and Langer Heinrich mines and the Husab Project which is currently under
construction by the Chinese stated owned enterprise, China General Nuclear Power Company (CGNPC). Etango is 73km
by road from Walvis Bay, one of southern Africa’s busiest deep water ports through which uranium has been exported
for over 35 years. Road, rail, electricity and water networks are all located nearby.
Bannerman completed a Definitive Feasibility Study (“DFS”) and Environmental and Social Impact Assessment (“ESIA”)
on the Etango Project in 2012. The respective studies, as announced to the market on 10 April 2012, confirmed the
technical, economic and environmental viability of the project at historical term uranium prices. In 2012 Bannerman
also received environmental approval for the Etango Project.
[All material assumptions detailed in this report and underpinning the production target and forecast financial information in the DFS (as previously
announced on 10 April 2012 and reported on 30 January 2014 in compliance with Listing Rule 5.16 and 5.17) continue to apply and have not
materially changed.]
Definitive Feasibility Study
Key outcomes from the DFS are as follows:
2004 JORC Code and NI 43-101 compliant Ore Reserves (at 100ppm cut-off) totalling 279.6 million
tonnes at an average grade of 194ppm U3O8 for 119.3 Mlbs of contained U3O8;
Production of 7-9 Mlbs U3O8 per year for the first five years and 6-8 Mlbs U3O8 per year thereafter,
based on an average processing throughput of 20 Mt per annum and an average recovery rate of
86.9%, which would rank Etango as a global top 10 uranium only mine;
Cash operating costs of US$41/lb U3O8 in the first 5 years and US$46/lb U3O8 over the life of mine;
At a uranium price of US$75/lb U3O8, the Etango Project generates operating cash flow of
US$2.7 billion before capital and tax, and free cash flow of US$923 million after capital and tax,
Page 4 of 18
based on 104Mlbs U3O8 life of mine production;
Pre-production capital cost of US$870 million; and
Minimum mine life of 16 years, with further extensions possible through the inclusion of measured
and indicated resources below the designed pit, and the conversion of existing inferred resources.
Bannerman announced on 8 April 2014 the progression to a heap leach demonstration plant program as an integral
step in progress towards the project’s detailed engineering and financing phases. The program is specifically aimed at:
Demonstrating the design and projected performance reflected in the DFS,
Further enhancing project knowledge, and
Pursuing value engineering.
On 22 September 2014 Bannerman announced award of the major contracts to construct and operate the Etango Heap
Leach Demonstration Plant. Activities at the site commenced in early October, with completion of the construction and
official opening on 24 March 2015.
The demonstration program schedule and objectives are summarised in the Table below:
Phase
Objective(s)
Activities
1
Commissioning of Plant.
Open cycle operation of all cribs and June
2015
columns.
Quarter
Commissioning
Schedule
Validate leaching assumptions
in DFS.
Identify issues and correct plant and
operating procedures as required.
2
Heap Leaching
Demonstrate
operation of plant.
consistent Operate 2 cribs and 4 columns.
September
2015 Quarter
Utilize same blended sample in both cribs.
Validate leaching assumptions
in DFS.
3
Solution Recycle
Simulate the heap leach pad Operate three cribs in closed cycle.
December
cycle to generate Pregnant
2015 Quarter
Leach Solution (PLS).
Analyse the possible build-up of deleterious
elements.
Assess the possible impacts of
the build-up of deleterious
Generate and store sufficient PLS to enable
elements emanating from the
the validation of SX assumptions in Phase 4.
recycling of solution.
4
Demonstrate
the
solvent Operate SX plant in laboratory in March 2016
extraction
process
and Swakopmund.
Quarter
Solvent Extraction
assumptions
in
the
DFS.
&
Value
Engineering
Primarily utilize 8 columns to evaluate
5
Value Engineering
Conduct optimisation studies.
various opportunities to improve the project
economics.
Conduct optimisation studies
Primarily utilize 8 columns to evaluate June
2016
various opportunities to improve the project Quarter
economics.
Page 5 of 18
PLANT LAYOUT
The layout design of the Demonstration Plant took advantage of a historical exploration camp and the topography of
the area. The flowsheet resembles the front end of the processing plant up to the heap leaching stage. Provisions have
been made to install either a pulsed column or mixer settler unit to demonstrate the solvent extraction component of
the flowsheet, in due course.
The photograph below shows the plant site from the north east. The plant is self-sufficient with respect to electricity
and operates on a continuous cycle. The cribs are able to be operated in open (i.e. individually) or closed loop (i.e. in
series) circuit. The latter allows simulation of the full scale operation of heap leach pads.
Acid leaching of agglomerated ore stacked to 5m occurs in four 2m x 2m x 6m leach cribs. In addition to the cribs, eight
5m high columns with an internal diameter of 0.185m enable parallel leaching. This arrangement enables direct
comparison of the leaching performance of the respective 200kg and 30 tonne samples, and hence an assessment of
the scale–up factors as well as the opportunity to conduct optimisation studies on smaller volumes. The setup of the
cribs and the columns is shown in the photographs below.
Page 6 of 18
The series of gates on the front of the cribs allow for the progressive stacking from the bottom up, instead of dropping
the material in at the top. This practice simulates the vertical drop of the stacking procedure envisaged during full scale
operation.
PROCESS OVERVIEW
Bulk Sample
The 3,000 tonne bulk sample was sourced from the northern end of the Etango ore body as shown in the photograph
below. This area was selected because the ore grade was representative of the Etango ore body and the cost of
excavation was low due to it outcropping. The clean ore allows for controlled blending with waste material to achieve
the specified dilution.
Page 7 of 18
Comminution
Blasting
The 12m by 21m area was blasted on a 2m x 2m pattern with 5m deep drill holes. The blasted material shown below
highlights the clean nature of the granite (alaskite) hosted ore.
Crushing & Grinding
The blasted material was transported 2 km to the plant site. The bulk sample was crushed using conventional primary
and secondary crushing equipment to generate ore with P100 of <22mm. This product was then tertiary crushed using
a High Pressure Grinding Roll (HPGR) unit to generate the DFS product with a target P80 of 5.3mm.
Page 8 of 18
Over and above generating material similar to that specified in the DFS, two other samples were generated to enable
future value engineering studies. These were coarser HPGR and conventional crushed material. Waste material (Gneiss
rock) to be used for ore dilution purposes was crushed in a similar manner. The ore and waste stockpiles generated are
shown in the photograph below.
Ore Sample Preparation
In Phase 1 the ore sample was diluted by 10% with Gneiss rock sourced from the planned pit area to generate a
blended sample representative of the projected run of mine orefeed. Ore blending was conducted with the aid of a
Quarter Splitter and a Front End Loader as shown below. The Quarter Splitter was used to prepare a uniform sample for
each of the four cribs and eight columns.
Quarter Splitter with
3m x 3m Hopper
Page 9 of 18
The material in the four cribs had a P80 of between 3 and 4 mm by comparison to the DFS specification of P80 < 5.3
mm.
Ore Agglomeration
The ore was fed into the agglomeration drum via conveyor at a controlled feed rate, and agglomerated through adding
sulphuric acid, a polymer binder and water to produce agglomerated ore with properties as per DFS specifications.
Agglomerate samples were taken from the stacking conveyor on an hourly basis and analysed for moisture content.
The photographs below show the agglomerated ore at approximately 10 - 12% moisture content.
Page 10 of 18
Ore Stacking and Column Loading
Crib stacking and column loading occurred concurrently with the agglomeration process using a conveyor. To minimise
compaction and segregation in the cribs, a drop height of one meter from the head of the conveyor was maintained
throughout.
The agglomerated ore used in the two parallel columns per crib was collected on an hourly basis from the conveyor
stacking the crib concerned and then loaded into the columns using a sample bag. Care was taken to maintain the one
meter drop height whilst loading the columns.
The cribs and columns were pre-loaded with a 350 mm layer of drainage material to serve as a filter for the solution
collection during irrigation.
After stacking, the cribs and columns were left to cure for 3 days, before initiating the leach irrigation phase.
Solution Irrigation and Drain
Phase 1 entailed the open circuit heap leach operation of all four cribs and eight columns. Each crib was fed from a
separate Irrigation Feed Tank located in the reagent mixing area as shown in the photograph below. The leach solution
comprising of 16 - 17 g/l of Sulphuric acid and 3 g/l Ferric was prepared in the Reagent Mixing Tank and then
transferred to the respective feed tanks.
Page 11 of 18
98% Sulphuric
Acid15T ISO
Tanker
Ferric Sulphate
IBCs
Reagent Mix
Tank
Irrigation Feed Tanks
2
Leach solution was introduced at the top of each crib via dripper lines at a constant irrigation rate of 15 L/m /hr. The
photographs below show the even solution distribution as observed at the start of and during irrigation of a crib.
Page 12 of 18
Leach irrigation was conducted for 20 days followed by a post leach drain of 2 days and then a rinse and post rinse
phase of 3 days and 5 days respectively. A weak sulphuric acid solution (2 g/l) was used as rinse solution.
Sampling and Unloading of Ripios from Cribs and Columns
At the completion of the post rinse phase, all four cribs and their respective columns were carefully unloaded in a
manner which enabled taking samples for assaying of uranium, moisture and size distribution. The location of these
samples was accurately recorded to enable developing three dimensional profiles of the leach performance. The
information was also used to determine the final extraction in each crib.
In Crib 1, a total of nine core samples were obtained for each vertical meter segment using a 1 meter pipe with an
internal diameter of 110mm sampling grid designed to ensure consistent sampling throughout the crib.
Ore was carefully removed in one meter intervals using hand shovels and weighed to confirm the stacked tonnes. The
samples were also analysed for moisture content to determine the dry stacked tonnage in each crib. The photographs
below illustrate the unloading process and sampling methodology.
Page 13 of 18
Heap stability and the integrity of the agglomerates were clearly evident during unloading process. As expected slight
segregation of ore due to the stacking was observed at each meter segment, with the finer content located in the
centre as shown in the photograph below. However no percolation issues were observed.
Finer
Coarser
Coarser
DATA COLLECTION AND SAMPLING
Monitoring of the solution inventory was done every 2 hours and solution samples were taken during the leach, drain
and rinse phases of the operation to monitor uranium and reagent concentrations in the various streams. Analytical
services were provided by the Bureau Veritas laboratory in Swakopmund.
Head grade samples were taken during ore blending and quartering activities, agglomerate samples during the
agglomeration phase and ripios (tails) samples during unloading of the cribs.
The assaying of solution and ore samples was also done by the Bureau Veritas laboratory in Swakopmund.
LEACH PERFORMANCE
Uranium Extraction
As referred to earlier in the report, the leach performance was assessed through monitoring the solution in- and
outputs during the leaching process and assaying the ripios post completion of the leach cycle.
The methodical sampling of the ripios material enabled gaining an understanding of the three dimensional profile of
percolation, extraction and segregation through the 2m x 2m x 5m crib samples.
The schematic diagram below shows the ripios grade, leach extraction and moisture content in each of the 45 samples
taken from Crib 1. Each quadrant of 9 blocks represents one vertical meter. The 9 x 5 matrix of information presents an
important insight to the leach process through the 2m x 2m x 5m crib and will be further analysed to enable optimising
the heap leach design.
Page 14 of 18
The highest sample extraction achieved was 97% and the lowest was 87%. The average overall uranium extraction for
Crib 1 was 94.3%.
Ripios Grade (ppm U3O8)
Row
Row
Row
Door
1
2
3
6.5
7.6
13.2
Uranium Extraction (%)
Row
Row
Row
Door
1
2
3
97
96
94
1m
1m
2m
3m
4m
5m
9
8.6
9.2
8.4
7.9
11.6
14.6
8.6
8.5
8.3
9.1
10.5
7
9.9
9.6
Door
Moisture (%)
Row
Row
1
2
6.2
6.3
Row
3
6.7
1m
6.6
5.50
6.1
5.7
6.6
5.2
7.0
6.6
6.6
6.5
6.7
6.1
96
96
96
96
96
94
93
96
96
96
96
95
16.2
97
95
92
6.5
6.5
4.8
10.4
14.9
95
95
93
7.1
6.5
6.6
8.6
10.6
9.1
96
95
96
7.1
6.6
6.9
8.3
11.9
26.5
96
94
87
7.1
6.4
5.2
11.9
11.2
20.6
94
95
90
7.2
6.8
7.1
9.8
12.7
11.6
95
94
94
7.0
6.7
6.5
2m
3m
4m
2m
3m
4m
9
13.8
21.1
96
93
90
7.3
6.4
5.3
14.9
11.1
22.3
93
95
89
8.1
8.4
7.8
11.3
11.4
13.3
95
94
94
8.3
8.4
8.3
9.9
12.6
17.5
95
94
92
8.2
8.1
7.0
5m
5m
On average, approximately 85% uranium extraction was achieved by day 10 and over 90% by day 15 (refer graph
below). Leach irrigation was stopped at day 20 and the overall uranium extraction achieved after the drain, rinse and
post rinse phase was approximately 94%. The extraction curves for the larger scale cribs are similar in profile to that for
the previous column testing, from which the DFS design of 32 days was interpreted. Hence it may indicate that initial
scale-up interpretations were conservative, and that the leach time may be shorter than predicted.
Uranium Extraction
100%
90%
Uranium Extraction (%)
80%
Post Leach
Drain
70%
60%
Rinse
50%
Post Rinse
Drain
40%
30%
20%
Unloading
10%
0%
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Days
CRIB 1: % U Extraction
CRIB 2: % U Extraction
CRIB 3: % U Extraction
CRIB 4 % U Extraction
Page 15 of 18
Acid Consumption
The rate of acid consumption was consistent with previous testing (black dotted line) and averaged approximately 16
kg/tonne for the four cribs (compared with DFS projections of 18kg/t) .
Acid Consumption for Cribs relative to Previous 7m Column Test
Acid Consumption (kg/tonne)
25
20
15
10
5
0
Days
CRIB 1: Acid Consumption (kg/tonne)
CRIB 3: Acid Consumption (kg/tonne)
ALS-A12889 (7m) - Acid Consumption (kg/tonne)
CRIB 2: Acid Consumption (kg/tonne)
CRIB 4: Acid Consumption (kg/tonne)
IN SUMMARY
The results from the larger scale cribs match those from the parallel columns and earlier laboratory testing and strongly
support the assumptions and projections incorporated in the Etango Definitive Feasibility Study (“DFS”).
Phase 1 highlights included:
Fast and high leach recovery – within 20 days average overall recovery of 94% for the cribs and 93% for the
columns.
Low sulphuric acid consumption – averaged approximately 16 kg/tonne (compared with DFS projection of
18kg/tonne).
Geotechnical stability - visual observations during the unloading of the cribs confirmed the uniform
percolation through the material, integrity of the agglomerate and geotechnical stability of the heap.
The similar performance of the larger scale (30t sample) cribs to the (200kg sample) columns may be an
indication of potential upside related to the projection of the previous column testing results to the full scale
heap leach performance parameters in the DFS. More work is required in this regard.
Capability building – rapid growth in understanding of the process control and metallurgical accounting
associated with the specific characteristics of the Etango deposit and design flowsheet.
Page 16 of 18
ENVIRONMENTAL MANAGEMENT
The area from where the ore
sample was sourced has been
rehabilitated.
Tarpaulins placed on all the
stockpiles to both protect the
samples and minimise dust
generation.
Double
lined
solution
evaporation ponds with leak
detection.
Page 17 of 18
TECHNICAL DISCLOSURES
Certain disclosures in this report, including management's assessment of Bannerman’s plans and projects, constitute forward looking statements that
are subject to numerous risks, uncertainties and other factors relating to Bannerman’s operation as a mineral development company that may cause
future results to differ materially from those expressed or implied in such forward-looking statements. Full descriptions of these risks can be found in
Bannerman’s various statutory reports, including its Annual Information Form available on the SEDAR website, sedar.com. Readers are cautioned not
to place undue reliance on forward-looking statements. Bannerman expressly disclaims any intention or obligation to update or revise any forwardlooking statements whether as a result of new information, future events or otherwise.
Mineral Resources that are not Ore Reserves do not have demonstrated economic viability.
Bannerman Resources Limited (“Bannerman”) manages its drilling and assaying activities in accordance with industry standard quality
assurance/quality control (QA/QC) procedures.
Samples are collected by Bannerman personnel and prepared in accordance with specified
procedures at the relevant assay laboratories. Drill samples were analysed for uranium by the Bureau Veritas Laboratory in Swakopmund, Namibia.
Bureau Veritas is an International Laboratory Group with operations in 140 countries, including Ultratrace and Amdel in Australia. Assay QA/QC
involves the use of assay standards (sourced from African Mineral Standards (AMIS) in Johannesburg, made from Bannerman pulp rejects and crosschecked through umpire laboratories for which the round robin reports are available), field duplicates, blanks and barren quartz flushes. A third party
“umpire” laboratory (Genalysis in Perth) is used to cross-check and validate approximately 5% of the assay results in accordance with standard
procedures. Sample coarse rejects are retained and approximately 5% of samples are re-submitted for further assay verification. All sample pulps,
half-core and rock-chip samples are retained at Bannerman’s Goanikontes Warehouse Facility (GWS) on site.
The inform